KAILASH TOWER
by KAILASH DEVELOPERS · Vasai, Palghar
Possession: KAILASH TOWER is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000008452. Status: Completed. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KAILASH TOWER?
How the possession date of KAILASH TOWER has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT99000005328)
Reason the builder gave MahaRERA:
“Respected Sir, We have already applied for the Occupancy certificate towards the authority as on 13th August 2019. However still we are in process of the obtaining of Occupancy Certificate from the VVCMC Authority as on date. We have alread…” Read the full reason
“Respected Sir, We have already applied for the Occupancy certificate towards the authority as on 13th August 2019. However still we are in process of the obtaining of Occupancy Certificate from the VVCMC Authority as on date. We have already uploaded Form 4 as obtained by architect in the respect of above project. We request you to kindly extend the Date of Completion so as to obtain certificate from the authority. Thanking You”30 June 2022
Extended at the builder's request (MahaRERA application EXT99000010198)
Reason the builder gave MahaRERA:
“Respected Sir, We Promoter of above mentioned project wants to state as follows: - 1. Completion of Project: - We promoters of the above mentioned project have timely completed all the construction and finishing work of the project. We are…” Read the full reason
“Respected Sir, We Promoter of above mentioned project wants to state as follows: - 1. Completion of Project: - We promoters of the above mentioned project have timely completed all the construction and finishing work of the project. We are enclosing form 4 of architect stating completion of Project, for your ready reference. 2. Application of Occupancy Certificate: - We had made application for grant of Occupancy Certificate to the project 13/08/2019, which is Still Pending with the Town Planning Department of Municipal Corporation i.e. VVCMC. We are enclosing copy of same for your referenc…”30 December 2024
Extended at the builder's request (MahaRERA application EXT99000012931)
Reason the builder gave MahaRERA: “As per Letter Attached”
Source: KAILASH TOWER’s extension records on MahaRERA (P99000008452), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KAILASH TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000008452
- Status
- Completed
- Builder
- KAILASH DEVELOPERS
- Location
- Vasai, Palghar · 401303
- Project type
- Others
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2024
- Delay so far
- 60 months
- Homes
- 118
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of KAILASH TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KAILASH TOWER | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KAILASH TOWER every month.
KAILASH TOWER: buildings, flats and land, as filed on MahaRERA
- Buildings: KAILASH TOWER (14 floors)
- Land: 1,397 sq m (about 0.3 acres) · sanctioned built-up 6,056 sq m · recreational space 844 sq m
The builder’s record and reviews
Kailash Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 56 months). 4 complaints on MahaRERA across 1 project.
Read Google reviews of KAILASH TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KAILASH TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KAILASH TOWER
What is the possession date of KAILASH TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KAILASH TOWER in Vasai, Palghar is 30 December 2024 — 60 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KAILASH TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KAILASH TOWER's builder has filed on MahaRERA, the official one, is 30 December 2024, already 60 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KAILASH TOWER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "Respected Sir, We have already applied for the Occupancy certificate towards the authority as on 13th August 2019. However still we are in process of the obtaining of Occupancy Certificate from the VVCMC Authority as on date. We have already uploaded Form 4 as obtained by architect in the respect of above project. We request you to kindly extend the Date of Completion so as to obtain certificate from the authority. Thanking You"; to 30 June 2022, giving the reason "Respected Sir, We Promoter of above mentioned project wants to state as follows: - 1. Completion of Project: - We promoters of the above mentioned project have timely completed all the construction and finishing work of the project. We are enclosing form 4 of architect stating completion of Project, for your ready reference. 2. Application of Occupancy Certificate: - We had made application for grant of Occupancy Certificate to the project 13/08/2019, which is Still Pending with the Town Planning Department of Municipal Corporation i.e. VVCMC. We are enclosing copy of same for your referenc…"; to 30 December 2024, giving the reason "As per Letter Attached".
What is the RERA number of KAILASH TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KAILASH TOWER in Vasai, Palghar is P99000008452.
Is KAILASH TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER is registered as P99000008452 and its status is "Completed".
What is the construction status of KAILASH TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER's status on MahaRERA is "Completed". As filed by the builder, slab work on KAILASH TOWER is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does KAILASH TOWER have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KAILASH TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER is registered on MahaRERA as P99000008452, its MahaRERA status is "Completed", its completion date has moved 60 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KAILASH TOWER's possession date changes?
The latest dates are on KAILASH TOWER's MahaRERA page (P99000008452). GharKundli's Kundli Watch sends a free WhatsApp update on KAILASH TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KAILASH TOWER have?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER has one building filed: KAILASH TOWER with 14 floors.
How big is the land of KAILASH TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER stands on 1,397 sq m of land (about 0.3 acres), with 6,056 sq m of sanctioned built-up area and 844 sq m of recreational open space.
What is the track record of KAILASH TOWER's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Kailash Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 56 months). 4 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KAILASH TOWER?
Google Maps has reviews of KAILASH TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KAILASH TOWER?
KAILASH TOWER by KAILASH DEVELOPERS is in Vasai, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000008452, per GharKundli's check of MahaRERA records.
How many homes are in KAILASH TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER has 118 homes in 1 tower registered on MahaRERA.
When was KAILASH TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KAILASH TOWER was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KAILASH TOWER?
No court cases are listed for KAILASH TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of KAILASH TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KAILASH DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of KAILASH TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Vasai
- SERENO
- ALTURA UMELE
- PATIL ARCADE
- YASHWANT COUNTY
- AAI CHANDIKA HILLS
- SANSKRUTI EMERALD
- Vishwakarma Heights
- DEEP SKY F WING
Other projects by KAILASH DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.