Puraniks Abitante Fiore Phase 2C1
by Puranik Buildcon Private Limited (Fortune) · Bavdhan, Pune
Possession date of Puraniks Abitante Fiore Phase 2C1: 30 October 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100049352, and currently active. Its completion date is now October 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Puraniks Abitante Fiore Phase 2C1?
How the possession date of Puraniks Abitante Fiore Phase 2C1 has moved
30 June 2028
Completion date given when the project was registered
30 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Puraniks Abitante Fiore Phase 2C1’s extension records on MahaRERA (P52100049352), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Puraniks Abitante Fiore Phase 2C1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100049352
- Status
- Registered and active
- Builder
- Puranik Buildcon Private Limited
- Location
- Bavdhan, Pune · 411021
- Project type
- Residential / Group Housing
- Registered on
- 7 Feb 2023
- Completion date at registration
- June 2028
- Latest completion date
- October 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 448
- Sold or booked
- 67%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of Puraniks Abitante Fiore Phase 2C1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| I - Alvino | 0% | 0% | 0% | 0% |
| J - Amaranta | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Puraniks Abitante Fiore Phase 2C1 every month.
Puraniks Abitante Fiore Phase 2C1: buildings, flats and land, as filed on MahaRERA
- Buildings: I - Alvino (30 floors) · J - Amaranta (30 floors)
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 6 finished, all within the promised date; 21 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects.
Read Google reviews of Puraniks Abitante Fiore Phase 2C1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Puraniks Abitante Fiore Phase 2C1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Puraniks Abitante Fiore Phase 2C1
What is the possession date of Puraniks Abitante Fiore Phase 2C1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Puraniks Abitante Fiore Phase 2C1 in Bavdhan, Pune is 30 October 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Puraniks Abitante Fiore Phase 2C1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Puraniks Abitante Fiore Phase 2C1's builder has filed on MahaRERA, the official one, is 30 October 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Puraniks Abitante Fiore Phase 2C1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Puraniks Abitante Fiore Phase 2C1 in Bavdhan, Pune is P52100049352.
Is Puraniks Abitante Fiore Phase 2C1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Puraniks Abitante Fiore Phase 2C1 is registered as P52100049352 and its status is "Registered and active".
What is the construction status of Puraniks Abitante Fiore Phase 2C1?
According to GharKundli's check of MahaRERA records (updated November 2026), Puraniks Abitante Fiore Phase 2C1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Puraniks Abitante Fiore Phase 2C1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Puraniks Abitante Fiore Phase 2C1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Puraniks Abitante Fiore Phase 2C1 is registered on MahaRERA as P52100049352, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Puraniks Abitante Fiore Phase 2C1's possession date changes?
The latest dates are on Puraniks Abitante Fiore Phase 2C1's MahaRERA page (P52100049352). GharKundli's Kundli Watch sends a free WhatsApp update on Puraniks Abitante Fiore Phase 2C1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Puraniks Abitante Fiore Phase 2C1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Puraniks Abitante Fiore Phase 2C1 has 2 buildings filed: I - Alvino with 30 floors; J - Amaranta with 30 floors.
What is the track record of Puraniks Abitante Fiore Phase 2C1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 6 finished, all within the promised date; 21 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Puraniks Abitante Fiore Phase 2C1?
Google Maps has reviews of Puraniks Abitante Fiore Phase 2C1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Puraniks Abitante Fiore Phase 2C1?
Puraniks Abitante Fiore Phase 2C1 by Puranik Buildcon Private Limited (Fortune) is in Bavdhan, Pune (pincode 411021), Maharashtra, and is registered on MahaRERA as P52100049352, per GharKundli's check of MahaRERA records.
How many homes are in Puraniks Abitante Fiore Phase 2C1?
According to GharKundli's check of MahaRERA records (updated November 2026), Puraniks Abitante Fiore Phase 2C1 has 448 homes in 2 towers registered on MahaRERA, and 67% of them are sold or booked.
When was Puraniks Abitante Fiore Phase 2C1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Puraniks Abitante Fiore Phase 2C1 was registered on MahaRERA on 7 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Puraniks Abitante Fiore Phase 2C1?
3 court cases are listed for Puraniks Abitante Fiore Phase 2C1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Puraniks Abitante Fiore Phase 2C1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Puranik Buildcon Private Limited, the company Fortune files this project under, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Puraniks Abitante Fiore Phase 2C1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in Bavdhan
- Purva Aspire
- Survi Heritage
- Symphony
- Mont Vert Axis
- Infinia Vista
- Geras Isle Royale Tower 4 and 5
- SHANTAI
- Ratan Vihar
Other projects by Puranik Buildcon Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.