29 GOLD COAST PHASE 6
by MANTRA 29 GOLD COST DEVELOPERS LLP · Dhanori, PuneAlso near Dighi Camp
Possession date of 29 GOLD COAST PHASE 6: 31 December 2025, moved from 31 December 2024 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100029378. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about 29 GOLD COAST PHASE 6?
How the possession date of 29 GOLD COAST PHASE 6 has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT52100013356)
Reason the builder gave MahaRERA: “Launch of Project is Delayed and therefore applying for Extension.”
Source: 29 GOLD COAST PHASE 6’s extension records on MahaRERA (P52100029378), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 29 GOLD COAST PHASE 6
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- 29 GOLD COAST PHASE 1P52100002674
- 29 GOLD COAST PHASE 2P52100016777
- 29 GOLD COAST PHASE 3P52100017100
- 29 GOLD COAST PHASE 4P52100023097
- 29 GOLD COAST PHASE 5P52100023345
- 29 GOLD COAST PHASE 7P52100045500 · possession 16 Feb 2025
- MahaRERA registration
- P52100029378
- Status
- Lapsed (registration period ended)
- Builder
- MANTRA 29 GOLD COST DEVELOPERS LLP
- Location
- Dhanori, Pune · 411015
- Project type
- Others
- Registered on
- 29 May 2021
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 215
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of 29 GOLD COAST PHASE 6, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING D1 | 100% | 100% | 100% | 100% |
| BUILDING D2 | 100% | 100% | 100% | 100% |
| BUILDING D3 | 100% | 100% | 100% | 100% |
| BUILDING D4 | 100% | 100% | 100% | 100% |
| BUILDING D5 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 29 GOLD COAST PHASE 6 every month.
29 GOLD COAST PHASE 6: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING D1 (6 floors) · BUILDING D2 (6 floors) · BUILDING D3 (6 floors) · BUILDING D4 (6 floors) · BUILDING D5 (6 floors)
- Land: 12,630 sq m (about 3.1 acres) · sanctioned built-up 20,003 sq m · recreational space 5,405 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Mantra Zirconia (a group of 15 linked companies) has 78 projects on MahaRERA since 2017, this one included. Of the 52 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 38 months); 35 still being built, none past the promised date yet; 9 lapsed. 31 complaints on MahaRERA across 14 projects.
Read Google reviews of 29 GOLD COAST PHASE 6 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
29 GOLD COAST PHASE 6: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 29 GOLD COAST PHASE 6
What is the possession date of 29 GOLD COAST PHASE 6?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 29 GOLD COAST PHASE 6 in Dhanori, Pune is 31 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for 29 GOLD COAST PHASE 6?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 29 GOLD COAST PHASE 6's builder has filed on MahaRERA, the official one, is 31 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of 29 GOLD COAST PHASE 6 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "Launch of Project is Delayed and therefore applying for Extension.".
What is the RERA number of 29 GOLD COAST PHASE 6?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 29 GOLD COAST PHASE 6 in Dhanori, Pune is P52100029378.
Is 29 GOLD COAST PHASE 6 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6 is registered as P52100029378 and its status is "Lapsed (registration period ended)".
What is the construction status of 29 GOLD COAST PHASE 6?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does 29 GOLD COAST PHASE 6 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is 29 GOLD COAST PHASE 6 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6 is registered on MahaRERA as P52100029378, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does 29 GOLD COAST PHASE 6 have other wings or phases?
Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: 29 GOLD COAST PHASE 1 (P52100002674); 29 GOLD COAST PHASE 2 (P52100016777); 29 GOLD COAST PHASE 3 (P52100017100); 29 GOLD COAST PHASE 4 (P52100023097); 29 GOLD COAST PHASE 5 (P52100023345); 29 GOLD COAST PHASE 7 (P52100045500, possession 16 Feb 2025). Check that your agreement names the registration of your own wing.
How can I get updates if 29 GOLD COAST PHASE 6's possession date changes?
The latest dates are on 29 GOLD COAST PHASE 6's MahaRERA page (P52100029378). GharKundli's Kundli Watch sends a free WhatsApp update on 29 GOLD COAST PHASE 6 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 29 GOLD COAST PHASE 6 have?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6 has 5 buildings filed: BUILDING D1 with 6 floors; BUILDING D2 with 6 floors; BUILDING D3 with 6 floors; BUILDING D4 with 6 floors; BUILDING D5 with 6 floors.
How big is the land of 29 GOLD COAST PHASE 6?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6 stands on 12,630 sq m of land (about 3.1 acres), with 20,003 sq m of sanctioned built-up area and 5,405 sq m of recreational open space.
What is the track record of 29 GOLD COAST PHASE 6's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Mantra Zirconia (a group of 15 linked companies) has 78 projects on MahaRERA since 2017, this one included. Of the 52 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 38 months); 35 still being built, none past the promised date yet; 9 lapsed. 31 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of 29 GOLD COAST PHASE 6?
Google Maps has reviews of 29 GOLD COAST PHASE 6 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 29 GOLD COAST PHASE 6?
29 GOLD COAST PHASE 6 by MANTRA 29 GOLD COST DEVELOPERS LLP is in Dhanori, Pune (pincode 411015), near Dighi Camp, Maharashtra, and is registered on MahaRERA as P52100029378, per GharKundli's check of MahaRERA records.
How many homes are in 29 GOLD COAST PHASE 6?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6 has 215 homes in 5 towers registered on MahaRERA.
When was 29 GOLD COAST PHASE 6 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 29 GOLD COAST PHASE 6 was registered on MahaRERA on 29 May 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on 29 GOLD COAST PHASE 6?
4 court cases are listed for 29 GOLD COAST PHASE 6 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of 29 GOLD COAST PHASE 6?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MANTRA 29 GOLD COST DEVELOPERS LLP, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 29 GOLD COAST PHASE 6
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 411015
- DELLA REGENCY
- UJWAL TOWER
- SPARKLE ENCLAVE
- VEDANTA
- QUE 101 PHASE I
- NYATI ERA III
- Kohinoor Viva Pixel- Phase II
- GANGA NEWTOWN PH 6 F BLDG
Other projects by MANTRA 29 GOLD COST DEVELOPERS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.