Skip to content
GharKundli

Sunguard Park Ivory Phase II

by SUNGUARD BUILDERS LLP · Kalewadi Phata, Pune 411057Registered on MahaRERA as “PARK IVORY PHASE II”

What’s in the report? →

Possession: Sunguard Park Ivory Phase II (MahaRERA P52100015699) is marked completed on MahaRERA. It has 192 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100015699. Status: Completed.

Source: MahaRERA website — records for P52100015699, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sunguard Park Ivory Phase II?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Sunguard Park Ivory Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100015699
Status
Completed
Builder
SUNGUARD BUILDERS LLP
Location
Kalewadi Phata, Pune · 411057
Project type
Residential / Group Housing
Registered on
16 Mar 2018
Completion date at registration
June 2022
Latest completion date
June 2022
Homes
192
Towers
3
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Sunguard Park Ivory Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
F100%100%100%100%
G100%100%100%100%
H100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunguard Park Ivory Phase II every 1–2 months.

Sunguard Park Ivory Phase II: buildings, flats and land, as filed on MahaRERA

  • Buildings: F (13 floors) · G (13 floors) · H (14 floors)
  • Land: 7,680 sq m (about 1.9 acres) · sanctioned built-up 24,189 sq m
  • Land, as filed: 214 215
  • Map: Get directions

The builder’s record and reviews

Sunguard Builders (a group of 2 linked companies) has 5 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of Sunguard Park Ivory Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sunguard Park Ivory Phase II: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sunguard Park Ivory Phase II

What is the possession date of Sunguard Park Ivory Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sunguard Park Ivory Phase II in Kalewadi Phata, Pune is 30 June 2022.

Is the builder's possession date different from the MahaRERA date for Sunguard Park Ivory Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunguard Park Ivory Phase II's builder has filed on MahaRERA, the official one, is 30 June 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sunguard Park Ivory Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sunguard Park Ivory Phase II in Kalewadi Phata, Pune is P52100015699.

Is Sunguard Park Ivory Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II is registered as P52100015699 and its status is "Completed".

What is the current construction status of Sunguard Park Ivory Phase II? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Sunguard Park Ivory Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sunguard Park Ivory Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II is registered on MahaRERA as P52100015699, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sunguard Park Ivory Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Sunguard Park Ivory Phase II?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sunguard Park Ivory Phase II: gharkundli.com/tools/property-cost-calculator

Has Sunguard Park Ivory Phase II received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Sunguard Park Ivory Phase II completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II is marked completed on MahaRERA, and the completion date filed there is 30 June 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Sunguard Park Ivory Phase II uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Sunguard Park Ivory Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Sunguard Park Ivory Phase II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: PARK IVORY PHASE III (P52100030055, possession 30 Apr 2024). Check that your agreement names the registration of your own wing.

How can I get updates if Sunguard Park Ivory Phase II's possession date changes?

The latest dates are on Sunguard Park Ivory Phase II's MahaRERA page (P52100015699). GharKundli's Kundli Watch sends a free WhatsApp update on Sunguard Park Ivory Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sunguard Park Ivory Phase II have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II has 3 buildings filed: F with 13 floors; G with 13 floors; H with 14 floors.

How big is the land of Sunguard Park Ivory Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II stands on 7,680 sq m of land (about 1.9 acres), with 24,189 sq m of sanctioned built-up area.

What is the track record of Sunguard Park Ivory Phase II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Builders (a group of 2 linked companies) has 5 projects on MahaRERA since 2018, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sunguard Park Ivory Phase II?

Google Maps has reviews of Sunguard Park Ivory Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sunguard Park Ivory Phase II?

Sunguard Park Ivory Phase II by SUNGUARD BUILDERS LLP is in Kalewadi Phata, Pune, pincode 411057, Maharashtra, and is registered on MahaRERA as P52100015699, per GharKundli's check of MahaRERA records. Its land is filed as 214 215. GharKundli lists all 644 MahaRERA projects in Wakad (411057).

How many flats are in Sunguard Park Ivory Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II has 192 homes in 3 towers registered on MahaRERA.

When was Sunguard Park Ivory Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sunguard Park Ivory Phase II was registered on MahaRERA on 16 March 2018. GharKundli did not find a title report on the land on file there.

Does Sunguard Park Ivory Phase II have any legal issues or court cases?

1 court case is listed for Sunguard Park Ivory Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Sunguard Park Ivory Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SUNGUARD BUILDERS LLP, which has 3 other projects registered on MahaRERA.

Other projects in Mulshi

All 644 projects in Wakad (411057) →

Other projects by SUNGUARD BUILDERS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.