How the possession date of DRUMADAL has moved

  1. 30 September 2023

    Completion date given when the project was registered

  2. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52100017575)

    Reason the builder gave MahaRERA:
    “1) We are currently in the position of applying for completion certificate from our respective authority i.e. Pune Municipal Corporation but we are facing disruptions and hurdles in the form of administration and procedural delays in obtain…” Read the full reason“1) We are currently in the position of applying for completion certificate from our respective authority i.e. Pune Municipal Corporation but we are facing disruptions and hurdles in the form of administration and procedural delays in obtaining the completion certificate, we are diligently keeping track of the same on regular intervals. We have also communicated this issue to our allottees in a transparent matter and just as a preventive measure we are hereby applying for this extension. 2) Also, our project has been physically almost complete in all aspects, which is indicated by the latest…”

Source: DRUMADAL’s extension records on MahaRERA (P52100026105), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DRUMADAL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100026105
Status
Completed
Builder
Ranjekar Realty LLP
Location
Shivajinagar, Bhamburda, Pune · 411016
Project type
Residential / Group Housing
Registered on
19 Aug 2020
Completion date at registration
September 2023
Latest completion date
March 2024
Delay so far
6 months
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
15

Construction progress of DRUMADAL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DRUMADAL0%100%85%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DRUMADAL every month.

DRUMADAL: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of DRUMADAL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DRUMADAL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DRUMADAL

What is the possession date of DRUMADAL?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DRUMADAL in Shivajinagar, Bhamburda, Pune is 31 March 2024 — 6 months later than 30 September 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for DRUMADAL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DRUMADAL's builder has filed on MahaRERA, the official one, is 31 March 2024, already 6 months later than the 30 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DRUMADAL extended?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "1) We are currently in the position of applying for completion certificate from our respective authority i.e. Pune Municipal Corporation but we are facing disruptions and hurdles in the form of administration and procedural delays in obtaining the completion certificate, we are diligently keeping track of the same on regular intervals. We have also communicated this issue to our allottees in a transparent matter and just as a preventive measure we are hereby applying for this extension. 2) Also, our project has been physically almost complete in all aspects, which is indicated by the latest…".

What is the RERA number of DRUMADAL?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DRUMADAL in Shivajinagar, Bhamburda, Pune is P52100026105.

Is DRUMADAL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL is registered as P52100026105 and its status is "Completed".

What is the construction status of DRUMADAL?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL's status on MahaRERA is "Completed". As filed by the builder, slab work on DRUMADAL is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does DRUMADAL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is DRUMADAL safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL is registered on MahaRERA as P52100026105, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DRUMADAL's possession date changes?

The latest dates are on DRUMADAL's MahaRERA page (P52100026105). GharKundli's Kundli Watch sends a free WhatsApp update on DRUMADAL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DRUMADAL have?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL has one building filed: DRUMADAL with 6 floors.

How big is the land of DRUMADAL?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL stands on 673 sq m of land (about 0.2 acres), with 652 sq m of sanctioned built-up area.

Where can I read reviews of DRUMADAL?

Google Maps has reviews of DRUMADAL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DRUMADAL?

DRUMADAL by Ranjekar Realty LLP is in Shivajinagar, Bhamburda, Pune (pincode 411016), near Model Colony, Bhamburda Shivajinagar, Shivaji Nagar, Maharashtra, and is registered on MahaRERA as P52100026105, per GharKundli's check of MahaRERA records.

How many homes are in DRUMADAL?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL has 12 homes in 1 tower registered on MahaRERA.

When was DRUMADAL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DRUMADAL was registered on MahaRERA on 19 August 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on DRUMADAL?

No court cases are listed for DRUMADAL on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of DRUMADAL?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ranjekar Realty LLP, which has 15 other projects registered on MahaRERA.

Other projects in pincode 411016

All 59 projects in Model Colony (411016) →

Other projects by Ranjekar Realty LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.