Possession: Skyways Esfera B Wing (MahaRERA P52100025786) is marked completed on MahaRERA. It has 109 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100025786. Status: Completed.

Source: MahaRERA website — records for P52100025786, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Skyways Esfera B Wing?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Skyways Esfera B Wing has moved

  1. 31 October 2022

    Completion date given when the project was registered

  2. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT52100010770)

    Reason the builder gave MahaRERA: “DUE TO COVID-19 AND SHORTAGE OF LABOUR”
  3. 30 March 2024

    Revised completion date on MahaRERA

Source: Skyways Esfera B Wing’s extension records on MahaRERA (P52100025786), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Skyways Esfera B Wing

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100025786
Status
Completed
Builder
Moze Associates
Location
Lohegaon, Pune · 411047
Project type
Residential / Group Housing
Registered on
14 Jul 2020
Completion date at registration
October 2022
Latest completion date
March 2024
Delay so far
17 months
Homes
109
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Skyways Esfera B Wing, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B Wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Skyways Esfera B Wing every 1–2 months.

Skyways Esfera B Wing: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Moze Associates (a group of 5 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 11 months); 3 still being built, 2 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Skyways Esfera B Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Skyways Esfera B Wing: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Skyways Esfera B Wing

What is the possession date of Skyways Esfera B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Skyways Esfera B Wing in Lohegaon, Pune is 30 March 2024 — 17 months later than 31 October 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Skyways Esfera B Wing?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Skyways Esfera B Wing's builder has filed on MahaRERA, the official one, is 30 March 2024, already 17 months later than the 31 October 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Skyways Esfera B Wing extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing's builder applied to MahaRERA to extend the completion date once: to 30 September 2023, giving the reason "DUE TO COVID-19 AND SHORTAGE OF LABOUR".

What is the RERA number of Skyways Esfera B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Skyways Esfera B Wing in Lohegaon, Pune is P52100025786.

Is Skyways Esfera B Wing registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing is registered as P52100025786 and its status is "Completed".

What is the current construction status of Skyways Esfera B Wing? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing's status on MahaRERA is "Completed". As filed by the builder, slab work on B Wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Skyways Esfera B Wing have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Skyways Esfera B Wing safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing is registered on MahaRERA as P52100025786, its MahaRERA status is "Completed", its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Skyways Esfera B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Skyways Esfera B Wing?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Skyways Esfera B Wing: gharkundli.com/tools/property-cost-calculator

Has Skyways Esfera B Wing received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Skyways Esfera B Wing completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing is marked completed on MahaRERA, and the completion date filed there is 30 March 2024. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Skyways Esfera B Wing uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Skyways Esfera B Wing was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Skyways Esfera B Wing's possession date changes?

The latest dates are on Skyways Esfera B Wing's MahaRERA page (P52100025786). GharKundli's Kundli Watch sends a free WhatsApp update on Skyways Esfera B Wing every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Skyways Esfera B Wing have?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing has one building filed: B Wing with 15 floors.

How big is the land of Skyways Esfera B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing stands on 2,003 sq m of land (about 0.5 acres), with 10,573 sq m of sanctioned built-up area.

What is the track record of Skyways Esfera B Wing's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Moze Associates (a group of 5 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 11 months); 3 still being built, 2 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Skyways Esfera B Wing?

Google Maps has reviews of Skyways Esfera B Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Skyways Esfera B Wing?

Skyways Esfera B Wing by Moze Associates (Pranam) is in Lohegaon, Pune, pincode 411047 (near Dhanori, Shivajinagar, Parande Park), Maharashtra, and is registered on MahaRERA as P52100025786, per GharKundli's check of MahaRERA records. Its land is filed as 284/3, 284/4. GharKundli lists all 196 MahaRERA projects in Lohegaon (411047).

How many flats are in Skyways Esfera B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing has 109 homes in 1 tower registered on MahaRERA.

When was Skyways Esfera B Wing registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyways Esfera B Wing was registered on MahaRERA on 14 July 2020. GharKundli did not find a title report on the land on file there.

Does Skyways Esfera B Wing have any legal issues or court cases?

No court cases are listed for Skyways Esfera B Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Skyways Esfera B Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Moze Associates, the company Pranam files this project under, which has 3 other projects registered on MahaRERA.

Other projects in Lohegaon (411047)

All 196 projects in Lohegaon (411047) →

Other projects by Moze Associates

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.