Anand Kirti Tower
by S R and Shah Developers · Dongare, Palghar
Possession date of Anand Kirti Tower: 31 December 2026, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000003076, and currently active. 33 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Anand Kirti Tower?
How the possession date of Anand Kirti Tower has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT99000009813)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.”30 December 2023
Extended at the builder's request (MahaRERA application EXT99000013228)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 74.07% allottees for purpose of extension of RERA registration period of the said project.”31 December 2025
Extended at the builder's request (MahaRERA application EXT99000018877)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 93.02% allottees for purpose of extension of RERA registration period of the said project.”31 December 2026
Extended at the builder's request (MahaRERA application EA24032620355)
Reason the builder gave MahaRERA:
“We, S R And Shah Developers , the promoter of the project Anand Kirti Tower (Registration No. P99000003076) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We sincerely apologize for the…” Read the full reason
“We, S R And Shah Developers , the promoter of the project Anand Kirti Tower (Registration No. P99000003076) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We sincerely apologize for the delay in completing the project and submitting this request. The delay was caused by a combination of procurement challenges, financial constraints, site-related issues, and a dispute between project partners which affected funding and overall progress. These circumstances were unforeseen and significantly impacted the project timeline. The matters have…”
Source: Anand Kirti Tower’s extension records on MahaRERA (P99000003076), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Anand Kirti Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 33 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000003076
- Status
- Registered and active
- Builder
- S R and Shah Developers
- Location
- Dongare, Palghar · 401303
- Project type
- Others
- Registered on
- 4 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2026
- Delay so far
- 66 months
- Homes
- 100
- Sold or booked
- 47%
- Towers
- 2
- Complaints on MahaRERA
- 33
- Court cases listed
- 0
- Appeals at the tribunal
- 5
- Title report on file
- Not found
Construction progress of Anand Kirti Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A wing | 100% | 100% | 50% | 7.5% |
| C wing | 100% | 100% | 50% | 7.5% |
Commencement certificate (CC), as filed on MahaRERA
- A wing: covers 16 (G + 15)
- C wing: covers 1 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anand Kirti Tower every month.
Anand Kirti Tower: buildings, flats and land, as filed on MahaRERA
- Buildings: A wing (17 floors, 112 units) · C wing (1 floors, 2 units)
- Land: 1,297 sq m (about 0.3 acres) · sanctioned built-up 6,518 sq m
- Boundaries filed include: garden
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Anand Kirti Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Anand Kirti Tower: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Anand Kirti Tower
What is the possession date of Anand Kirti Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Anand Kirti Tower in Dongare, Palghar is 31 December 2026 — 66 months later than 30 June 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Anand Kirti Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Anand Kirti Tower's builder has filed on MahaRERA, the official one, is 31 December 2026, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Anand Kirti Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry."; to 30 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 74.07% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 93.02% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2026, giving the reason "We, S R And Shah Developers , the promoter of the project Anand Kirti Tower (Registration No. P99000003076) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We sincerely apologize for the delay in completing the project and submitting this request. The delay was caused by a combination of procurement challenges, financial constraints, site-related issues, and a dispute between project partners which affected funding and overall progress. These circumstances were unforeseen and significantly impacted the project timeline. The matters have…".
What is the RERA number of Anand Kirti Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Anand Kirti Tower in Dongare, Palghar is P99000003076.
Is Anand Kirti Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower is registered as P99000003076 and its status is "Registered and active".
What is the construction status of Anand Kirti Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Anand Kirti Tower have complaints on MahaRERA?
33 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Anand Kirti Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower is registered on MahaRERA as P99000003076, its completion date has moved 66 months since registration and 33 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Anand Kirti Tower's possession date changes?
The latest dates are on Anand Kirti Tower's MahaRERA page (P99000003076). GharKundli's Kundli Watch sends a free WhatsApp update on Anand Kirti Tower every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Anand Kirti Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower has 2 buildings filed: A wing with 17 floors and 112 units; C wing with 1 floors and 2 units.
How big is the land of Anand Kirti Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower stands on 1,297 sq m of land (about 0.3 acres), with 6,518 sq m of sanctioned built-up area.
Where can I read reviews of Anand Kirti Tower?
Google Maps has reviews of Anand Kirti Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 33 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Anand Kirti Tower?
Anand Kirti Tower by S R and Shah Developers is in Dongare, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000003076, per GharKundli's check of MahaRERA records. Its boundaries filed there include garden.
How many homes are in Anand Kirti Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower has 100 homes in 2 towers registered on MahaRERA, and 47% of them are sold or booked.
When was Anand Kirti Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Kirti Tower was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Anand Kirti Tower?
No court cases are listed for Anand Kirti Tower on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Anand Kirti Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is S R and Shah Developers.
Check it yourself on MahaRERA
- How to check the possession date of Anand Kirti Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Palghar →
Other projects in Vasai
- ESSAR APEX
- STAR LEGACY
- VIMALNATH Building no-2
- GULMOHAR HERITAGE BUILDING NO 3 WING E PHASE I
- DHANANJAY ICON
- COMFORT AARADHYA
- Acciano Bianca
- SHIVNERI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.