by KEYSTONE REALTY · Shivajinagar, Pune 411005Also near Shivaji Nagar, Model Colony, Range HillsRegistered on MahaRERA as “VB CAPITOL”

What’s in the report? →

Possession date of Keystone VB Capitol (MahaRERA P52100016113): 30 June 2022, moved from 1 April 2021 (14 months later), and it has already passed. It has 37 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100016113. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100016113, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2022) has passed.

What do you want to know about Keystone VB Capitol?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Keystone VB Capitol has moved

  1. 1 April 2021

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT52100010005)

    Reason the builder gave MahaRERA: “Due to global pandemic situation (Covid -19) site is working at minimum labour capacity,”
  3. 30 June 2022

    Revised completion date on MahaRERA

Source: Keystone VB Capitol’s extension records on MahaRERA (P52100016113), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Keystone VB Capitol

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100016113
Status
Lapsed (registration period ended)
Builder
KEYSTONE REALTY
Location
Shivajinagar, Pune · 411005
Project type
Commercial
Registered on
17 Apr 2018
Completion date at registration
April 2021
Latest completion date
June 2022
Delay so far
14 months
Homes
37
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Keystone VB Capitol, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VB CAPITOL100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Keystone VB Capitol every 1–2 months.

Keystone VB Capitol: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Keystone Real Estate (a group of 4 linked companies) has 4 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 2 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of Keystone VB Capitol →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Keystone VB Capitol: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Keystone VB Capitol

What is the possession date of Keystone VB Capitol?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Keystone VB Capitol in Shivajinagar, Pune is 30 June 2022 — 14 months later than 1 April 2021, the date given at registration. That date has already passed.

The date has already moved 14 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Keystone VB Capitol?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Keystone VB Capitol's builder has filed on MahaRERA, the official one, is 30 June 2022, already 14 months later than the 1 April 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Keystone VB Capitol extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol's builder applied to MahaRERA to extend the completion date once: to 31 December 2021, giving the reason "Due to global pandemic situation (Covid -19) site is working at minimum labour capacity,".

What is the RERA number of Keystone VB Capitol?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Keystone VB Capitol in Shivajinagar, Pune is P52100016113.

Is Keystone VB Capitol registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol is registered as P52100016113 and its status is "Lapsed (registration period ended)".

What is the current construction status of Keystone VB Capitol? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VB CAPITOL is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Keystone VB Capitol have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Keystone VB Capitol safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol is registered on MahaRERA as P52100016113, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 14 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Keystone VB Capitol?

Keystone VB Capitol isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Keystone VB Capitol?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Keystone VB Capitol: gharkundli.com/tools/property-cost-calculator

Has Keystone VB Capitol received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Keystone VB Capitol?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Keystone VB Capitol uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Keystone VB Capitol was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Keystone VB Capitol's possession date changes?

The latest dates are on Keystone VB Capitol's MahaRERA page (P52100016113). GharKundli's Kundli Watch sends a free WhatsApp update on Keystone VB Capitol every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Keystone VB Capitol have?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol has one building filed: VB CAPITOL with 15 floors.

How big is the land of Keystone VB Capitol?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol stands on 1,000 sq m of land (about 0.2 acres), with 1,142 sq m of sanctioned built-up area.

What is the track record of Keystone VB Capitol's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone Real Estate (a group of 4 linked companies) has 4 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 2 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Keystone VB Capitol?

Google Maps has reviews of Keystone VB Capitol written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Keystone VB Capitol?

Keystone VB Capitol by KEYSTONE REALTY is in Shivajinagar, Pune, pincode 411005 (near Shivaji Nagar, Model Colony, Range Hills), Maharashtra, and is registered on MahaRERA as P52100016113, per GharKundli's check of MahaRERA records. Its boundaries filed there include VRINDAVAN SOCIETY. Its land is filed as 2709. GharKundli lists all 57 MahaRERA projects in Shivajinagar (411005).

How many flats are in Keystone VB Capitol?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol has 37 homes in 1 tower registered on MahaRERA.

When was Keystone VB Capitol registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Keystone VB Capitol was registered on MahaRERA on 17 April 2018. GharKundli did not find a title report on the land on file there.

Does Keystone VB Capitol have any legal issues or court cases?

No court cases are listed for Keystone VB Capitol on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Keystone VB Capitol?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KEYSTONE REALTY.