by JAGDAMBA ENTERPRISES AND CONSTRUCTION · KOLWADi, Pune 412207Registered on MahaRERA as “SAI VILLA”

What’s in the report? →

Possession date of Jagdamba Sai Villa (MahaRERA P52100014320): 30 December 2022, moved from 31 January 2019 (47 months later), and it has already passed. It has 23 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100014320. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100014320, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2022) has passed.

What do you want to know about Jagdamba Sai Villa?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Jagdamba Sai Villa has moved

  1. 31 January 2019

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT52100008406)

    Reason the builder gave MahaRERA: “aaa”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52100008871)

    Reason the builder gave MahaRERA: “DEVELOPMENT WORK”
  4. 30 December 2022

    Revised completion date on MahaRERA

Source: Jagdamba Sai Villa’s extension records on MahaRERA (P52100014320), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Jagdamba Sai Villa

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100014320
Status
Lapsed (registration period ended)
Builder
JAGDAMBA ENTERPRISES AND CONSTRUCTION
Location
KOLWADi, Pune · 412207
Project type
Residential / Group Housing
Registered on
23 Nov 2017
Completion date at registration
January 2019
Latest completion date
December 2022
Delay so far
47 months
Homes
23
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Jagdamba Sai Villa, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI VILLA100%100%60%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jagdamba Sai Villa every 1–2 months.

Jagdamba Sai Villa: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI VILLA (5 floors)
  • Land: 406 sq m (about 0.1 acres) · recreational space 406 sq m
  • Land, as filed: 210
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Jagdamba Sai Villa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Jagdamba Sai Villa: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Jagdamba Sai Villa

What is the possession date of Jagdamba Sai Villa?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Jagdamba Sai Villa in KOLWADi, Pune is 30 December 2022 — 47 months later than 31 January 2019, the date given at registration. That date has already passed.

The date has already moved 47 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Jagdamba Sai Villa?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Jagdamba Sai Villa's builder has filed on MahaRERA, the official one, is 30 December 2022, already 47 months later than the 31 January 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Jagdamba Sai Villa extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2020, giving the reason "aaa"; to 30 June 2022, giving the reason "DEVELOPMENT WORK".

What is the RERA number of Jagdamba Sai Villa?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Jagdamba Sai Villa in KOLWADi, Pune is P52100014320.

Is Jagdamba Sai Villa registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa is registered as P52100014320 and its status is "Lapsed (registration period ended)".

What is the current construction status of Jagdamba Sai Villa? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI VILLA is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Jagdamba Sai Villa have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Jagdamba Sai Villa safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa is registered on MahaRERA as P52100014320, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 47 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Jagdamba Sai Villa?

Jagdamba Sai Villa isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Jagdamba Sai Villa?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Jagdamba Sai Villa: gharkundli.com/tools/property-cost-calculator

Has Jagdamba Sai Villa received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Jagdamba Sai Villa?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Jagdamba Sai Villa uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Jagdamba Sai Villa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Jagdamba Sai Villa's possession date changes?

The latest dates are on Jagdamba Sai Villa's MahaRERA page (P52100014320). GharKundli's Kundli Watch sends a free WhatsApp update on Jagdamba Sai Villa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Jagdamba Sai Villa have?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa has one building filed: SAI VILLA with 5 floors.

How big is the land of Jagdamba Sai Villa?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa stands on 406 sq m of land (about 0.1 acres) and 406 sq m of recreational open space.

What are the reviews of Jagdamba Sai Villa?

Google Maps has reviews of Jagdamba Sai Villa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Jagdamba Sai Villa?

Jagdamba Sai Villa by JAGDAMBA ENTERPRISES AND CONSTRUCTION is in KOLWADi, Pune, pincode 412207, Maharashtra, and is registered on MahaRERA as P52100014320, per GharKundli's check of MahaRERA records. Its land is filed as 210. GharKundli lists all 379 MahaRERA projects in Wagholi (412207).

How many flats are in Jagdamba Sai Villa?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa has 23 homes in 1 tower registered on MahaRERA.

When was Jagdamba Sai Villa registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Jagdamba Sai Villa was registered on MahaRERA on 23 November 2017. GharKundli did not find a title report on the land on file there.

Does Jagdamba Sai Villa have any legal issues or court cases?

No court cases are listed for Jagdamba Sai Villa on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Jagdamba Sai Villa?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JAGDAMBA ENTERPRISES AND CONSTRUCTION.

Other projects in Haveli

All 379 projects in Wagholi (412207) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.