Skip to content
GharKundli

CHAANDRAI CAPITAL

by SBS PROPERTIES (Chaandrai) · Ambgaon Bk, Pune

Possession: CHAANDRAI CAPITAL is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100022361. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about CHAANDRAI CAPITAL?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CHAANDRAI CAPITAL has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT52100012225)

    Reason the builder gave MahaRERA:
    “AS PER REVISED UDPCR (ADDITINAOL FSI POTENTIAL) WE GET SANCTION ON 27/05/2021.UDPCR IS PUBLISED IN MONTH DEC 2020. THEN COVID PANDAMIC.TDR POTENTIAL TILL PENDING DUE TO PMC AND STATEMENT GOVERMENT CIRCULAR NO TPS1818/1267/P C 237/18/NAVI-13…” Read the full reason“AS PER REVISED UDPCR (ADDITINAOL FSI POTENTIAL) WE GET SANCTION ON 27/05/2021.UDPCR IS PUBLISED IN MONTH DEC 2020. THEN COVID PANDAMIC.TDR POTENTIAL TILL PENDING DUE TO PMC AND STATEMENT GOVERMENT CIRCULAR NO TPS1818/1267/P C 237/18/NAVI-13 DATED 06.08.2021”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52100016527)

    Reason the builder gave MahaRERA:
    “We SBS PROPERTIES is developing a project CHAANDRAI CAPITAL and we were due to complete the project on 31-03-2023. Due to the Covid-19 pandemic we were not able to construct anymore because of lack of labour contractors and the poor market…” Read the full reason“We SBS PROPERTIES is developing a project CHAANDRAI CAPITAL and we were due to complete the project on 31-03-2023. Due to the Covid-19 pandemic we were not able to construct anymore because of lack of labour contractors and the poor market condition we were unable to complete the project within the due time. Hence, we request you to kindly allow us an extension till the extension date for 31-03-2024.”

Source: CHAANDRAI CAPITAL’s extension records on MahaRERA (P52100022361), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CHAANDRAI CAPITAL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100022361
Status
Completed
Builder
SBS PROPERTIES
Location
Ambgaon Bk, Pune · 411046
Project type
Others
Registered on
16 Sep 2019
Completion date at registration
June 2022
Latest completion date
March 2024
Delay so far
21 months
Homes
158
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of CHAANDRAI CAPITAL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B WING100%100%100%100%
A WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CHAANDRAI CAPITAL every month.

CHAANDRAI CAPITAL: buildings, flats and land, as filed on MahaRERA

  • Buildings: B WING (11 floors) · A WING (11 floors)
  • Land: 3,950 sq m (about 1.0 acres) · sanctioned built-up 10,366 sq m · recreational space 395 sq m

The builder’s record and reviews

SBS Prroperties (a group of 7 linked companies) has 9 projects on MahaRERA since 2019, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 5 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of CHAANDRAI CAPITAL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CHAANDRAI CAPITAL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CHAANDRAI CAPITAL

What is the possession date of CHAANDRAI CAPITAL?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CHAANDRAI CAPITAL in Ambgaon Bk, Pune is 31 March 2024 — 21 months later than 30 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for CHAANDRAI CAPITAL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CHAANDRAI CAPITAL's builder has filed on MahaRERA, the official one, is 31 March 2024, already 21 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CHAANDRAI CAPITAL extended?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2023, giving the reason "AS PER REVISED UDPCR (ADDITINAOL FSI POTENTIAL) WE GET SANCTION ON 27/05/2021.UDPCR IS PUBLISED IN MONTH DEC 2020. THEN COVID PANDAMIC.TDR POTENTIAL TILL PENDING DUE TO PMC AND STATEMENT GOVERMENT CIRCULAR NO TPS1818/1267/P C 237/18/NAVI-13 DATED 06.08.2021"; to 31 March 2024, giving the reason "We SBS PROPERTIES is developing a project CHAANDRAI CAPITAL and we were due to complete the project on 31-03-2023. Due to the Covid-19 pandemic we were not able to construct anymore because of lack of labour contractors and the poor market condition we were unable to complete the project within the due time. Hence, we request you to kindly allow us an extension till the extension date for 31-03-2024.".

What is the RERA number of CHAANDRAI CAPITAL?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CHAANDRAI CAPITAL in Ambgaon Bk, Pune is P52100022361.

Is CHAANDRAI CAPITAL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL is registered as P52100022361 and its status is "Completed".

What is the construction status of CHAANDRAI CAPITAL?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does CHAANDRAI CAPITAL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is CHAANDRAI CAPITAL safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL is registered on MahaRERA as P52100022361, its MahaRERA status is "Completed", its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CHAANDRAI CAPITAL's possession date changes?

The latest dates are on CHAANDRAI CAPITAL's MahaRERA page (P52100022361). GharKundli's Kundli Watch sends a free WhatsApp update on CHAANDRAI CAPITAL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CHAANDRAI CAPITAL have?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL has 2 buildings filed: B WING with 11 floors; A WING with 11 floors.

How big is the land of CHAANDRAI CAPITAL?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL stands on 3,950 sq m of land (about 1.0 acres), with 10,366 sq m of sanctioned built-up area and 395 sq m of recreational open space.

What is the track record of CHAANDRAI CAPITAL's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), SBS Prroperties (a group of 7 linked companies) has 9 projects on MahaRERA since 2019, this one included. Of the 8 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months); 5 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of CHAANDRAI CAPITAL?

Google Maps has reviews of CHAANDRAI CAPITAL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CHAANDRAI CAPITAL?

CHAANDRAI CAPITAL by SBS PROPERTIES (Chaandrai) is in Ambgaon Bk, Pune (pincode 411046), Maharashtra, and is registered on MahaRERA as P52100022361, per GharKundli's check of MahaRERA records.

How many homes are in CHAANDRAI CAPITAL?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL has 158 homes in 2 towers registered on MahaRERA.

When was CHAANDRAI CAPITAL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CHAANDRAI CAPITAL was registered on MahaRERA on 16 September 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on CHAANDRAI CAPITAL?

No court cases are listed for CHAANDRAI CAPITAL on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of CHAANDRAI CAPITAL?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SBS PROPERTIES, the company Chaandrai files this project under.

Other projects in Haveli

All 216 projects in Katraj (411046) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.