by PATE CONSTRUCTIONS JOINT VENTURE · Bibwewadi, PuneAlso near Theur

Possession: KIMAYA E is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100017427. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about KIMAYA E?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KIMAYA E has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 December 2022

    Extended at the builder's request (MahaRERA application EXT52100012482)

    Reason the builder gave MahaRERA: “Covid”

Source: KIMAYA E’s extension records on MahaRERA (P52100017427), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KIMAYA E

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100017427
Status
Completed
Builder
PATE CONSTRUCTIONS JOINT VENTURE
Location
Bibwewadi, Pune · 411037
Project type
Residential / Group Housing
Registered on
13 Aug 2018
Completion date at registration
June 2022
Latest completion date
December 2022
Delay so far
6 months
Homes
22
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KIMAYA E, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KIMAYA E0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KIMAYA E every month.

KIMAYA E: buildings, flats and land, as filed on MahaRERA

  • Buildings: KIMAYA E (12 floors)
  • Land: 9,312 sq m (about 2.3 acres) · sanctioned built-up 1,920 sq m · recreational space 1,076 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KIMAYA E →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KIMAYA E: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KIMAYA E

What is the possession date of KIMAYA E?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KIMAYA E in Bibwewadi, Pune is 30 December 2022 — 6 months later than 30 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for KIMAYA E?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KIMAYA E's builder has filed on MahaRERA, the official one, is 30 December 2022, already 6 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KIMAYA E extended?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E's builder applied to MahaRERA to extend the completion date once: to 30 December 2022, giving the reason "Covid".

What is the RERA number of KIMAYA E?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KIMAYA E in Bibwewadi, Pune is P52100017427.

Is KIMAYA E registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E is registered as P52100017427 and its status is "Completed".

What is the construction status of KIMAYA E?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E's status on MahaRERA is "Completed". As filed by the builder, slab work on KIMAYA E is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does KIMAYA E have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KIMAYA E safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E is registered on MahaRERA as P52100017427, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KIMAYA E's possession date changes?

The latest dates are on KIMAYA E's MahaRERA page (P52100017427). GharKundli's Kundli Watch sends a free WhatsApp update on KIMAYA E every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KIMAYA E have?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E has one building filed: KIMAYA E with 12 floors.

How big is the land of KIMAYA E?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E stands on 9,312 sq m of land (about 2.3 acres), with 1,920 sq m of sanctioned built-up area and 1,076 sq m of recreational open space.

Where can I read reviews of KIMAYA E?

Google Maps has reviews of KIMAYA E written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KIMAYA E?

KIMAYA E by PATE CONSTRUCTIONS JOINT VENTURE is in Bibwewadi, Pune (pincode 411037), near Theur, Maharashtra, and is registered on MahaRERA as P52100017427, per GharKundli's check of MahaRERA records.

How many homes are in KIMAYA E?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E has 22 homes in 1 tower registered on MahaRERA.

When was KIMAYA E registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KIMAYA E was registered on MahaRERA on 13 August 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on KIMAYA E?

No court cases are listed for KIMAYA E on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KIMAYA E?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PATE CONSTRUCTIONS JOINT VENTURE.