Vaanya Cluster C

by Pharande Promoters and Builders (Benchmarrk) · Boradewadi, PuneAlso near Moshi, Chikhali, Guruvihar Bhosari

Possession date of Vaanya Cluster C: 30 October 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100045598, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Vaanya Cluster C?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Vaanya Cluster C has moved

  1. 30 June 2027

    Completion date given when the project was registered

  2. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Vaanya Cluster C’s extension records on MahaRERA (P52100045598), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vaanya Cluster C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100045598
Status
Registered and active
Builder
Pharande Promoters and Builders
Location
Boradewadi, Pune · 412105
Project type
Residential / Group Housing
Registered on
26 May 2022
Completion date at registration
June 2027
Latest completion date
October 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
69
Sold or booked
99%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
19

Construction progress of Vaanya Cluster C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B100%70%13%0%

Commencement certificate (CC), as filed on MahaRERA

  • B: covers 21 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vaanya Cluster C every month.

Vaanya Cluster C: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Pharande Promoters And Builders (a group of 4 linked companies) has 43 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 1 finished, all within the promised date; 21 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. 17 complaints on MahaRERA across 6 projects.

Read Google reviews of Vaanya Cluster C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vaanya Cluster C: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Vaanya Cluster C

What is the possession date of Vaanya Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vaanya Cluster C in Boradewadi, Pune is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Vaanya Cluster C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vaanya Cluster C's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Vaanya Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vaanya Cluster C in Boradewadi, Pune is P52100045598.

Is Vaanya Cluster C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vaanya Cluster C is registered as P52100045598 and its status is "Registered and active".

What is the construction status of Vaanya Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), Vaanya Cluster C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on B is 70% done and internal work 13%. GharKundli's full report compares construction progress with the deadline.

Does Vaanya Cluster C have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Vaanya Cluster C safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vaanya Cluster C is registered on MahaRERA as P52100045598, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Vaanya Cluster C have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Vaanya Cluster A (P52100029260); Vaanya Cluster B (P52100031670); Vaanya Cluster D (P52100045985, possession 30 Oct 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Vaanya Cluster C's possession date changes?

The latest dates are on Vaanya Cluster C's MahaRERA page (P52100045598). GharKundli's Kundli Watch sends a free WhatsApp update on Vaanya Cluster C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vaanya Cluster C have?

According to GharKundli's check of MahaRERA records (updated November 2026), Vaanya Cluster C has one building filed: B with 21 floors and 69 units.

How big is the land of Vaanya Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), Vaanya Cluster C stands on 1,262 sq m of land (about 0.3 acres), with 6,679 sq m of sanctioned built-up area and 1,091 sq m of recreational open space.

What is the track record of Vaanya Cluster C's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Pharande Promoters And Builders (a group of 4 linked companies) has 43 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 1 finished, all within the promised date; 21 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. 17 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Vaanya Cluster C?

Google Maps has reviews of Vaanya Cluster C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Vaanya Cluster C?

Vaanya Cluster C by Pharande Promoters and Builders (Benchmarrk) is in Boradewadi, Pune (pincode 412105), near Moshi, Chikhali, Guruvihar Bhosari, Maharashtra, and is registered on MahaRERA as P52100045598, per GharKundli's check of MahaRERA records.

How many homes are in Vaanya Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), Vaanya Cluster C has 69 homes in 1 tower registered on MahaRERA, and 99% of them are sold or booked.

When was Vaanya Cluster C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vaanya Cluster C was registered on MahaRERA on 26 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Vaanya Cluster C?

No court cases are listed for Vaanya Cluster C on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Vaanya Cluster C?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Pharande Promoters and Builders, the company Benchmarrk files this project under, which has 19 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in Haveli

All 590 projects in Alandi Devachi (412105) →

Other projects by Pharande Promoters and Builders

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.