Aditya Complex Phase 2
by Rohidas Maruti Jadhav · Near Mahadev Mandir Gavthan, Pune
Possession: Aditya Complex Phase 2 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100016827. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Aditya Complex Phase 2?
How the possession date of Aditya Complex Phase 2 has moved
30 December 2021
Completion date given when the project was registered
30 December 2022
Extended at the builder's request (MahaRERA application EXT52100011388)
Reason the builder gave MahaRERA: “DUE TO COVID 19 WE WERE UNABLE TO COMPLETE PROJECT ON TIME”
31 December 2024
Extended at the builder's request (MahaRERA application EXT52100013624)
Reason the builder gave MahaRERA: “Due to Completion Certificate not received from Corporation.”
Source: Aditya Complex Phase 2’s extension records on MahaRERA (P52100016827), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Aditya Complex Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100016827
- Status
- Completed
- Builder
- Rohidas Maruti Jadhav
- Location
- Near Mahadev Mandir Gavthan, Pune · 411027
- Project type
- Residential / Group Housing
- Registered on
- 18 Jun 2018
- Completion date at registration
- December 2021
- Latest completion date
- December 2024
- Delay so far
- 36 months
- Homes
- 47
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Aditya Complex Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C Wing | 0% | 100% | 100% | 95% |
| D Wing | 0% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aditya Complex Phase 2 every month.
Aditya Complex Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: C Wing (5 floors) · D Wing (5 floors)
- Land: 2,218 sq m (about 0.5 acres) · sanctioned built-up 2,218 sq m · recreational space 230 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Aditya Complex Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aditya Complex Phase 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Aditya Complex Phase 2
What is the possession date of Aditya Complex Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aditya Complex Phase 2 in Near Mahadev Mandir Gavthan, Pune is 31 December 2024 — 36 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Aditya Complex Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aditya Complex Phase 2's builder has filed on MahaRERA, the official one, is 31 December 2024, already 36 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Aditya Complex Phase 2 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2022, giving the reason "DUE TO COVID 19 WE WERE UNABLE TO COMPLETE PROJECT ON TIME"; to 31 December 2024, giving the reason "Due to Completion Certificate not received from Corporation.".
What is the RERA number of Aditya Complex Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aditya Complex Phase 2 in Near Mahadev Mandir Gavthan, Pune is P52100016827.
Is Aditya Complex Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2 is registered as P52100016827 and its status is "Completed".
What is the construction status of Aditya Complex Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Aditya Complex Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Aditya Complex Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2 is registered on MahaRERA as P52100016827, its MahaRERA status is "Completed", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Aditya Complex Phase 2's possession date changes?
The latest dates are on Aditya Complex Phase 2's MahaRERA page (P52100016827). GharKundli's Kundli Watch sends a free WhatsApp update on Aditya Complex Phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aditya Complex Phase 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2 has 2 buildings filed: C Wing with 5 floors; D Wing with 5 floors.
How big is the land of Aditya Complex Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2 stands on 2,218 sq m of land (about 0.5 acres), with 2,218 sq m of sanctioned built-up area and 230 sq m of recreational open space.
Where can I read reviews of Aditya Complex Phase 2?
Google Maps has reviews of Aditya Complex Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Aditya Complex Phase 2?
Aditya Complex Phase 2 by Rohidas Maruti Jadhav is in Near Mahadev Mandir Gavthan, Pune (pincode 411027), Maharashtra, and is registered on MahaRERA as P52100016827, per GharKundli's check of MahaRERA records.
How many homes are in Aditya Complex Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2 has 47 homes in 2 towers registered on MahaRERA.
When was Aditya Complex Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Aditya Complex Phase 2 was registered on MahaRERA on 18 June 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Aditya Complex Phase 2?
No court cases are listed for Aditya Complex Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Aditya Complex Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Rohidas Maruti Jadhav.
Check it yourself on MahaRERA
- How to check the possession date of Aditya Complex Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
All 111 projects in Pimple Nilakh (411027) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.