What’s in the report? →Possession date of Utopia Gold (MahaRERA P52100033254): 30 April 2027, moved from 31 December 2025 (12 months later). It has 513 homes, 87% sold or booked. 54 complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100033254, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100033254, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Utopia Gold?
54 complaints MahaRERA par. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Utopia Gold has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA07112518258)
Reason the builder gave MahaRERA:
“The progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to ma…” Read the full reason
“The progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to make the area safe for further work. We request an extension of the project completion period due to this unavoidable situation.”31 December 2026
Extended at the builder's request (MahaRERA application EA23052621071)
Reason the builder gave MahaRERA:
“The progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to ma…” Read the full reason
“The progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to make the area safe for further work. We request an extension of the project completion period due to this unavoidable situation.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Utopia Gold’s extension records on MahaRERA (P52100033254), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Utopia Gold
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 54 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100033254
- Status
- Registered and active
- Builder
- AKSHAY DEEPAK PANJABI
- Location
- Borhadewadi Moshi, Pune · 412105
- Project type
- Others
- Registered on
- 9 Feb 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 513
- Sold or booked
- 87%
- Towers
- 4
- Complaints on MahaRERA
- 54
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Utopia Gold, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| UTOPIA GOLD - TOWER A | 100% | 100% | 99% | 95% |
| UTOPIA GOLD - TOWER B | 100% | 100% | 99% | 95% |
| UTOPIA GOLD - TOWER C | 100% | 100% | 100% | 100% |
| UTOPIA GOLD - TOWER D | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- UTOPIA GOLD - TOWER A: covers 18 floors
- UTOPIA GOLD - TOWER B: covers 18 floors
- UTOPIA GOLD - TOWER C: covers 18 floors
- UTOPIA GOLD - TOWER D: covers 18 floors
Latest CC order on MahaRERA: dated 30/11/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Utopia Gold every 1–2 months.
Utopia Gold: buildings, flats and land, as filed on MahaRERA
- Buildings: UTOPIA GOLD - TOWER A (24 floors, 153 units) · UTOPIA GOLD - TOWER B (24 floors, 136 units) · UTOPIA GOLD - TOWER C (23 floors, 136 units) · UTOPIA GOLD - TOWER D (23 floors, 119 units)
- Car parking: 520 covered
- Land: 7,457 sq m (about 1.8 acres) · sanctioned built-up 43,703 sq m · recreational space 746 sq m
- Land, as filed: 129 p AT BORHADEWADI
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Utopia Gold →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Utopia Gold: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Utopia Gold
What is the possession date of Utopia Gold?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Utopia Gold in Borhadewadi Moshi, Pune is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Utopia Gold?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Utopia Gold's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Utopia Gold extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "The progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to make the area safe for further work. We request an extension of the project completion period due to this unavoidable situation."; to 31 December 2026, giving the reason "The progress of our project was unavoidably delayed Due to heavy rainfall, a large amount of water got accumulated in the project basement. This caused delays in construction and finishing work as dewatering and drying took extra time to make the area safe for further work. We request an extension of the project completion period due to this unavoidable situation.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Utopia Gold?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Utopia Gold in Borhadewadi Moshi, Pune is P52100033254.
Is Utopia Gold registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold is registered as P52100033254 and its status is "Registered and active".
What is the current construction status of Utopia Gold? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Utopia Gold have complaints on MahaRERA?
54 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
54 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →
Is Utopia Gold safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold is registered on MahaRERA as P52100033254, its completion date has moved 12 months since registration and 54 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Utopia Gold?
Utopia Gold is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Utopia Gold?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Utopia Gold: gharkundli.com/tools/property-cost-calculator
Has Utopia Gold received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Utopia Gold uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Utopia Gold was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Utopia Gold's possession date changes?
The latest dates are on Utopia Gold's MahaRERA page (P52100033254). GharKundli's Kundli Watch sends a free WhatsApp update on Utopia Gold every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Utopia Gold have?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold has 4 buildings filed: UTOPIA GOLD - TOWER A with 24 floors and 153 units; UTOPIA GOLD - TOWER B with 24 floors and 136 units; UTOPIA GOLD - TOWER C with 23 floors and 136 units; UTOPIA GOLD - TOWER D with 23 floors and 119 units.
How much parking does Utopia Gold have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 520 covered car parking spaces for Utopia Gold.
How big is the land of Utopia Gold?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold stands on 7,457 sq m of land (about 1.8 acres), with 43,703 sq m of sanctioned built-up area and 746 sq m of recreational open space.
What are the reviews of Utopia Gold?
Google Maps has reviews of Utopia Gold written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 54 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Utopia Gold?
Utopia Gold by AKSHAY DEEPAK PANJABI is in Borhadewadi Moshi, Pune, pincode 412105 (near Chikhali, Moshi - Borhadewadi, Dehu Alandi Road), Maharashtra, and is registered on MahaRERA as P52100033254, per GharKundli's check of MahaRERA records. Its land is filed as 129 p AT BORHADEWADI. GharKundli lists all 885 MahaRERA projects in Alandi Devachi (412105).
How many flats are in Utopia Gold, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold has 513 homes in 4 towers registered on MahaRERA, and 87% of them are sold or booked.
When was Utopia Gold registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Utopia Gold was registered on MahaRERA on 9 February 2022. GharKundli did not find a title report on the land on file there.
Does Utopia Gold have any legal issues or court cases?
No court cases are listed for Utopia Gold on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Utopia Gold?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AKSHAY DEEPAK PANJABI.
Check it yourself on MahaRERA
- How to check the possession date of Utopia Gold
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Haveli
All 885 projects in Alandi Devachi (412105) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.