Bhosale Megha Sparkle Towers

by S D Bhosale Developers · Bhosale Vasti, Pune 412105Registered on MahaRERA as “Megha Sparkle Towers”

What’s in the report? →

Possession date of Bhosale Megha Sparkle Towers (MahaRERA P52100016778): 30 September 2022, and it has already passed. It has 132 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100016778. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100016778, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2022) has passed.

What do you want to know about Bhosale Megha Sparkle Towers?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Bhosale Megha Sparkle Towers

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100016778
Status
Lapsed (registration period ended)
Builder
S D Bhosale Developers
Location
Bhosale Vasti, Pune · 412105
Project type
Residential / Group Housing
Registered on
12 Jun 2018
Completion date at registration
September 2022
Latest completion date
September 2022
Homes
132
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Bhosale Megha Sparkle Towers, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%100%100%100%
B100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhosale Megha Sparkle Towers every 1–2 months.

Bhosale Megha Sparkle Towers: buildings, flats and land, as filed on MahaRERA

  • Buildings: A (25 floors) · B (23 floors)
  • Land: 3,828 sq m (about 0.9 acres) · sanctioned built-up 4,662 sq m · recreational space 383 sq m
  • Land, as filed: 253/5, 253/6, 255/1,255/2
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Bhosale Megha Sparkle Towers →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Bhosale Megha Sparkle Towers: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Bhosale Megha Sparkle Towers

What is the possession date of Bhosale Megha Sparkle Towers?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Bhosale Megha Sparkle Towers in Bhosale Vasti, Pune is 30 September 2022. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Bhosale Megha Sparkle Towers?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhosale Megha Sparkle Towers's builder has filed on MahaRERA, the official one, is 30 September 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Bhosale Megha Sparkle Towers?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Bhosale Megha Sparkle Towers in Bhosale Vasti, Pune is P52100016778.

Is Bhosale Megha Sparkle Towers registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers is registered as P52100016778 and its status is "Lapsed (registration period ended)".

What is the current construction status of Bhosale Megha Sparkle Towers? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Bhosale Megha Sparkle Towers have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Bhosale Megha Sparkle Towers safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers is registered on MahaRERA as P52100016778, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Bhosale Megha Sparkle Towers?

Bhosale Megha Sparkle Towers isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Bhosale Megha Sparkle Towers?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Bhosale Megha Sparkle Towers: gharkundli.com/tools/property-cost-calculator

Has Bhosale Megha Sparkle Towers received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Bhosale Megha Sparkle Towers?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Bhosale Megha Sparkle Towers uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Bhosale Megha Sparkle Towers was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Bhosale Megha Sparkle Towers's possession date changes?

The latest dates are on Bhosale Megha Sparkle Towers's MahaRERA page (P52100016778). GharKundli's Kundli Watch sends a free WhatsApp update on Bhosale Megha Sparkle Towers every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Bhosale Megha Sparkle Towers have?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers has 2 buildings filed: A with 25 floors; B with 23 floors.

How big is the land of Bhosale Megha Sparkle Towers?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers stands on 3,828 sq m of land (about 0.9 acres), with 4,662 sq m of sanctioned built-up area and 383 sq m of recreational open space.

What are the reviews of Bhosale Megha Sparkle Towers?

Google Maps has reviews of Bhosale Megha Sparkle Towers written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Bhosale Megha Sparkle Towers?

Bhosale Megha Sparkle Towers by S D Bhosale Developers is in Bhosale Vasti, Pune, pincode 412105, Maharashtra, and is registered on MahaRERA as P52100016778, per GharKundli's check of MahaRERA records. Its land is filed as 253/5, 253/6, 255/1,255/2. GharKundli lists all 885 MahaRERA projects in Alandi Devachi (412105).

How many flats are in Bhosale Megha Sparkle Towers?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers has 132 homes in 2 towers registered on MahaRERA.

When was Bhosale Megha Sparkle Towers registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bhosale Megha Sparkle Towers was registered on MahaRERA on 12 June 2018. GharKundli did not find a title report on the land on file there.

Does Bhosale Megha Sparkle Towers have any legal issues or court cases?

No court cases are listed for Bhosale Megha Sparkle Towers on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Bhosale Megha Sparkle Towers?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is S D Bhosale Developers.