SHRI SAMARTH

by SAMARTH CONSTRUCTION · Shukrawar Peth, PuneAlso near Pune City, Kasba Peth, S.P. College

Possession date of SHRI SAMARTH: 30 November 2023, moved from 1 December 2022 (11 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100023397. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (November 2023) has passed.

What do you want to know about SHRI SAMARTH?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRI SAMARTH has moved

  1. 1 December 2022

    Completion date given when the project was registered

  2. 30 November 2023

    Extended at the builder's request (MahaRERA application EXT52100013626)

    Reason the builder gave MahaRERA: “Respected sir, Due to less sell of flats we are having financial problems. Till 90℅ work of project completed. please issue us Extension certificate to complete remaining work.”

Source: SHRI SAMARTH’s extension records on MahaRERA (P52100023397), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRI SAMARTH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100023397
Status
Lapsed (registration period ended)
Builder
SAMARTH CONSTRUCTION
Location
Shukrawar Peth, Pune · 411002
Project type
Others
Registered on
12 Dec 2019
Completion date at registration
December 2022
Latest completion date
November 2023
Delay so far
11 months
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of SHRI SAMARTH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHRI SAMARTH100%100%100%99%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI SAMARTH every month.

SHRI SAMARTH: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHRI SAMARTH (7 floors)
  • Land: 319 sq m (about 0.1 acres) · sanctioned built-up 494 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHRI SAMARTH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRI SAMARTH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRI SAMARTH

What is the possession date of SHRI SAMARTH?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHRI SAMARTH in Shukrawar Peth, Pune is 30 November 2023 — 11 months later than 1 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHRI SAMARTH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI SAMARTH's builder has filed on MahaRERA, the official one, is 30 November 2023, already 11 months later than the 1 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRI SAMARTH extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH's builder applied to MahaRERA to extend the completion date once: to 30 November 2023, giving the reason "Respected sir, Due to less sell of flats we are having financial problems. Till 90℅ work of project completed. please issue us Extension certificate to complete remaining work.".

What is the RERA number of SHRI SAMARTH?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHRI SAMARTH in Shukrawar Peth, Pune is P52100023397.

Is SHRI SAMARTH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH is registered as P52100023397 and its status is "Lapsed (registration period ended)".

What is the construction status of SHRI SAMARTH?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHRI SAMARTH is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHRI SAMARTH have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHRI SAMARTH safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH is registered on MahaRERA as P52100023397, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRI SAMARTH's possession date changes?

The latest dates are on SHRI SAMARTH's MahaRERA page (P52100023397). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI SAMARTH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRI SAMARTH have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH has one building filed: SHRI SAMARTH with 7 floors.

How big is the land of SHRI SAMARTH?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH stands on 319 sq m of land (about 0.1 acres), with 494 sq m of sanctioned built-up area.

Where can I read reviews of SHRI SAMARTH?

Google Maps has reviews of SHRI SAMARTH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRI SAMARTH?

SHRI SAMARTH by SAMARTH CONSTRUCTION is in Shukrawar Peth, Pune (pincode 411002), near Pune City, Kasba Peth, S.P. College, Maharashtra, and is registered on MahaRERA as P52100023397, per GharKundli's check of MahaRERA records.

How many homes are in SHRI SAMARTH?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH has 17 homes in 1 tower registered on MahaRERA.

When was SHRI SAMARTH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI SAMARTH was registered on MahaRERA on 12 December 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRI SAMARTH?

No court cases are listed for SHRI SAMARTH on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHRI SAMARTH?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAMARTH CONSTRUCTION, which has 5 other projects registered on MahaRERA.

Other projects in pincode 411002

All 74 projects in Shukrawar Peth (411002) →

Other projects by SAMARTH CONSTRUCTION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.