by Sunil Sudhakar Sable · Sadhashiv Peth, PuneAlso near Wakad, Baner, Kiwale

Possession date of Shri Venkateshwara: 28 February 2024, moved from 28 February 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100015573. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (February 2024) has passed.

What do you want to know about Shri Venkateshwara?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shri Venkateshwara has moved

  1. 28 February 2023

    Completion date given when the project was registered

  2. 28 February 2024

    Extended at the builder's request (MahaRERA application EXT52100013881)

    Reason the builder gave MahaRERA: “Respected sir We almost completed 95% project work. We require extension certificate for Building Completion from PMC Authority and for agreement sale Deed. we assure you to complete remaining work in Extended time. Regards”

Source: Shri Venkateshwara’s extension records on MahaRERA (P52100015573), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shri Venkateshwara

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100015573
Status
Lapsed (registration period ended)
Builder
Sunil Sudhakar Sable
Location
Sadhashiv Peth, Pune · 411030
Project type
Others
Registered on
8 Mar 2018
Completion date at registration
February 2023
Latest completion date
February 2024
Delay so far
12 months
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shri Venkateshwara, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shri Venkateshwara100%100%100%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shri Venkateshwara every month.

Shri Venkateshwara: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shri Venkateshwara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shri Venkateshwara: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shri Venkateshwara

What is the possession date of Shri Venkateshwara?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shri Venkateshwara in Sadhashiv Peth, Pune is 28 February 2024 — 12 months later than 28 February 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shri Venkateshwara?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shri Venkateshwara's builder has filed on MahaRERA, the official one, is 28 February 2024, already 12 months later than the 28 February 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shri Venkateshwara extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara's builder applied to MahaRERA to extend the completion date once: to 28 February 2024, giving the reason "Respected sir We almost completed 95% project work. We require extension certificate for Building Completion from PMC Authority and for agreement sale Deed. we assure you to complete remaining work in Extended time. Regards".

What is the RERA number of Shri Venkateshwara?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shri Venkateshwara in Sadhashiv Peth, Pune is P52100015573.

Is Shri Venkateshwara registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara is registered as P52100015573 and its status is "Lapsed (registration period ended)".

What is the construction status of Shri Venkateshwara?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shri Venkateshwara is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shri Venkateshwara have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shri Venkateshwara safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara is registered on MahaRERA as P52100015573, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shri Venkateshwara's possession date changes?

The latest dates are on Shri Venkateshwara's MahaRERA page (P52100015573). GharKundli's Kundli Watch sends a free WhatsApp update on Shri Venkateshwara every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shri Venkateshwara have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara has one building filed: Shri Venkateshwara with 10 floors.

How big is the land of Shri Venkateshwara?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara stands on 385 sq m of land (about 0.1 acres), with 477 sq m of sanctioned built-up area.

Where can I read reviews of Shri Venkateshwara?

Google Maps has reviews of Shri Venkateshwara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shri Venkateshwara?

Shri Venkateshwara by Sunil Sudhakar Sable is in Sadhashiv Peth, Pune (pincode 411030), near Wakad, Baner, Kiwale, Maharashtra, and is registered on MahaRERA as P52100015573, per GharKundli's check of MahaRERA records.

How many homes are in Shri Venkateshwara?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara has 20 homes in 1 tower registered on MahaRERA.

When was Shri Venkateshwara registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shri Venkateshwara was registered on MahaRERA on 8 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Shri Venkateshwara?

No court cases are listed for Shri Venkateshwara on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Shri Venkateshwara?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sunil Sudhakar Sable.

Other projects in pincode 411030

All 90 projects in Sadashiv Peth (411030) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.