by Reality Constructions · Chondhe Dara, Pune 412115

What’s in the report? →

Possession date of The Green Hill (MahaRERA P52100033175): 2 April 2028, moved from 5 December 2024 (36 months later). 1 complaint on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100033175, and currently active. Its completion date has moved from December 2024 to April 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100033175, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The Green Hill?

1 complaint MahaRERA par. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The Green Hill has moved

  1. 5 December 2024

    Completion date given when the project was registered

  2. 4 December 2025

    Extended at the builder's request (MahaRERA application EXT52100025683)

    Reason the builder gave MahaRERA:
    “We have applied for completion certificate of the project to PMRDA, Pune, but the same has not been received as on 21.12.2024. There is time required for getting documents compliance to get completion certificate, you are requested to pleas…” Read the full reason“We have applied for completion certificate of the project to PMRDA, Pune, but the same has not been received as on 21.12.2024. There is time required for getting documents compliance to get completion certificate, you are requested to please give us extension for the same. Proposed date of extension is 04/12/2025”
  3. 2 December 2027

    Extended at the builder's request (MahaRERA application EA10082622075)

    Reason the builder gave MahaRERA: “Due to finance & PMRDA Occupancy work”
  4. 2 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Green Hill’s extension records on MahaRERA (P52100033175), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Green Hill

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100033175
Status
Registered and active
Builder
Reality Constructions
Location
Chondhe Dara, Pune · 412115
Project type
Residential / Group Housing
Registered on
9 Feb 2022
Completion date at registration
December 2024
Latest completion date
April 2028
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of The Green Hill, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
The Green Hill100%100%100%99%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Green Hill every 1–2 months.

The Green Hill: buildings, flats and land, as filed on MahaRERA

  • Buildings: The Green Hill (11 floors)
  • Land: 1,766 sq m (about 0.4 acres) · sanctioned built-up 2,004 sq m · recreational space 200 sq m
  • Land, as filed: 279/1
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of The Green Hill →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Green Hill: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Green Hill

What is the possession date of The Green Hill?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Green Hill in Chondhe Dara, Pune is 2 April 2028 — 36 months later than 5 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for The Green Hill?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Green Hill's builder has filed on MahaRERA, the official one, is 2 April 2028, already 36 months later than the 5 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The Green Hill extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill's builder applied to MahaRERA to extend the completion date 2 times: to 4 December 2025, giving the reason "We have applied for completion certificate of the project to PMRDA, Pune, but the same has not been received as on 21.12.2024. There is time required for getting documents compliance to get completion certificate, you are requested to please give us extension for the same. Proposed date of extension is 04/12/2025"; to 2 December 2027, giving the reason "Due to finance & PMRDA Occupancy work". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of The Green Hill?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Green Hill in Chondhe Dara, Pune is P52100033175.

Is The Green Hill registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill is registered as P52100033175 and its status is "Registered and active".

What is the current construction status of The Green Hill? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill's status on MahaRERA is "Registered and active". As filed by the builder, slab work on The Green Hill is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does The Green Hill have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

1 complaint is filed on this project. Know what went wrong before you pay a token. See how it ended →

Is The Green Hill safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill is registered on MahaRERA as P52100033175, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Green Hill?

The Green Hill is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Green Hill?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in The Green Hill: gharkundli.com/tools/property-cost-calculator

Has The Green Hill received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill is still under construction, with 2 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has The Green Hill uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Green Hill was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Green Hill's possession date changes?

The latest dates are on The Green Hill's MahaRERA page (P52100033175). GharKundli's Kundli Watch sends a free WhatsApp update on The Green Hill every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Green Hill have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill has one building filed: The Green Hill with 11 floors.

How big is the land of The Green Hill?

According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill stands on 1,766 sq m of land (about 0.4 acres), with 2,004 sq m of sanctioned built-up area and 200 sq m of recreational open space.

What are the reviews of The Green Hill?

Google Maps has reviews of The Green Hill written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Green Hill?

The Green Hill by Reality Constructions is in Chondhe Dara, Pune, pincode 412115, Maharashtra, and is registered on MahaRERA as P52100033175, per GharKundli's check of MahaRERA records. Its land is filed as 279/1. GharKundli lists all 237 MahaRERA projects in Pirangut (412115).

When was The Green Hill registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Green Hill was registered on MahaRERA on 9 February 2022. GharKundli did not find a title report on the land on file there.

Does The Green Hill have any legal issues or court cases?

No court cases are listed for The Green Hill on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The Green Hill?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Reality Constructions, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Pune →

Other projects in Mulshi

All 237 projects in Pirangut (412115) →

Other projects by Reality Constructions

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.