C SQUARE PARK

by C'SQUARE REALTY PVT.LTD. · Nallasopara, PalgharAlso near Virar West

Possession date of C SQUARE PARK: 30 June 2024, moved from 30 June 2021 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000003651. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about C SQUARE PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of C SQUARE PARK has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT99000009387)

    Reason the builder gave MahaRERA:
    “Project completion date is 30.06.2021 but we are applying for project extension in advance as we are sure that we will require more time period than already given by RERA authority to complete the project. Construction work is already delay…” Read the full reason“Project completion date is 30.06.2021 but we are applying for project extension in advance as we are sure that we will require more time period than already given by RERA authority to complete the project. Construction work is already delayed due to Covid-19 situation and shortage of labour. Kindly consider our proposal of extension of our project & approve the same as we are already suffering from financial crisis but do not want to compromise with the quality of our work.”
  3. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT99000012345)

    Reason the builder gave MahaRERA:
    “Already extended date of the project completion is 30.06.2022 but we are applying for further extension as we will require more time period to complete the project. Construction work is delayed due to Covid-19 situation & increase in raw ma…” Read the full reason“Already extended date of the project completion is 30.06.2022 but we are applying for further extension as we will require more time period to complete the project. Construction work is delayed due to Covid-19 situation & increase in raw material cost. Kindly consider our proposal for further extension of project completion date & approve the same as we are suffering from financial crisis & will not compromise with the construction quality.”
  4. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT99000016492)

    Reason the builder gave MahaRERA:
    “Project completion mainly got delayed due to the delay in approval from VVCMC (Vasai Virar City Municipal Corporation). We would like to inform you that the project is at completion stage only. We request for extension only for the completi…” Read the full reason“Project completion mainly got delayed due to the delay in approval from VVCMC (Vasai Virar City Municipal Corporation). We would like to inform you that the project is at completion stage only. We request for extension only for the completion of balance construction work.”
  5. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT99000018496)

    Reason the builder gave MahaRERA: “Due to the delay in supply of construction material on site, our project completion process got delayed.”

Source: C SQUARE PARK’s extension records on MahaRERA (P99000003651), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on C SQUARE PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000003651
Status
Lapsed (registration period ended)
Builder
C'SQUARE REALTY PVT.LTD.
Location
Nallasopara, Palghar · 401303
Project type
Others
Registered on
6 Aug 2017
Completion date at registration
June 2021
Latest completion date
June 2024
Delay so far
36 months
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of C SQUARE PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%70%50%0%
WING B100%70%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on C SQUARE PARK every month.

C SQUARE PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (12 floors) · WING B (11 floors)
  • Land: 1,423 sq m (about 0.4 acres) · sanctioned built-up 1,403 sq m · recreational space 141 sq m
  • Boundaries filed include: KONARK SOCIETY
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of C SQUARE PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

C SQUARE PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about C SQUARE PARK

What is the possession date of C SQUARE PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for C SQUARE PARK in Nallasopara, Palghar is 30 June 2024 — 36 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for C SQUARE PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date C SQUARE PARK's builder has filed on MahaRERA, the official one, is 30 June 2024, already 36 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of C SQUARE PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), C SQUARE PARK's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "Project completion date is 30.06.2021 but we are applying for project extension in advance as we are sure that we will require more time period than already given by RERA authority to complete the project. Construction work is already delayed due to Covid-19 situation and shortage of labour. Kindly consider our proposal of extension of our project & approve the same as we are already suffering from financial crisis but do not want to compromise with the quality of our work."; to 30 June 2023, giving the reason "Already extended date of the project completion is 30.06.2022 but we are applying for further extension as we will require more time period to complete the project. Construction work is delayed due to Covid-19 situation & increase in raw material cost. Kindly consider our proposal for further extension of project completion date & approve the same as we are suffering from financial crisis & will not compromise with the construction quality."; to 31 December 2023, giving the reason "Project completion mainly got delayed due to the delay in approval from VVCMC (Vasai Virar City Municipal Corporation). We would like to inform you that the project is at completion stage only. We request for extension only for the completion of balance construction work."; to 30 June 2024, giving the reason "Due to the delay in supply of construction material on site, our project completion process got delayed.".

What is the RERA number of C SQUARE PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of C SQUARE PARK in Nallasopara, Palghar is P99000003651.

Is C SQUARE PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), C SQUARE PARK is registered as P99000003651 and its status is "Lapsed (registration period ended)".

What is the construction status of C SQUARE PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), C SQUARE PARK's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 70% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does C SQUARE PARK have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is C SQUARE PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), C SQUARE PARK is registered on MahaRERA as P99000003651, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if C SQUARE PARK's possession date changes?

The latest dates are on C SQUARE PARK's MahaRERA page (P99000003651). GharKundli's Kundli Watch sends a free WhatsApp update on C SQUARE PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does C SQUARE PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), C SQUARE PARK has 2 buildings filed: WING A with 12 floors; WING B with 11 floors.

How big is the land of C SQUARE PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), C SQUARE PARK stands on 1,423 sq m of land (about 0.4 acres), with 1,403 sq m of sanctioned built-up area and 141 sq m of recreational open space.

Where can I read reviews of C SQUARE PARK?

Google Maps has reviews of C SQUARE PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is C SQUARE PARK?

C SQUARE PARK by C'SQUARE REALTY PVT.LTD. is in Nallasopara, Palghar (pincode 401303), near Virar West, Maharashtra, and is registered on MahaRERA as P99000003651, per GharKundli's check of MahaRERA records. Its boundaries filed there include KONARK SOCIETY.

When was C SQUARE PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), C SQUARE PARK was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on C SQUARE PARK?

No court cases are listed for C SQUARE PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of C SQUARE PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is C'SQUARE REALTY PVT.LTD..

Other projects in Nallasopara

All 211 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.