Haware Grace
by UJJWALA SATISH HAWARE · Kasapate Vasti, Pune 411057
What’s in the report? →Possession: Haware Grace (MahaRERA P52100022058) is marked completed on MahaRERA. It has 36 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100022058. Status: Completed.
Source: MahaRERA website — records for P52100022058, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Haware Grace?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Haware Grace
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100022058
- Status
- Completed
- Builder
- UJJWALA SATISH HAWARE
- Location
- Kasapate Vasti, Pune · 411057
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2019
- Completion date at registration
- December 2024
- Latest completion date
- December 2024
- Homes
- 36
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Haware Grace, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building A | 100% | 25% | 10% | 10% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Haware Grace every 1–2 months.
Haware Grace: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A (6 floors)
- Land: 1,206 sq m (about 0.3 acres) · sanctioned built-up 876 sq m
- Boundaries filed include: Road with 24 mtr
- Land, as filed: Survey No208/4
- Map: Get directions
The builder’s record and reviews
Haware Engineers AND Builders (a group of 5 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 17 months); 3 still being built, none past the promised date yet. 9 complaints on MahaRERA across 2 projects.
Read Google reviews of Haware Grace →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Haware Grace: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Haware Grace
What is the possession date of Haware Grace?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Haware Grace in Kasapate Vasti, Pune is 30 December 2024.
Is the builder's possession date different from the MahaRERA date for Haware Grace?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Haware Grace's builder has filed on MahaRERA, the official one, is 30 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Haware Grace?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Haware Grace in Kasapate Vasti, Pune is P52100022058.
Is Haware Grace registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace is registered as P52100022058 and its status is "Completed".
What is the current construction status of Haware Grace? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace's status on MahaRERA is "Completed". As filed by the builder, slab work on Building A is 25% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Haware Grace have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Haware Grace safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace is registered on MahaRERA as P52100022058, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Haware Grace?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Haware Grace?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Haware Grace: gharkundli.com/tools/property-cost-calculator
Has Haware Grace received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Haware Grace completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace is marked completed on MahaRERA, and the completion date filed there is 30 December 2024. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Haware Grace uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Haware Grace was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Haware Grace's possession date changes?
The latest dates are on Haware Grace's MahaRERA page (P52100022058). GharKundli's Kundli Watch sends a free WhatsApp update on Haware Grace every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Haware Grace have?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace has one building filed: Building A with 6 floors.
How big is the land of Haware Grace?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace stands on 1,206 sq m of land (about 0.3 acres), with 876 sq m of sanctioned built-up area.
What is the track record of Haware Grace's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Engineers AND Builders (a group of 5 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 17 months); 3 still being built, none past the promised date yet. 9 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Haware Grace?
Google Maps has reviews of Haware Grace written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Haware Grace?
Haware Grace by UJJWALA SATISH HAWARE is in Kasapate Vasti, Pune, pincode 411057, Maharashtra, and is registered on MahaRERA as P52100022058, per GharKundli's check of MahaRERA records. Its boundaries filed there include Road with 24 mtr. Its land is filed as Survey No208/4. GharKundli lists all 644 MahaRERA projects in Wakad (411057).
How many flats are in Haware Grace?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace has 36 homes in 1 tower registered on MahaRERA.
When was Haware Grace registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Haware Grace was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Does Haware Grace have any legal issues or court cases?
No court cases are listed for Haware Grace on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Haware Grace?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is UJJWALA SATISH HAWARE, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Haware Grace
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulshi
- Nirman Serenopolis
- Signature Park Phase - I
- Rohan Harita Phase 4
- Vyomora Phase 1
- Mahindra Rivenza Phase 1
- Mahindra Rivenza Phase 2
- Lotus Crest
- West World
Other projects by UJJWALA SATISH HAWARE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.