VIVA CITY - A3

by VIVA WINNER VENTURE REALTORS LLP · Virar West, Palghar

Possession date of VIVA CITY - A3: 30 October 2027, moved from 30 June 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000003245, and currently active. Its completion date has moved from June 2022 to October 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VIVA CITY - A3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VIVA CITY - A3 has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 29 June 2023

    Extended at the builder's request (MahaRERA application EXT99000012095)

    Reason the builder gave MahaRERA:
    “2. I/ We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all t…” Read the full reason“2. I/ We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. In addition, construction activities has severely been affected due to lockdown imposed by concerned authorities, Migration of labor forces and material supply etc. for past 1.5 year.”
  3. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT99000016905)

    Reason the builder gave MahaRERA:
    “We are highly regretful for the delay in handing over the possession of the above mentioned building. Construction progress and related activities were affected highly due to COVID - 19 pandemic in 2020-21, also current unfavorable market s…” Read the full reason“We are highly regretful for the delay in handing over the possession of the above mentioned building. Construction progress and related activities were affected highly due to COVID - 19 pandemic in 2020-21, also current unfavorable market scenario for the real estate industry has contributed in delay and majority of the developers in the industry have seen downfall in the business over the last few years”
  4. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT99000024178)

    Reason the builder gave MahaRERA:
    “We are highly regretful for the delay in handing over the possession of the said project. We are in the final phase of completion of the project. Progress of the work hampered due to the cash flow which was impacted due to current market sc…” Read the full reason“We are highly regretful for the delay in handing over the possession of the said project. We are in the final phase of completion of the project. Progress of the work hampered due to the cash flow which was impacted due to current market scenario in the region. Also, we faced material supply issue which also affected the progress of the work causing delay beyond our control.”
  5. 30 June 2026

    Extended at the builder's request (MahaRERA application EA25072502193)

    Reason the builder gave MahaRERA:
    “We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the dev…” Read the full reason“We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. This has caused us significant in issue financially which in turn affected the progress. However, we have addressed these issues and currently the activities are in full flow.”
  6. 30 June 2027

    Extended at the builder's request (MahaRERA application EA28072621913)

    Reason the builder gave MahaRERA:
    “We are highly regretful for the delay in handing over the possession of the abovementioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the deve…” Read the full reason“We are highly regretful for the delay in handing over the possession of the abovementioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. This has caused us significant in issue financially which in turn affected the progress. However, we have addressed these issues and currently the activities are in full flow.”
  7. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VIVA CITY - A3’s extension records on MahaRERA (P99000003245), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VIVA CITY - A3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000003245
Status
Registered and active
Builder
VIVA WINNER VENTURE REALTORS LLP
Location
Virar West, Palghar · 401303
Project type
Residential / Group Housing
Registered on
5 Aug 2017
Completion date at registration
June 2022
Latest completion date
October 2027
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
128
Sold or booked
71%
Towers
1
Complaints on MahaRERA
7
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of VIVA CITY - A3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A3100%100%100%96%

Commencement certificate (CC), as filed on MahaRERA

  • A3: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIVA CITY - A3 every month.

VIVA CITY - A3: buildings, flats and land, as filed on MahaRERA

  • Buildings: A3 (17 floors, 140 units)
  • Car parking: 9 covered, 55 open
  • Land: 2,409 sq m (about 0.6 acres) · sanctioned built-up 5,567 sq m · recreational space 5,153 sq m

The builder’s record and reviews

Viva Homes (a group of 4 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 36 months late); 10 lapsed. 25 complaints on MahaRERA across 11 projects.

Read Google reviews of VIVA CITY - A3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VIVA CITY - A3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VIVA CITY - A3

What is the possession date of VIVA CITY - A3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VIVA CITY - A3 in Virar West, Palghar is 30 October 2027 — 60 months later than 30 June 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VIVA CITY - A3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VIVA CITY - A3's builder has filed on MahaRERA, the official one, is 30 October 2027, already 60 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VIVA CITY - A3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3's builder applied to MahaRERA to extend the completion date 5 times: to 29 June 2023, giving the reason "2. I/ We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. In addition, construction activities has severely been affected due to lockdown imposed by concerned authorities, Migration of labor forces and material supply etc. for past 1.5 year."; to 29 June 2024, giving the reason "We are highly regretful for the delay in handing over the possession of the above mentioned building. Construction progress and related activities were affected highly due to COVID - 19 pandemic in 2020-21, also current unfavorable market scenario for the real estate industry has contributed in delay and majority of the developers in the industry have seen downfall in the business over the last few years"; to 30 June 2025, giving the reason "We are highly regretful for the delay in handing over the possession of the said project. We are in the final phase of completion of the project. Progress of the work hampered due to the cash flow which was impacted due to current market scenario in the region. Also, we faced material supply issue which also affected the progress of the work causing delay beyond our control."; to 30 June 2026, giving the reason "We are highly regretful for the delay in handing over the possession of the above mentioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. This has caused us significant in issue financially which in turn affected the progress. However, we have addressed these issues and currently the activities are in full flow."; to 30 June 2027, giving the reason "We are highly regretful for the delay in handing over the possession of the abovementioned building due to demonization and current market scenario which is totally unfavorable especially for the real estate industry and almost all the developers in the industry have seen downfall in the business over the last few years. This has caused us significant in issue financially which in turn affected the progress. However, we have addressed these issues and currently the activities are in full flow.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VIVA CITY - A3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VIVA CITY - A3 in Virar West, Palghar is P99000003245.

Is VIVA CITY - A3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3 is registered as P99000003245 and its status is "Registered and active".

What is the construction status of VIVA CITY - A3?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does VIVA CITY - A3 have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is VIVA CITY - A3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3 is registered on MahaRERA as P99000003245, its completion date has moved 60 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does VIVA CITY - A3 have other wings or phases?

Yes. MahaRERA lists 8 other registrations of the same project, each with its own possession date: VIVA CITY - A1 (P99000004874); VIVA CITY-A2 (P99000008341); VIVA CITY - A4 (P99000003476, possession 29 Oct 2027); VIVA CITY - A5 (P99000002985, possession 30 Oct 2027); VIVA CITY - A8 (P99000004130, possession 29 Jun 2025); VIVA CITY -A9 (P99000003243, possession 29 Jun 2025); and 2 more. Check that your agreement names the registration of your own wing.

How can I get updates if VIVA CITY - A3's possession date changes?

The latest dates are on VIVA CITY - A3's MahaRERA page (P99000003245). GharKundli's Kundli Watch sends a free WhatsApp update on VIVA CITY - A3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VIVA CITY - A3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3 has one building filed: A3 with 17 floors and 140 units.

How much parking does VIVA CITY - A3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 9 covered and 55 open car parking spaces for VIVA CITY - A3.

How big is the land of VIVA CITY - A3?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3 stands on 2,409 sq m of land (about 0.6 acres), with 5,567 sq m of sanctioned built-up area and 5,153 sq m of recreational open space.

What is the track record of VIVA CITY - A3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Viva Homes (a group of 4 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 36 months late); 10 lapsed. 25 complaints on MahaRERA across 11 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VIVA CITY - A3?

Google Maps has reviews of VIVA CITY - A3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VIVA CITY - A3?

VIVA CITY - A3 by VIVA WINNER VENTURE REALTORS LLP is in Virar West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000003245, per GharKundli's check of MahaRERA records.

How many homes are in VIVA CITY - A3?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3 has 128 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.

When was VIVA CITY - A3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIVA CITY - A3 was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VIVA CITY - A3?

No court cases are listed for VIVA CITY - A3 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of VIVA CITY - A3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIVA WINNER VENTURE REALTORS LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401303

All 210 projects in Virar West (401303) →

Other projects by VIVA WINNER VENTURE REALTORS LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.