SHIVPRIYA RESIDENCY

by OM GURUDEV PROMOTERS BUILDERS AND CONTRACTORS · Shukrawar Peth, PuneAlso near Sadashiv Peth, Nana Peth, Raviwar Peth

Possession date of SHIVPRIYA RESIDENCY: 31 December 2024, moved from 1 September 2022 (27 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100015863. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about SHIVPRIYA RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHIVPRIYA RESIDENCY has moved

  1. 1 September 2022

    Completion date given when the project was registered

  2. 31 August 2023

    Extended at the builder's request (MahaRERA application EXT52100012493)

    Reason the builder gave MahaRERA: “1) PROJECT CONSTRUCTION DELAYED DUE TO FUND ISSUES (NO SALE/BOOKING) 2) RESTRICTIONS ON SELF FUNDING 3) COVID 19”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52100016652)

    Reason the builder gave MahaRERA: “FUND FLOW AND SITE CONDITIONS AS SITE IS IN CITY AREA.”

Source: SHIVPRIYA RESIDENCY’s extension records on MahaRERA (P52100015863), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHIVPRIYA RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100015863
Status
Lapsed (registration period ended)
Builder
OM GURUDEV PROMOTERS BUILDERS AND CONTRACTORS
Location
Shukrawar Peth, Pune · 411002
Project type
Others
Registered on
28 Mar 2018
Completion date at registration
September 2022
Latest completion date
December 2024
Delay so far
27 months
Homes
45
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHIVPRIYA RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIVPRIYA RESIDENCY100%100%90%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIVPRIYA RESIDENCY every month.

SHIVPRIYA RESIDENCY: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHIVPRIYA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHIVPRIYA RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHIVPRIYA RESIDENCY

What is the possession date of SHIVPRIYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHIVPRIYA RESIDENCY in Shukrawar Peth, Pune is 31 December 2024 — 27 months later than 1 September 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHIVPRIYA RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIVPRIYA RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2024, already 27 months later than the 1 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHIVPRIYA RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 31 August 2023, giving the reason "1) PROJECT CONSTRUCTION DELAYED DUE TO FUND ISSUES (NO SALE/BOOKING) 2) RESTRICTIONS ON SELF FUNDING 3) COVID 19"; to 31 December 2024, giving the reason "FUND FLOW AND SITE CONDITIONS AS SITE IS IN CITY AREA.".

What is the RERA number of SHIVPRIYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHIVPRIYA RESIDENCY in Shukrawar Peth, Pune is P52100015863.

Is SHIVPRIYA RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY is registered as P52100015863 and its status is "Lapsed (registration period ended)".

What is the construction status of SHIVPRIYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHIVPRIYA RESIDENCY is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does SHIVPRIYA RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHIVPRIYA RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY is registered on MahaRERA as P52100015863, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHIVPRIYA RESIDENCY's possession date changes?

The latest dates are on SHIVPRIYA RESIDENCY's MahaRERA page (P52100015863). GharKundli's Kundli Watch sends a free WhatsApp update on SHIVPRIYA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHIVPRIYA RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY has one building filed: SHIVPRIYA RESIDENCY with 7 floors.

How big is the land of SHIVPRIYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY stands on 472 sq m of land (about 0.1 acres), with 1,110 sq m of sanctioned built-up area.

Where can I read reviews of SHIVPRIYA RESIDENCY?

Google Maps has reviews of SHIVPRIYA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHIVPRIYA RESIDENCY?

SHIVPRIYA RESIDENCY by OM GURUDEV PROMOTERS BUILDERS AND CONTRACTORS is in Shukrawar Peth, Pune (pincode 411002), near Sadashiv Peth, Nana Peth, Raviwar Peth, Maharashtra, and is registered on MahaRERA as P52100015863, per GharKundli's check of MahaRERA records. Its boundaries filed there include Shivaji Road.

How many homes are in SHIVPRIYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY has 45 homes in 1 tower registered on MahaRERA.

When was SHIVPRIYA RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVPRIYA RESIDENCY was registered on MahaRERA on 28 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SHIVPRIYA RESIDENCY?

No court cases are listed for SHIVPRIYA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHIVPRIYA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is OM GURUDEV PROMOTERS BUILDERS AND CONTRACTORS.

Other projects in pincode 411002

All 74 projects in Shukrawar Peth (411002) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.