NIRVANA
by ARNAV BUILDERS · Bopkhel, Pune
Possession: NIRVANA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100018556. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about NIRVANA?
How the possession date of NIRVANA has moved
30 June 2022
Completion date given when the project was registered
30 June 2023
Extended at the builder's request (MahaRERA application EXT52100012387)
Reason the builder gave MahaRERA:
“(1) Due to Global pandemic labours at site were not also material was not available due to that construction work was very slow. (2) Due to Global Pandemic Covid-19 sales of flat was very slow that also affected speed of construction (3) Du…” Read the full reason
“(1) Due to Global pandemic labours at site were not also material was not available due to that construction work was very slow. (2) Due to Global Pandemic Covid-19 sales of flat was very slow that also affected speed of construction (3) Due to lockdown 2 in year 2021 our construction completion got delayed and due to that we were unable to PCMC completion certificate.”
Source: NIRVANA’s extension records on MahaRERA (P52100018556), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NIRVANA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100018556
- Status
- Completed
- Builder
- ARNAV BUILDERS
- Location
- Bopkhel, Pune · 411031
- Project type
- Residential / Group Housing
- Registered on
- 13 Nov 2018
- Completion date at registration
- June 2022
- Latest completion date
- June 2023
- Delay so far
- 12 months
- Homes
- 32
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of NIRVANA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRVANA | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRVANA every month.
NIRVANA: buildings, flats and land, as filed on MahaRERA
- Buildings: NIRVANA (8 floors)
- Land: 900 sq m (about 0.2 acres) · sanctioned built-up 642 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NIRVANA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NIRVANA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NIRVANA
What is the possession date of NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRVANA in Bopkhel, Pune is 30 June 2023 — 12 months later than 30 June 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for NIRVANA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRVANA's builder has filed on MahaRERA, the official one, is 30 June 2023, already 12 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NIRVANA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "(1) Due to Global pandemic labours at site were not also material was not available due to that construction work was very slow. (2) Due to Global Pandemic Covid-19 sales of flat was very slow that also affected speed of construction (3) Due to lockdown 2 in year 2021 our construction completion got delayed and due to that we were unable to PCMC completion certificate.".
What is the RERA number of NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRVANA in Bopkhel, Pune is P52100018556.
Is NIRVANA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA is registered as P52100018556 and its status is "Completed".
What is the construction status of NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA's status on MahaRERA is "Completed". As filed by the builder, slab work on NIRVANA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does NIRVANA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is NIRVANA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA is registered on MahaRERA as P52100018556, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NIRVANA's possession date changes?
The latest dates are on NIRVANA's MahaRERA page (P52100018556). GharKundli's Kundli Watch sends a free WhatsApp update on NIRVANA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NIRVANA have?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA has one building filed: NIRVANA with 8 floors.
How big is the land of NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA stands on 900 sq m of land (about 0.2 acres), with 642 sq m of sanctioned built-up area.
Where can I read reviews of NIRVANA?
Google Maps has reviews of NIRVANA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NIRVANA?
NIRVANA by ARNAV BUILDERS is in Bopkhel, Pune (pincode 411031), Maharashtra, and is registered on MahaRERA as P52100018556, per GharKundli's check of MahaRERA records.
How many homes are in NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA has 32 homes in 1 tower registered on MahaRERA.
When was NIRVANA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRVANA was registered on MahaRERA on 13 November 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on NIRVANA?
No court cases are listed for NIRVANA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ARNAV BUILDERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NIRVANA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Bopkhel
- Crystal Space
- S. No. 1A/1,2,3,1B - AARAMBHA RESIDENCY
- AKSHA CASA PALLADIUM
- GHULE PRIDE
- MUKTAI AANGAN PHASE IX
- KUNDAN PRAANGAN
- ARJUN HEIGHTS
- KRUSHNARANG VILLA
Other projects by ARNAV BUILDERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.