Gokhale Shashi Madhav

by Gokhale Constructions · Bavdhan Khurd, Pune 411021Also near Shivaji Nagar, Sadashiv Peth, Sus GaonRegistered on MahaRERA as “Shashi Madhav”

What’s in the report? →

Possession: Gokhale Shashi Madhav (MahaRERA P52100015131) is marked completed on MahaRERA. It has 16 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100015131. Status: Completed.

Source: MahaRERA website — records for P52100015131, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Gokhale Shashi Madhav?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Gokhale Shashi Madhav has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 31 July 2020

    Extended at the builder's request (MahaRERA application EXT52100005315)

    Reason the builder gave MahaRERA: ““We have completed the RCC work, Brick work, flooring and plumbing work on the said property, however, the finishing work is going on at site””
  3. 31 January 2021

    Revised completion date on MahaRERA

Source: Gokhale Shashi Madhav’s extension records on MahaRERA (P52100015131), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gokhale Shashi Madhav

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100015131
Status
Completed
Builder
Gokhale Constructions
Location
Bavdhan Khurd, Pune · 411021
Project type
Residential / Group Housing
Registered on
31 Jan 2018
Completion date at registration
December 2019
Latest completion date
January 2021
Delay so far
13 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
14

Construction progress of Gokhale Shashi Madhav, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHASHI MADHAV100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gokhale Shashi Madhav every 1–2 months.

Gokhale Shashi Madhav: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Gokhale Constructions has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 13 months). No complaints on MahaRERA.

Read Google reviews of Gokhale Shashi Madhav →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gokhale Shashi Madhav: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Gokhale Shashi Madhav

What is the possession date of Gokhale Shashi Madhav?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Gokhale Shashi Madhav in Bavdhan Khurd, Pune is 31 January 2021 — 13 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Gokhale Shashi Madhav?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gokhale Shashi Madhav's builder has filed on MahaRERA, the official one, is 31 January 2021, already 13 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Gokhale Shashi Madhav extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav's builder applied to MahaRERA to extend the completion date once: to 31 July 2020, giving the reason "“We have completed the RCC work, Brick work, flooring and plumbing work on the said property, however, the finishing work is going on at site”".

What is the RERA number of Gokhale Shashi Madhav?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Gokhale Shashi Madhav in Bavdhan Khurd, Pune is P52100015131.

Is Gokhale Shashi Madhav registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav is registered as P52100015131 and its status is "Completed".

What is the current construction status of Gokhale Shashi Madhav? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav's status on MahaRERA is "Completed". As filed by the builder, slab work on SHASHI MADHAV is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Gokhale Shashi Madhav have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Gokhale Shashi Madhav safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav is registered on MahaRERA as P52100015131, its MahaRERA status is "Completed", its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Gokhale Shashi Madhav?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Gokhale Shashi Madhav?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Gokhale Shashi Madhav: gharkundli.com/tools/property-cost-calculator

Has Gokhale Shashi Madhav received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Gokhale Shashi Madhav completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav is marked completed on MahaRERA, and the completion date filed there is 31 January 2021. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Gokhale Shashi Madhav uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Gokhale Shashi Madhav was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Gokhale Shashi Madhav's possession date changes?

The latest dates are on Gokhale Shashi Madhav's MahaRERA page (P52100015131). GharKundli's Kundli Watch sends a free WhatsApp update on Gokhale Shashi Madhav every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gokhale Shashi Madhav have?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav has one building filed: SHASHI MADHAV with 8 floors.

How big is the land of Gokhale Shashi Madhav?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav stands on 638 sq m of land (about 0.2 acres), with 1,434 sq m of sanctioned built-up area.

What is the track record of Gokhale Shashi Madhav's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Constructions has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 13 months). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Gokhale Shashi Madhav?

Google Maps has reviews of Gokhale Shashi Madhav written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Gokhale Shashi Madhav?

Gokhale Shashi Madhav by Gokhale Constructions is in Bavdhan Khurd, Pune, pincode 411021 (near Shivaji Nagar, Sadashiv Peth, Sus Gaon), Maharashtra, and is registered on MahaRERA as P52100015131, per GharKundli's check of MahaRERA records. Its land is filed as Plot No ch old plot no. 14. GharKundli lists all 332 MahaRERA projects in Armament (411021).

How many flats are in Gokhale Shashi Madhav?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav has 16 homes in 1 tower registered on MahaRERA.

When was Gokhale Shashi Madhav registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Shashi Madhav was registered on MahaRERA on 31 January 2018. GharKundli did not find a title report on the land on file there.

Does Gokhale Shashi Madhav have any legal issues or court cases?

No court cases are listed for Gokhale Shashi Madhav on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Gokhale Shashi Madhav?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Gokhale Constructions, which has 14 other projects registered on MahaRERA.

Other projects in Armament (411021)

All 332 projects in Armament (411021) →

Other projects by Gokhale Constructions

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.