SHUBHAMYASH CONSTRUCTION AND DEVELOPERS
by SHUBHAMYASH CONSTRUCTION AND DEVELOPERS · Daund, Pune
Possession date of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS: 30 April 2033. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100034217, and currently active. Its completion date is now April 2033, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
How the possession date of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS has moved
31 December 2032
Completion date given when the project was registered
30 April 2033
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHUBHAMYASH CONSTRUCTION AND DEVELOPERS’s extension records on MahaRERA (P52100034217), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHUBHAMYASH CONSTRUCTION AND DEVELOPERS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2033 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100034217
- Status
- Registered and active
- Builder
- SHUBHAMYASH CONSTRUCTION AND DEVELOPERS
- Location
- Daund, Pune · 413801
- Project type
- Residential / Group Housing
- Registered on
- 25 Mar 2022
- Completion date at registration
- December 2032
- Latest completion date
- April 2033
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 23
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHUBHAMYASH CONSTRUCTION AND DEVELOPERS | 100% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHUBHAMYASH CONSTRUCTION AND DEVELOPERS every month.
SHUBHAMYASH CONSTRUCTION AND DEVELOPERS: buildings, flats and land, as filed on MahaRERA
- Buildings: SHUBHAMYASH CONSTRUCTION AND DEVELOPERS (8 floors)
- Land: 650 sq m (about 0.2 acres) · sanctioned built-up 1,456 sq m
- Boundaries filed include: RUDRAPRIYA COLONY, DEFENCE COLONY
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHUBHAMYASH CONSTRUCTION AND DEVELOPERS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHUBHAMYASH CONSTRUCTION AND DEVELOPERS
What is the possession date of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHUBHAMYASH CONSTRUCTION AND DEVELOPERS in Daund, Pune is 30 April 2033, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHUBHAMYASH CONSTRUCTION AND DEVELOPERS's builder has filed on MahaRERA, the official one, is 30 April 2033, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS in Daund, Pune is P52100034217.
Is SHUBHAMYASH CONSTRUCTION AND DEVELOPERS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBHAMYASH CONSTRUCTION AND DEVELOPERS is registered as P52100034217 and its status is "Registered and active".
What is the construction status of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBHAMYASH CONSTRUCTION AND DEVELOPERS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHUBHAMYASH CONSTRUCTION AND DEVELOPERS is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SHUBHAMYASH CONSTRUCTION AND DEVELOPERS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHUBHAMYASH CONSTRUCTION AND DEVELOPERS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBHAMYASH CONSTRUCTION AND DEVELOPERS is registered on MahaRERA as P52100034217, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHUBHAMYASH CONSTRUCTION AND DEVELOPERS's possession date changes?
The latest dates are on SHUBHAMYASH CONSTRUCTION AND DEVELOPERS's MahaRERA page (P52100034217). GharKundli's Kundli Watch sends a free WhatsApp update on SHUBHAMYASH CONSTRUCTION AND DEVELOPERS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHUBHAMYASH CONSTRUCTION AND DEVELOPERS have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBHAMYASH CONSTRUCTION AND DEVELOPERS has one building filed: SHUBHAMYASH CONSTRUCTION AND DEVELOPERS with 8 floors.
How big is the land of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBHAMYASH CONSTRUCTION AND DEVELOPERS stands on 650 sq m of land (about 0.2 acres), with 1,456 sq m of sanctioned built-up area.
Where can I read reviews of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
Google Maps has reviews of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
SHUBHAMYASH CONSTRUCTION AND DEVELOPERS by SHUBHAMYASH CONSTRUCTION AND DEVELOPERS is in Daund, Pune (pincode 413801), Maharashtra, and is registered on MahaRERA as P52100034217, per GharKundli's check of MahaRERA records. Its boundaries filed there include RUDRAPRIYA COLONY, DEFENCE COLONY.
How many homes are in SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBHAMYASH CONSTRUCTION AND DEVELOPERS has 23 homes in 1 tower registered on MahaRERA.
When was SHUBHAMYASH CONSTRUCTION AND DEVELOPERS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBHAMYASH CONSTRUCTION AND DEVELOPERS was registered on MahaRERA on 25 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
No court cases are listed for SHUBHAMYASH CONSTRUCTION AND DEVELOPERS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHUBHAMYASH CONSTRUCTION AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SHUBHAMYASH CONSTRUCTION AND DEVELOPERS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 413801
All 27 projects in Daund (413801) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.