Possession date of RG-C,D: 30 April 2027, moved from 15 June 2019 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000003657. Status: In abeyance (on hold by MahaRERA). Its completion date has moved from June 2019 to April 2027: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
Sales frozen by MahaRERA: shared bank account
MahaRERA has put this project in abeyance because it uses one bank account with another project (P99000003885), where each project must have its own. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about RG-C,D?
How the possession date of RG-C,D has moved
15 June 2019
Completion date given when the project was registered
14 June 2020
Extended at the builder's request (MahaRERA application EXT99000002526)
Reason the builder gave MahaRERA: “Delay in loading TDR for further development...”
31 December 2026
Extended at the builder's request (MahaRERA application EXT99000011664)
Reason the builder gave MahaRERA: “Delay in Commencement Certificate and due to which only 24 flats sold out of 124”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RG-C,D’s extension records on MahaRERA (P99000003657), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RG-C,D
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000003657
- Status
- In abeyance (on hold by MahaRERA)
- Builder
- RELIABLE REALTOUCH
- Location
- vasai east, Palghar · 401208
- Project type
- Others
- Registered on
- 6 Aug 2017
- Completion date at registration
- June 2019
- Latest completion date
- April 2027
- Delay so far
- 90 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 124
- Sold or booked
- 19%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of RG-C,D, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C WING | 100% | 10% | 0% | 0% |
| D WING | 100% | 10% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- C WING: covers 11 floors
- D WING: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RG-C,D every month.
RG-C,D: buildings, flats and land, as filed on MahaRERA
- Buildings: C WING (11 floors, 71 units) · D WING (11 floors, 53 units)
- Land: 1,677 sq m (about 0.4 acres) · sanctioned built-up 384 sq m · recreational space 1,022 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RG-C,D →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RG-C,D: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RG-C,D
What is the possession date of RG-C,D?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RG-C,D in vasai east, Palghar is 30 April 2027 — 90 months later than 15 June 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RG-C,D?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RG-C,D's builder has filed on MahaRERA, the official one, is 30 April 2027, already 90 months later than the 15 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RG-C,D extended?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D's builder applied to MahaRERA to extend the completion date 2 times: to 14 June 2020, giving the reason "Delay in loading TDR for further development..."; to 31 December 2026, giving the reason "Delay in Commencement Certificate and due to which only 24 flats sold out of 124". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RG-C,D?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RG-C,D in vasai east, Palghar is P99000003657.
Is RG-C,D registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D is registered as P99000003657 and its status is "In abeyance (on hold by MahaRERA)". On MahaRERA's own list: Sales frozen by MahaRERA: shared bank account. MahaRERA has put this project in abeyance because it uses one bank account with another project (P99000003885), where each project must have its own. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
What is the construction status of RG-C,D?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work is 10% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does RG-C,D have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RG-C,D safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D is registered on MahaRERA as P99000003657, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has moved 90 months since registration, 1 complaint is listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: shared bank account". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RG-C,D's possession date changes?
The latest dates are on RG-C,D's MahaRERA page (P99000003657). GharKundli's Kundli Watch sends a free WhatsApp update on RG-C,D every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RG-C,D have?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D has 2 buildings filed: C WING with 11 floors and 71 units; D WING with 11 floors and 53 units.
How big is the land of RG-C,D?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D stands on 1,677 sq m of land (about 0.4 acres), with 384 sq m of sanctioned built-up area and 1,022 sq m of recreational open space.
Where can I read reviews of RG-C,D?
Google Maps has reviews of RG-C,D written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RG-C,D?
RG-C,D by RELIABLE REALTOUCH is in vasai east, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000003657, per GharKundli's check of MahaRERA records.
How many homes are in RG-C,D?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D has 124 homes in 2 towers registered on MahaRERA, and 19% of them are sold or booked.
When was RG-C,D registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RG-C,D was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RG-C,D?
No court cases are listed for RG-C,D on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of RG-C,D?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RELIABLE REALTOUCH, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RG-C,D
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in pincode 401208
- Imperial Splendora F wing
- SERENO
- Agarwal Sky Heights
- Sunteck OneWorld -Tower 1
- Akhand Phase 3
- ARVIAN GENESIS
- ANANTA ONE
- Suraksha Smart City - Phase II
Other projects by RELIABLE REALTOUCH
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.