SPRING VALLEY

by R K ICON ASSOCIATES · Magarpatta, Pune

Possession: SPRING VALLEY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100028832. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SPRING VALLEY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SPRING VALLEY has moved

  1. 30 September 2023

    Completion date given when the project was registered

  2. 29 September 2024

    Extended at the builder's request (MahaRERA application EXT52100017615)

    Reason the builder gave MahaRERA:
    “As per our first sanction plan we had units from 3rd to 9th floor, whose occupancy certificate is already received and uploaded on website. There is addition of 2 floors (10th and 11th floor) in the new revised plan dated 07.03.2022,we have…” Read the full reason“As per our first sanction plan we had units from 3rd to 9th floor, whose occupancy certificate is already received and uploaded on website. There is addition of 2 floors (10th and 11th floor) in the new revised plan dated 07.03.2022,we have almost completed the project till 11th floor,but we need the occupancy and completion certificate so we need to extend the Project completion date by one year.”

Source: SPRING VALLEY’s extension records on MahaRERA (P52100028832), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SPRING VALLEY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100028832
Status
Completed
Builder
R K ICON ASSOCIATES
Location
Magarpatta, Pune · 412201
Project type
Residential / Group Housing
Registered on
5 Apr 2021
Completion date at registration
September 2023
Latest completion date
September 2024
Delay so far
12 months
Homes
51
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SPRING VALLEY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ORCHID100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SPRING VALLEY every month.

SPRING VALLEY: buildings, flats and land, as filed on MahaRERA

  • Buildings: ORCHID (14 floors)
  • Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 3,595 sq m · recreational space 1,168 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SPRING VALLEY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SPRING VALLEY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SPRING VALLEY

What is the possession date of SPRING VALLEY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SPRING VALLEY in Magarpatta, Pune is 29 September 2024 — 12 months later than 30 September 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SPRING VALLEY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SPRING VALLEY's builder has filed on MahaRERA, the official one, is 29 September 2024, already 12 months later than the 30 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SPRING VALLEY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY's builder applied to MahaRERA to extend the completion date once: to 29 September 2024, giving the reason "As per our first sanction plan we had units from 3rd to 9th floor, whose occupancy certificate is already received and uploaded on website. There is addition of 2 floors (10th and 11th floor) in the new revised plan dated 07.03.2022,we have almost completed the project till 11th floor,but we need the occupancy and completion certificate so we need to extend the Project completion date by one year.".

What is the RERA number of SPRING VALLEY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SPRING VALLEY in Magarpatta, Pune is P52100028832.

Is SPRING VALLEY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY is registered as P52100028832 and its status is "Completed".

What is the construction status of SPRING VALLEY?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY's status on MahaRERA is "Completed". As filed by the builder, slab work on ORCHID is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SPRING VALLEY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SPRING VALLEY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY is registered on MahaRERA as P52100028832, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SPRING VALLEY's possession date changes?

The latest dates are on SPRING VALLEY's MahaRERA page (P52100028832). GharKundli's Kundli Watch sends a free WhatsApp update on SPRING VALLEY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SPRING VALLEY have?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY has one building filed: ORCHID with 14 floors.

How big is the land of SPRING VALLEY?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY stands on 1,000 sq m of land (about 0.2 acres), with 3,595 sq m of sanctioned built-up area and 1,168 sq m of recreational open space.

Where can I read reviews of SPRING VALLEY?

Google Maps has reviews of SPRING VALLEY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SPRING VALLEY?

SPRING VALLEY by R K ICON ASSOCIATES is in Magarpatta, Pune (pincode 412201), Maharashtra, and is registered on MahaRERA as P52100028832, per GharKundli's check of MahaRERA records.

How many homes are in SPRING VALLEY?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY has 51 homes in 1 tower registered on MahaRERA.

When was SPRING VALLEY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SPRING VALLEY was registered on MahaRERA on 5 April 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on SPRING VALLEY?

No court cases are listed for SPRING VALLEY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SPRING VALLEY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is R K ICON ASSOCIATES.

Other projects in Haveli

All 31 projects in Kadamwakwasti (412201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.