Skip to content
GharKundli

Shubhchandra

by M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE · Rahatani, Pune

Possession: Shubhchandra is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100019627. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Shubhchandra?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shubhchandra has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52100012209)

    Reason the builder gave MahaRERA: “NON AVAILABILITY OF FUNDS AND LABOUR DUE TO FORCE MAJEURE CIRCUMSTANCES.”

Source: Shubhchandra’s extension records on MahaRERA (P52100019627), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shubhchandra

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100019627
Status
Completed
Builder
M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE
Location
Rahatani, Pune · 411017
Project type
Others
Registered on
14 Feb 2019
Completion date at registration
June 2022
Latest completion date
June 2023
Delay so far
12 months
Homes
66
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of Shubhchandra, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%42%0%
Wing B100%100%37%0%
Wing C100%100%37%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shubhchandra every month.

Shubhchandra: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (7 floors) · Wing B (7 floors) · Wing C (7 floors)
  • Land: 1,858 sq m (about 0.5 acres) · sanctioned built-up 1,402 sq m
  • Boundaries filed include: Hotel sitara Mr Kate

The builder’s record and reviews

Kiran Creators & Developers Through Proprietor MR Kashinath Ganesh Nehete has 11 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 5 months). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Shubhchandra →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shubhchandra: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shubhchandra

What is the possession date of Shubhchandra?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shubhchandra in Rahatani, Pune is 30 June 2023 — 12 months later than 30 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Shubhchandra?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shubhchandra's builder has filed on MahaRERA, the official one, is 30 June 2023, already 12 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shubhchandra extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "NON AVAILABILITY OF FUNDS AND LABOUR DUE TO FORCE MAJEURE CIRCUMSTANCES.".

What is the RERA number of Shubhchandra?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shubhchandra in Rahatani, Pune is P52100019627.

Is Shubhchandra registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra is registered as P52100019627 and its status is "Completed".

What is the construction status of Shubhchandra?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Shubhchandra have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shubhchandra safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra is registered on MahaRERA as P52100019627, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shubhchandra's possession date changes?

The latest dates are on Shubhchandra's MahaRERA page (P52100019627). GharKundli's Kundli Watch sends a free WhatsApp update on Shubhchandra every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shubhchandra have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra has 3 buildings filed: Wing A with 7 floors; Wing B with 7 floors; Wing C with 7 floors.

How big is the land of Shubhchandra?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra stands on 1,858 sq m of land (about 0.5 acres), with 1,402 sq m of sanctioned built-up area.

What is the track record of Shubhchandra's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Kiran Creators & Developers Through Proprietor MR Kashinath Ganesh Nehete has 11 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 5 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Shubhchandra?

Google Maps has reviews of Shubhchandra written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shubhchandra?

Shubhchandra by M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE is in Rahatani, Pune (pincode 411017), Maharashtra, and is registered on MahaRERA as P52100019627, per GharKundli's check of MahaRERA records. Its boundaries filed there include Hotel sitara Mr Kate.

How many homes are in Shubhchandra?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra has 66 homes in 3 towers registered on MahaRERA.

When was Shubhchandra registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubhchandra was registered on MahaRERA on 14 February 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Shubhchandra?

No court cases are listed for Shubhchandra on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Shubhchandra?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE, which has 10 other projects registered on MahaRERA.

Other projects in Rahatani

All 81 projects in Rahatani (411017) →

Other projects by M/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.