by CHOULWAR CONSTRUCTION · Bavdhan, Pune

Possession: SAI KUNJ is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100025939. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAI KUNJ?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI KUNJ has moved

  1. 31 January 2023

    Completion date given when the project was registered

  2. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT52100013610)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 PANDEMIC FUND ISSUES ARISES WE NEED TO EXTEND PROJECT FOR 6 MONTH ONLY KINDLY ALLOW THE REVISED PERIOD”

Source: SAI KUNJ’s extension records on MahaRERA (P52100025939), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI KUNJ

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100025939
Status
Completed
Builder
CHOULWAR CONSTRUCTION
Location
Bavdhan, Pune · 411021
Project type
Residential / Group Housing
Registered on
31 Jul 2020
Completion date at registration
January 2023
Latest completion date
July 2023
Delay so far
6 months
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SAI KUNJ, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI KUNJ0%100%90%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI KUNJ every month.

SAI KUNJ: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI KUNJ (5 floors)
  • Land: 286 sq m (about 0.1 acres) · sanctioned built-up 286 sq m
  • Boundaries filed include: GOVERNMENT ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI KUNJ →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI KUNJ: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI KUNJ

What is the possession date of SAI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI KUNJ in Bavdhan, Pune is 31 July 2023 — 6 months later than 31 January 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI KUNJ?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI KUNJ's builder has filed on MahaRERA, the official one, is 31 July 2023, already 6 months later than the 31 January 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI KUNJ extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ's builder applied to MahaRERA to extend the completion date once: to 31 July 2023, giving the reason "DUE TO COVID 19 PANDEMIC FUND ISSUES ARISES WE NEED TO EXTEND PROJECT FOR 6 MONTH ONLY KINDLY ALLOW THE REVISED PERIOD".

What is the RERA number of SAI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI KUNJ in Bavdhan, Pune is P52100025939.

Is SAI KUNJ registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ is registered as P52100025939 and its status is "Completed".

What is the construction status of SAI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ's status on MahaRERA is "Completed". As filed by the builder, slab work on SAI KUNJ is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does SAI KUNJ have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAI KUNJ safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ is registered on MahaRERA as P52100025939, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI KUNJ's possession date changes?

The latest dates are on SAI KUNJ's MahaRERA page (P52100025939). GharKundli's Kundli Watch sends a free WhatsApp update on SAI KUNJ every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI KUNJ have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ has one building filed: SAI KUNJ with 5 floors.

How big is the land of SAI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ stands on 286 sq m of land (about 0.1 acres), with 286 sq m of sanctioned built-up area.

Where can I read reviews of SAI KUNJ?

Google Maps has reviews of SAI KUNJ written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI KUNJ?

SAI KUNJ by CHOULWAR CONSTRUCTION is in Bavdhan, Pune (pincode 411021), Maharashtra, and is registered on MahaRERA as P52100025939, per GharKundli's check of MahaRERA records. Its boundaries filed there include GOVERNMENT ROAD.

How many homes are in SAI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ has 10 homes in 1 tower registered on MahaRERA.

When was SAI KUNJ registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI KUNJ was registered on MahaRERA on 31 July 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI KUNJ?

No court cases are listed for SAI KUNJ on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI KUNJ?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is CHOULWAR CONSTRUCTION.