Skip to content
GharKundli

Through Vastushree Building

by M/s.Shiv Developers through its Prop.Shri. Shankar Laxman Gaikwad · Opposite Side of Grampanchayat Bhigvan, Pune 413130Registered on MahaRERA as “Vastushree Building”

What’s in the report? →

Possession date of Through Vastushree Building (MahaRERA P52100026211): 15 September 2022, and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100026211. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100026211, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2022) has passed.

What do you want to know about Through Vastushree Building?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Through Vastushree Building

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100026211
Status
Lapsed (registration period ended)
Builder
M/s.Shiv Developers through its Prop.Shri. Shankar Laxman Gaikwad
Location
Opposite Side of Grampanchayat Bhigvan, Pune · 413130
Project type
Residential / Group Housing
Registered on
30 Aug 2020
Completion date at registration
September 2022
Latest completion date
September 2022
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Through Vastushree Building, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vastushree Building100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Through Vastushree Building every 1–2 months.

Through Vastushree Building: buildings, flats and land, as filed on MahaRERA

  • Buildings: Vastushree Building (3 floors)
  • Land: 546 sq m (about 0.1 acres) · sanctioned built-up 525 sq m
  • Land, as filed: 351 2
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Through Vastushree Building →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Through Vastushree Building: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Through Vastushree Building

What is the possession date of Through Vastushree Building?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Through Vastushree Building in Opposite Side of Grampanchayat Bhigvan, Pune is 15 September 2022. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Through Vastushree Building?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Through Vastushree Building's builder has filed on MahaRERA, the official one, is 15 September 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Through Vastushree Building?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Through Vastushree Building in Opposite Side of Grampanchayat Bhigvan, Pune is P52100026211.

Is Through Vastushree Building registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building is registered as P52100026211 and its status is "Lapsed (registration period ended)".

What is the current construction status of Through Vastushree Building? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Vastushree Building is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Through Vastushree Building have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Through Vastushree Building safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building is registered on MahaRERA as P52100026211, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Through Vastushree Building?

Through Vastushree Building isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Through Vastushree Building?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Through Vastushree Building: gharkundli.com/tools/property-cost-calculator

Has Through Vastushree Building received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 15 September 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Through Vastushree Building?

According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (15 September 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Through Vastushree Building uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Through Vastushree Building was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Through Vastushree Building's possession date changes?

The latest dates are on Through Vastushree Building's MahaRERA page (P52100026211). GharKundli's Kundli Watch sends a free WhatsApp update on Through Vastushree Building every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Through Vastushree Building have?

According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building has one building filed: Vastushree Building with 3 floors.

How big is the land of Through Vastushree Building?

According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building stands on 546 sq m of land (about 0.1 acres), with 525 sq m of sanctioned built-up area.

What are the reviews of Through Vastushree Building?

Google Maps has reviews of Through Vastushree Building written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Through Vastushree Building?

Through Vastushree Building by M/s.Shiv Developers through its Prop.Shri. Shankar Laxman Gaikwad is in Opposite Side of Grampanchayat Bhigvan, Pune, pincode 413130, Maharashtra, and is registered on MahaRERA as P52100026211, per GharKundli's check of MahaRERA records. Its land is filed as 351 2. GharKundli lists all 6 MahaRERA projects in Bhigwan (413130).

When was Through Vastushree Building registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Through Vastushree Building was registered on MahaRERA on 30 August 2020. GharKundli did not find a title report on the land on file there.

Does Through Vastushree Building have any legal issues or court cases?

No court cases are listed for Through Vastushree Building on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Through Vastushree Building?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s.Shiv Developers through its Prop.Shri. Shankar Laxman Gaikwad.

Other projects in Indapur

All 6 projects in Bhigwan (413130) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.