Possession: Royal Residency is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100033743. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Royal Residency?
How the possession date of Royal Residency has moved
30 June 2023
Completion date given when the project was registered
29 June 2024
Extended at the builder's request (MahaRERA application EXT52100016926)
Reason the builder gave MahaRERA: “As per Self Explanatory Note Attached in Sr No 1”
Source: Royal Residency’s extension records on MahaRERA (P52100033743), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Royal Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100033743
- Status
- Completed
- Builder
- Royal Eterprises
- Location
- Krupasinndhu Park, Pune · 412105
- Project type
- Residential / Group Housing
- Registered on
- 8 Mar 2022
- Completion date at registration
- June 2023
- Latest completion date
- June 2024
- Delay so far
- 12 months
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Royal Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Royal Residency | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Royal Residency every month.
Royal Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Royal Residency (5 floors)
- Land: 336 sq m (about 0.1 acres) · sanctioned built-up 806 sq m · recreational space 336 sq m
- Boundaries filed include: B Plot 02 Internal Road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Royal Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Royal Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Royal Residency
What is the possession date of Royal Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Royal Residency in Krupasinndhu Park, Pune is 29 June 2024 — 12 months later than 30 June 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Royal Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Royal Residency's builder has filed on MahaRERA, the official one, is 29 June 2024, already 12 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Royal Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency's builder applied to MahaRERA to extend the completion date once: to 29 June 2024, giving the reason "As per Self Explanatory Note Attached in Sr No 1".
What is the RERA number of Royal Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Royal Residency in Krupasinndhu Park, Pune is P52100033743.
Is Royal Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency is registered as P52100033743 and its status is "Completed".
What is the construction status of Royal Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency's status on MahaRERA is "Completed". As filed by the builder, slab work on Royal Residency is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Royal Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Royal Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency is registered on MahaRERA as P52100033743, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Royal Residency's possession date changes?
The latest dates are on Royal Residency's MahaRERA page (P52100033743). GharKundli's Kundli Watch sends a free WhatsApp update on Royal Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Royal Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency has one building filed: Royal Residency with 5 floors.
How big is the land of Royal Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency stands on 336 sq m of land (about 0.1 acres), with 806 sq m of sanctioned built-up area and 336 sq m of recreational open space.
Where can I read reviews of Royal Residency?
Google Maps has reviews of Royal Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Royal Residency?
Royal Residency by Royal Eterprises is in Krupasinndhu Park, Pune (pincode 412105), Maharashtra, and is registered on MahaRERA as P52100033743, per GharKundli's check of MahaRERA records. Its boundaries filed there include B Plot 02 Internal Road.
How many homes are in Royal Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency has 10 homes in 1 tower registered on MahaRERA.
When was Royal Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Royal Residency was registered on MahaRERA on 8 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Royal Residency?
No court cases are listed for Royal Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Royal Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Royal Eterprises.
Check it yourself on MahaRERA
- How to check the possession date of Royal Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
- QUE 101 PHASE I
- CULLINAN
- SIDDHI AURUM
- MADHUGHAT
- ATS - THE CONDOMINIUMS
- BALWANT EMPIRE
- DYNAMIC SOLITAIRE – PHASE II
- SnehKunj
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.