by Sai Anand Properties · Near Nana nani Park, Pune 411048Also near Kondhwa Bk, Kondhwa- Budruk, KatrajRegistered on MahaRERA as “Sai kalash”

What’s in the report? →

Possession date of Anand Sai kalash (MahaRERA P52100019989): 15 March 2027, moved from 15 December 2022 (47 months later). It has 40 homes, 100% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100019989, and currently active. Its completion date has moved from December 2022 to March 2027: 47 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100019989, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Anand Sai kalash?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Anand Sai kalash has moved

  1. 15 December 2022

    Completion date given when the project was registered

  2. 15 December 2024

    Extended at the builder's request (MahaRERA application EXT52100013268)

    Reason the builder gave MahaRERA:
    “Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the par…” Read the full reason“Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the…”
  3. 15 November 2026

    Extended at the builder's request (MahaRERA application EA29072621917)

    Reason the builder gave MahaRERA:
    “The Occupancy Certificate for the project has already been obtained from the Competent Authority. However, due to administrative and procedural reasons, the application for project completion could not be successfully processed on the MahaC…” Read the full reason“The Occupancy Certificate for the project has already been obtained from the Competent Authority. However, due to administrative and procedural reasons, the application for project completion could not be successfully processed on the MahaCRITI portal before the project registration lapsed.The extension is therefore being sought solely to enable access to the MahaCRITI portal for completing the pending statutory compliances, carrying out the necessary corrections, and submitting the project completion application. No construction activity or sale of units is pending, and the project has alr…”
  4. 15 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Anand Sai kalash’s extension records on MahaRERA (P52100019989), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Anand Sai kalash

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100019989
Status
Registered and active
Builder
Sai Anand Properties
Location
Near Nana nani Park, Pune · 411048
Project type
Residential / Group Housing
Registered on
15 Mar 2019
Completion date at registration
December 2022
Latest completion date
March 2027
Delay so far
47 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
40
Sold or booked
100%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Anand Sai kalash, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building A100%100%100%100%
Building B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Building A: covers 6 floors
  • Building B: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anand Sai kalash every 1–2 months.

Anand Sai kalash: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Anand Sai kalash →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Anand Sai kalash: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Anand Sai kalash

What is the possession date of Anand Sai kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Anand Sai kalash in Near Nana nani Park, Pune is 15 March 2027 — 47 months later than 15 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 47 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Anand Sai kalash?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Anand Sai kalash's builder has filed on MahaRERA, the official one, is 15 March 2027, already 47 months later than the 15 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Anand Sai kalash extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash's builder applied to MahaRERA to extend the completion date 2 times: to 15 December 2024, giving the reason "Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the…"; to 15 November 2026, giving the reason "The Occupancy Certificate for the project has already been obtained from the Competent Authority. However, due to administrative and procedural reasons, the application for project completion could not be successfully processed on the MahaCRITI portal before the project registration lapsed.The extension is therefore being sought solely to enable access to the MahaCRITI portal for completing the pending statutory compliances, carrying out the necessary corrections, and submitting the project completion application. No construction activity or sale of units is pending, and the project has alr…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Anand Sai kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Anand Sai kalash in Near Nana nani Park, Pune is P52100019989.

Is Anand Sai kalash registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash is registered as P52100019989 and its status is "Registered and active".

What is the current construction status of Anand Sai kalash? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Anand Sai kalash have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Anand Sai kalash safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash is registered on MahaRERA as P52100019989, its completion date has moved 47 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Anand Sai kalash?

Anand Sai kalash is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Anand Sai kalash?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Anand Sai kalash: gharkundli.com/tools/property-cost-calculator

Has Anand Sai kalash received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash is still under construction, with 15 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Anand Sai kalash uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Anand Sai kalash was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Anand Sai kalash's possession date changes?

The latest dates are on Anand Sai kalash's MahaRERA page (P52100019989). GharKundli's Kundli Watch sends a free WhatsApp update on Anand Sai kalash every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Anand Sai kalash have?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash has 2 buildings filed: Building A with 6 floors and 20 units; Building B with 5 floors and 20 units.

How big is the land of Anand Sai kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash stands on 1,600 sq m of land (about 0.4 acres), with 1,760 sq m of sanctioned built-up area.

What are the reviews of Anand Sai kalash?

Google Maps has reviews of Anand Sai kalash written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Anand Sai kalash?

Anand Sai kalash by Sai Anand Properties is in Near Nana nani Park, Pune, pincode 411048 (near Kondhwa Bk, Kondhwa- Budruk, Katraj), Maharashtra, and is registered on MahaRERA as P52100019989, per GharKundli's check of MahaRERA records. Its land is filed as S No 66-1-6, 66-5-34A. GharKundli lists all 369 MahaRERA projects in N I B M (411048).

How many flats are in Anand Sai kalash, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash has 40 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Anand Sai kalash registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Anand Sai kalash was registered on MahaRERA on 15 March 2019. GharKundli did not find a title report on the land on file there.

Does Anand Sai kalash have any legal issues or court cases?

No court cases are listed for Anand Sai kalash on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Anand Sai kalash?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sai Anand Properties.

All projects with possession due in 2027 in Pune →

Other projects in Haveli

All 369 projects in N I B M (411048) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.