Unity by Lotus
by Lotus Logistics and Developers Private Limited · versova, MumbaiAlso near Andheri East, Andheri West, Marol
Possession date of Unity by Lotus: 30 June 2023, moved from 30 September 2020 (33 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800006403. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2023) has passed.
What do you want to know about Unity by Lotus?
How the possession date of Unity by Lotus has moved
30 September 2020
Completion date given when the project was registered
30 September 2021
Extended at the builder's request (MahaRERA application EXT51800005697)
Reason the builder gave MahaRERA:
“The Applicant is developing the said Project on the land as described on the website of MahaRERA which admeasures 6,640 sq. mtrs. The amended plans in respect of the said Project were approved by MCGM on 3rd April 2018 in respect of the bui…” Read the full reason
“The Applicant is developing the said Project on the land as described on the website of MahaRERA which admeasures 6,640 sq. mtrs. The amended plans in respect of the said Project were approved by MCGM on 3rd April 2018 in respect of the building interalia comprising of Wing B Stilt + 1st to 14th upper floor. The Commencement Certificate dated 24th July 2015 issued in respect of the said Project was further re-endorsed for Wing B comprising of stilt +1st to 14th (pt) upper floor on 28th May 2018. The Urban Development Department of Maharashtra (“said Department”) vide its notification dated…”30 June 2023
Extended at the builder's request (MahaRERA application EXT51800012679)
Reason the builder gave MahaRERA:
“the said Project was delayed because of ensuing litigation between the Society and the Applicant which lead to a delay of approximately 9 (nine) months in completing the said Project. The consent terms and the relevant supplemental agreemen…” Read the full reason
“the said Project was delayed because of ensuing litigation between the Society and the Applicant which lead to a delay of approximately 9 (nine) months in completing the said Project. The consent terms and the relevant supplemental agreement in respect of the said litigation are executed as per the order dated 17th March 2022 of the Court of Sessions Dindoshi (Borivali Division), Goregaon, Mumbai bearing stamp no. 2262 of 2022.”
Source: Unity by Lotus’s extension records on MahaRERA (P51800006403), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Unity by Lotus
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800006403
- Status
- Lapsed (registration period ended)
- Builder
- Lotus Logistics and Developers Private Limited
- Location
- versova, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- September 2020
- Latest completion date
- June 2023
- Delay so far
- 33 months
- Homes
- 124
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Unity by Lotus, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing B Sale | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Unity by Lotus every month.
Unity by Lotus: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing B Sale (22 floors)
- Land: 6,640 sq m (about 1.6 acres) · sanctioned built-up 18,265 sq m · recreational space 995 sq m
- Boundaries filed include: Wildwood Park
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Lotus Logistics And Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 21 months); 1 still being built, 1 past the promised date (typically 34 months late); 1 lapsed. 11 complaints on MahaRERA across 3 projects.
Read Google reviews of Unity by Lotus →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Unity by Lotus: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Unity by Lotus
What is the possession date of Unity by Lotus?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Unity by Lotus in versova, Mumbai is 30 June 2023 — 33 months later than 30 September 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Unity by Lotus?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Unity by Lotus's builder has filed on MahaRERA, the official one, is 30 June 2023, already 33 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Unity by Lotus extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2021, giving the reason "The Applicant is developing the said Project on the land as described on the website of MahaRERA which admeasures 6,640 sq. mtrs. The amended plans in respect of the said Project were approved by MCGM on 3rd April 2018 in respect of the building interalia comprising of Wing B Stilt + 1st to 14th upper floor. The Commencement Certificate dated 24th July 2015 issued in respect of the said Project was further re-endorsed for Wing B comprising of stilt +1st to 14th (pt) upper floor on 28th May 2018. The Urban Development Department of Maharashtra (“said Department”) vide its notification dated…"; to 30 June 2023, giving the reason "the said Project was delayed because of ensuing litigation between the Society and the Applicant which lead to a delay of approximately 9 (nine) months in completing the said Project. The consent terms and the relevant supplemental agreement in respect of the said litigation are executed as per the order dated 17th March 2022 of the Court of Sessions Dindoshi (Borivali Division), Goregaon, Mumbai bearing stamp no. 2262 of 2022.".
What is the RERA number of Unity by Lotus?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Unity by Lotus in versova, Mumbai is P51800006403.
Is Unity by Lotus registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus is registered as P51800006403 and its status is "Lapsed (registration period ended)".
What is the construction status of Unity by Lotus?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Wing B Sale is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Unity by Lotus have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Unity by Lotus safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus is registered on MahaRERA as P51800006403, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Unity by Lotus's possession date changes?
The latest dates are on Unity by Lotus's MahaRERA page (P51800006403). GharKundli's Kundli Watch sends a free WhatsApp update on Unity by Lotus every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Unity by Lotus have?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus has one building filed: Wing B Sale with 22 floors.
How big is the land of Unity by Lotus?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus stands on 6,640 sq m of land (about 1.6 acres), with 18,265 sq m of sanctioned built-up area and 995 sq m of recreational open space.
What is the track record of Unity by Lotus's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Lotus Logistics And Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 21 months); 1 still being built, 1 past the promised date (typically 34 months late); 1 lapsed. 11 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Unity by Lotus?
Google Maps has reviews of Unity by Lotus written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Unity by Lotus?
Unity by Lotus by Lotus Logistics and Developers Private Limited is in versova, Mumbai (pincode 400053), near Andheri East, Andheri West, Marol, Maharashtra, and is registered on MahaRERA as P51800006403, per GharKundli's check of MahaRERA records. Its boundaries filed there include Wildwood Park.
How many homes are in Unity by Lotus?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus has 124 homes in 1 tower registered on MahaRERA.
When was Unity by Lotus registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Unity by Lotus was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Unity by Lotus?
No court cases are listed for Unity by Lotus on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Unity by Lotus?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Lotus Logistics and Developers Private Limited.
Check it yourself on MahaRERA
- How to check the possession date of Unity by Lotus
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Andheri
- ocean view
- SHRADDHA WEST RESIDENCY
- Green Bay
- SHIVSAI SRA CHS
- Live Well Chs Ltd
- Lotus Sky Plaza
- THERESE
- Pruthvi Symphony
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.