by NALAWADE CONSTRUCTION · Kasaba Peth, Pune 411011Also near Pune City, S.P. College, SwargateRegistered on MahaRERA as “OM SAI”

What’s in the report? →

Possession date of Nalawade Om Sai (MahaRERA P52100014674): 30 December 2021, moved from 30 December 2019 (24 months later), and it has already passed. It has 9 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100014674. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100014674, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about Nalawade Om Sai?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Nalawade Om Sai has moved

  1. 30 December 2019

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT52100005980)

    Reason the builder gave MahaRERA: “The project has been already been 95% completed. The reason for delayed for non completion is that there was some disputes between one commercial tenant and other financial obligation, however, the dispute has been resolved”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: Nalawade Om Sai’s extension records on MahaRERA (P52100014674), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Nalawade Om Sai

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100014674
Status
Lapsed (registration period ended)
Builder
NALAWADE CONSTRUCTION
Location
Kasaba Peth, Pune · 411011
Project type
Residential / Group Housing
Registered on
20 Dec 2017
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
9
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Nalawade Om Sai, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
OM SAI0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nalawade Om Sai every 1–2 months.

Nalawade Om Sai: buildings, flats and land, as filed on MahaRERA

  • Buildings: OM SAI (5 floors)
  • Land: 198 sq m (about 0.0 acres) · sanctioned built-up 383 sq m
  • Land, as filed: 748, KASABA PETH, PUNE
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Nalawade Om Sai →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nalawade Om Sai: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nalawade Om Sai

What is the possession date of Nalawade Om Sai?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nalawade Om Sai in Kasaba Peth, Pune is 30 December 2021 — 24 months later than 30 December 2019, the date given at registration. That date has already passed.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Nalawade Om Sai?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nalawade Om Sai's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 30 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Nalawade Om Sai extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai's builder applied to MahaRERA to extend the completion date once: to 31 December 2020, giving the reason "The project has been already been 95% completed. The reason for delayed for non completion is that there was some disputes between one commercial tenant and other financial obligation, however, the dispute has been resolved".

What is the RERA number of Nalawade Om Sai?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nalawade Om Sai in Kasaba Peth, Pune is P52100014674.

Is Nalawade Om Sai registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai is registered as P52100014674 and its status is "Lapsed (registration period ended)".

What is the current construction status of Nalawade Om Sai? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on OM SAI is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Nalawade Om Sai have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Nalawade Om Sai safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai is registered on MahaRERA as P52100014674, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nalawade Om Sai?

Nalawade Om Sai isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Nalawade Om Sai?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nalawade Om Sai: gharkundli.com/tools/property-cost-calculator

Has Nalawade Om Sai received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Nalawade Om Sai?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Nalawade Om Sai uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Nalawade Om Sai was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nalawade Om Sai's possession date changes?

The latest dates are on Nalawade Om Sai's MahaRERA page (P52100014674). GharKundli's Kundli Watch sends a free WhatsApp update on Nalawade Om Sai every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nalawade Om Sai have?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai has one building filed: OM SAI with 5 floors.

How big is the land of Nalawade Om Sai?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai stands on 198 sq m of land (about 0.0 acres), with 383 sq m of sanctioned built-up area.

What are the reviews of Nalawade Om Sai?

Google Maps has reviews of Nalawade Om Sai written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nalawade Om Sai?

Nalawade Om Sai by NALAWADE CONSTRUCTION is in Kasaba Peth, Pune, pincode 411011 (near Pune City, S.P. College, Swargate), Maharashtra, and is registered on MahaRERA as P52100014674, per GharKundli's check of MahaRERA records. Its land is filed as 748, KASABA PETH, PUNE. GharKundli lists all 77 MahaRERA projects in Kasba Peth (411011).

How many flats are in Nalawade Om Sai?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai has 9 homes in 1 tower registered on MahaRERA.

When was Nalawade Om Sai registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Nalawade Om Sai was registered on MahaRERA on 20 December 2017. GharKundli did not find a title report on the land on file there.

Does Nalawade Om Sai have any legal issues or court cases?

No court cases are listed for Nalawade Om Sai on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Nalawade Om Sai?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NALAWADE CONSTRUCTION.

Other projects in Kasba Peth (411011)

All 77 projects in Kasba Peth (411011) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.