Skip to content
GharKundli

Kekarav Phase I

by SHREM TRADING LLP · Bavdhan, Pune

Possession date of Kekarav Phase I: 31 March 2024, moved from 31 July 2022 (20 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100025894. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about Kekarav Phase I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Kekarav Phase I has moved

  1. 31 July 2022

    Completion date given when the project was registered

  2. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT52100012570)

    Reason the builder gave MahaRERA:
    “All the project facilities are ready only landscape & amenities are under construction which requires additional time. In addition to this, the project situated in hilly area of Bavdhan and due to heavy rains in the said region during monso…” Read the full reason“All the project facilities are ready only landscape & amenities are under construction which requires additional time. In addition to this, the project situated in hilly area of Bavdhan and due to heavy rains in the said region during monsoon season project developments activities on ground cannot be carried out for 4-6 months. (iii) This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks of Customers’ need the RERA Certificate showing availability of project completion date.”
  3. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT52100015401)

    Reason the builder gave MahaRERA:
    “All the project facilities are ready only landscaping work in under construction which requires additional time. The extension is needed as, while executing the agreement of sale unsold plots with registering authority and financing banks o…” Read the full reason“All the project facilities are ready only landscaping work in under construction which requires additional time. The extension is needed as, while executing the agreement of sale unsold plots with registering authority and financing banks of customers need the RERA certificate showing availability of project completion date.”
  4. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52100017642)

    Reason the builder gave MahaRERA:
    “i. Amenities like club house & Landscaping Work are under construction which requires additional time. ii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks Custo…” Read the full reason“i. Amenities like club house & Landscaping Work are under construction which requires additional time. ii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks Customers need the RERA Certificate showing the availability of the project completion date.”

Source: Kekarav Phase I’s extension records on MahaRERA (P52100025894), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kekarav Phase I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100025894
Status
Lapsed (registration period ended)
Builder
SHREM TRADING LLP
Location
Bavdhan, Pune · 411021
Project type
Plotted
Registered on
27 Jul 2020
Completion date at registration
July 2022
Latest completion date
March 2024
Delay so far
20 months
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Kekarav Phase I: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shrem Trading has 4 projects on MahaRERA since 2020, this one included. Of the 4 GharKundli has checked: 3 still being built, 2 past the promised date (typically 43 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Kekarav Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kekarav Phase I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Kekarav Phase I

What is the possession date of Kekarav Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kekarav Phase I in Bavdhan, Pune is 31 March 2024 — 20 months later than 31 July 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Kekarav Phase I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kekarav Phase I's builder has filed on MahaRERA, the official one, is 31 March 2024, already 20 months later than the 31 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kekarav Phase I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Kekarav Phase I's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2023, giving the reason "All the project facilities are ready only landscape & amenities are under construction which requires additional time. In addition to this, the project situated in hilly area of Bavdhan and due to heavy rains in the said region during monsoon season project developments activities on ground cannot be carried out for 4-6 months. (iii) This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks of Customers’ need the RERA Certificate showing availability of project completion date."; to 31 July 2023, giving the reason "All the project facilities are ready only landscaping work in under construction which requires additional time. The extension is needed as, while executing the agreement of sale unsold plots with registering authority and financing banks of customers need the RERA certificate showing availability of project completion date."; to 31 March 2024, giving the reason "i. Amenities like club house & Landscaping Work are under construction which requires additional time. ii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks Customers need the RERA Certificate showing the availability of the project completion date.".

What is the RERA number of Kekarav Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kekarav Phase I in Bavdhan, Pune is P52100025894.

Is Kekarav Phase I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kekarav Phase I is registered as P52100025894 and its status is "Lapsed (registration period ended)".

What is the construction status of Kekarav Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Kekarav Phase I's status on MahaRERA is "Lapsed (registration period ended)". GharKundli's full report compares construction progress with the deadline.

Does Kekarav Phase I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Kekarav Phase I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Kekarav Phase I is registered on MahaRERA as P52100025894, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 20 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Kekarav Phase I have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Kekarav Phase II (P52100031548, possession 31 Jul 2028); Kekarav Phase III (P52100034729, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.

How can I get updates if Kekarav Phase I's possession date changes?

The latest dates are on Kekarav Phase I's MahaRERA page (P52100025894). GharKundli's Kundli Watch sends a free WhatsApp update on Kekarav Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Kekarav Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Kekarav Phase I stands on 36,576 sq m of land (about 9.0 acres), with 22,478 sq m of sanctioned built-up area and 607 sq m of recreational open space.

What is the track record of Kekarav Phase I's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shrem Trading has 4 projects on MahaRERA since 2020, this one included. Of the 4 GharKundli has checked: 3 still being built, 2 past the promised date (typically 43 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Kekarav Phase I?

Google Maps has reviews of Kekarav Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Kekarav Phase I?

Kekarav Phase I by SHREM TRADING LLP is in Bavdhan, Pune (pincode 411021), Maharashtra, and is registered on MahaRERA as P52100025894, per GharKundli's check of MahaRERA records.

When was Kekarav Phase I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kekarav Phase I was registered on MahaRERA on 27 July 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Kekarav Phase I?

No court cases are listed for Kekarav Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Kekarav Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREM TRADING LLP, which has 3 other projects registered on MahaRERA.

Other projects in Bavdhan

All 210 projects in Armament (411021) →

Other projects by SHREM TRADING LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.