by LAXMIDEEP INFRASTRUCTURES · Mordewadi, Pune 410503Registered on MahaRERA as “SAIRAJ”

What’s in the report? →

Possession date of Laxmideep Sairaj (MahaRERA P52100026844): 30 April 2027, moved from 28 February 2023 (46 months later). It has 36 homes, 6% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100026844, and currently active. Its completion date has moved from February 2023 to April 2027: 46 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100026844, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Laxmideep Sairaj?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Laxmideep Sairaj has moved

  1. 28 February 2023

    Completion date given when the project was registered

  2. 31 October 2024

    Extended at the builder's request (MahaRERA application EXT52100016543)

    Reason the builder gave MahaRERA:
    “WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT…” Read the full reason“WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 28/02/2024”
  3. 30 November 2025

    Extended at the builder's request (MahaRERA application EXT52100027667)

    Reason the builder gave MahaRERA:
    “WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT…” Read the full reason“WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 31/11/2025.”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA21032620312)

    Reason the builder gave MahaRERA:
    “WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT…” Read the full reason“WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 31/12/2026.”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Laxmideep Sairaj’s extension records on MahaRERA (P52100026844), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Laxmideep Sairaj

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100026844
Status
Registered and active
Builder
LAXMIDEEP INFRASTRUCTURES
Location
Mordewadi, Pune · 410503
Project type
Residential / Group Housing
Registered on
31 Oct 2020
Completion date at registration
February 2023
Latest completion date
April 2027
Delay so far
46 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
36
Sold or booked
6%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Laxmideep Sairaj, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAIRAJ A100%25%45.1%0%
SAIRAJ B100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SAIRAJ A: covers 3 floors
  • SAIRAJ B: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Laxmideep Sairaj every 1–2 months.

Laxmideep Sairaj: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAIRAJ A (118 floors, 21 units) · SAIRAJ B (56 floors, 15 units)
  • Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 2,260 sq m
  • Boundaries filed include: MANCHAR MORDEWADI ROAD
  • Land, as filed: 2/7
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Laxmideep Sairaj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Laxmideep Sairaj: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Laxmideep Sairaj

What is the possession date of Laxmideep Sairaj?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Laxmideep Sairaj in Mordewadi, Pune is 30 April 2027 — 46 months later than 28 February 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 46 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Laxmideep Sairaj?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Laxmideep Sairaj's builder has filed on MahaRERA, the official one, is 30 April 2027, already 46 months later than the 28 February 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Laxmideep Sairaj extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj's builder applied to MahaRERA to extend the completion date 3 times: to 31 October 2024, giving the reason "WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 28/02/2024"; to 30 November 2025, giving the reason "WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 31/11/2025."; to 31 December 2026, giving the reason "WE HAVE RECEIVED RERA NO FOR PROJECT AND WORK STOPPED DUE TO OWN CONTRIBUTION OF FUNDS ISSUES FROM PARTNERS HENCE PROJECT IS DELAYED, ALSO WE HAVE COMPLETED APPROX 90% PROJECT FROM OUR OWN FUNDS, ALSO WE ARE CAPABLE TO COMPLETE ALL PROJECT ON THE BASIS OF OUR OWN FUNDS BUT IN BETWEEN PROJECT DATE IS EXPIRED. KINDLY ALLOW THE EXTENSION TILL DATE 31/12/2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Laxmideep Sairaj?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Laxmideep Sairaj in Mordewadi, Pune is P52100026844.

Is Laxmideep Sairaj registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj is registered as P52100026844 and its status is "Registered and active".

What is the current construction status of Laxmideep Sairaj? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 25% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Laxmideep Sairaj have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Laxmideep Sairaj safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj is registered on MahaRERA as P52100026844, its completion date has moved 46 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Laxmideep Sairaj?

Laxmideep Sairaj is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Laxmideep Sairaj?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Laxmideep Sairaj: gharkundli.com/tools/property-cost-calculator

Has Laxmideep Sairaj received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Laxmideep Sairaj uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Laxmideep Sairaj was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Laxmideep Sairaj's possession date changes?

The latest dates are on Laxmideep Sairaj's MahaRERA page (P52100026844). GharKundli's Kundli Watch sends a free WhatsApp update on Laxmideep Sairaj every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Laxmideep Sairaj have?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj has 2 buildings filed: SAIRAJ A with 118 floors and 21 units; SAIRAJ B with 56 floors and 15 units.

How big is the land of Laxmideep Sairaj?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj stands on 2,000 sq m of land (about 0.5 acres), with 2,260 sq m of sanctioned built-up area.

What are the reviews of Laxmideep Sairaj?

Google Maps has reviews of Laxmideep Sairaj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Laxmideep Sairaj?

Laxmideep Sairaj by LAXMIDEEP INFRASTRUCTURES is in Mordewadi, Pune, pincode 410503, Maharashtra, and is registered on MahaRERA as P52100026844, per GharKundli's check of MahaRERA records. Its boundaries filed there include MANCHAR MORDEWADI ROAD. Its land is filed as 2/7. GharKundli lists all 36 MahaRERA projects in Manchar (410503).

How many flats are in Laxmideep Sairaj, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj has 36 homes in 2 towers registered on MahaRERA, and 6% of them are sold or booked.

When was Laxmideep Sairaj registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Laxmideep Sairaj was registered on MahaRERA on 31 October 2020. GharKundli did not find a title report on the land on file there.

Does Laxmideep Sairaj have any legal issues or court cases?

No court cases are listed for Laxmideep Sairaj on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Laxmideep Sairaj?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAXMIDEEP INFRASTRUCTURES.

All projects with possession due in 2027 in Pune →

Other projects in Ambegaon

All 36 projects in Manchar (410503) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.