Skip to content
GharKundli

Haridwar Siddh

by Haridwar Corp · Virar West, Palghar

Possession date of Haridwar Siddh: 30 April 2027, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000004713, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Haridwar Siddh?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Haridwar Siddh has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT99000009935)

    Reason the builder gave MahaRERA: “Project completion has been delayed due to the lockdown and the presnt ongoing pandemic and the shortage of workers. Therefore, request to extent the project completion date still 30/06/2022”
  3. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT99000013991)

    Reason the builder gave MahaRERA:
    “We would like to inform that due to Covod-19 pandemic, frequent lock down and non favorable factors likes slowdown in real estate activities, shortage of building materials and shortage of skilled manpower construction of project were large…” Read the full reason“We would like to inform that due to Covod-19 pandemic, frequent lock down and non favorable factors likes slowdown in real estate activities, shortage of building materials and shortage of skilled manpower construction of project were largely affected and project was not able to complete in time. And we expect some more delay in completion of project. We have completed 80% work of project. So we request you to extend the project completion date upto 30/12/2025.”
  4. 30 December 2026

    Extended at the builder's request (MahaRERA application EA25052621081)

    Reason the builder gave MahaRERA: “We have completed 98% of project work and are in the process of 100% completion and in the process of applying to VVCMC for Occupancy Certificate.”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Haridwar Siddh’s extension records on MahaRERA (P99000004713), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Haridwar Siddh

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000004713
Status
Registered and active
Builder
Haridwar Corp
Location
Virar West, Palghar · 401303
Project type
Mixed
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
April 2027
Delay so far
66 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
88
Sold or booked
35%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of Haridwar Siddh, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Haridwar Siddh100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • Haridwar Siddh: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Haridwar Siddh every month.

Haridwar Siddh: buildings, flats and land, as filed on MahaRERA

  • Buildings: Haridwar Siddh (17 floors, 98 units)
  • Car parking: 7 covered
  • Land: 1,035 sq m (about 0.3 acres) · sanctioned built-up 5,986 sq m
  • Boundaries filed include: Garden

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Haridwar Siddh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Haridwar Siddh: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Haridwar Siddh

What is the possession date of Haridwar Siddh?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Haridwar Siddh in Virar West, Palghar is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Haridwar Siddh?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Haridwar Siddh's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Haridwar Siddh extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Project completion has been delayed due to the lockdown and the presnt ongoing pandemic and the shortage of workers. Therefore, request to extent the project completion date still 30/06/2022"; to 30 December 2025, giving the reason "We would like to inform that due to Covod-19 pandemic, frequent lock down and non favorable factors likes slowdown in real estate activities, shortage of building materials and shortage of skilled manpower construction of project were largely affected and project was not able to complete in time. And we expect some more delay in completion of project. We have completed 80% work of project. So we request you to extend the project completion date upto 30/12/2025."; to 30 December 2026, giving the reason "We have completed 98% of project work and are in the process of 100% completion and in the process of applying to VVCMC for Occupancy Certificate.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Haridwar Siddh?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Haridwar Siddh in Virar West, Palghar is P99000004713.

Is Haridwar Siddh registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh is registered as P99000004713 and its status is "Registered and active".

What is the construction status of Haridwar Siddh?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Haridwar Siddh is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Haridwar Siddh have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Haridwar Siddh safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh is registered on MahaRERA as P99000004713, its completion date has moved 66 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Haridwar Siddh's possession date changes?

The latest dates are on Haridwar Siddh's MahaRERA page (P99000004713). GharKundli's Kundli Watch sends a free WhatsApp update on Haridwar Siddh every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Haridwar Siddh have?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh has one building filed: Haridwar Siddh with 17 floors and 98 units.

How much parking does Haridwar Siddh have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 7 covered car parking spaces for Haridwar Siddh.

How big is the land of Haridwar Siddh?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh stands on 1,035 sq m of land (about 0.3 acres), with 5,986 sq m of sanctioned built-up area.

Where can I read reviews of Haridwar Siddh?

Google Maps has reviews of Haridwar Siddh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Haridwar Siddh?

Haridwar Siddh by Haridwar Corp is in Virar West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000004713, per GharKundli's check of MahaRERA records. Its boundaries filed there include Garden.

How many homes are in Haridwar Siddh?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh has 88 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.

When was Haridwar Siddh registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Haridwar Siddh was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Haridwar Siddh?

No court cases are listed for Haridwar Siddh on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Haridwar Siddh?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Haridwar Corp.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401303

All 189 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.