GOLDEN PALMS

by PRAKASH NANDLAL LAKHWANI · Lonavala, Pune

Possession date of GOLDEN PALMS: 31 March 2027, moved from 31 December 2025 (15 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100050226, and currently active.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GOLDEN PALMS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GOLDEN PALMS has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA12082622113)

    Reason the builder gave MahaRERA:
    “The promoter respectfully submits that the delay in completion of the project "Golden Palms" (MahaRERA Registration No. P52100050226) has arisen on account of the revision of the sanctioned building plan by the Pimpri Chinchwad Municipal Co…” Read the full reason“The promoter respectfully submits that the delay in completion of the project "Golden Palms" (MahaRERA Registration No. P52100050226) has arisen on account of the revision of the sanctioned building plan by the Pimpri Chinchwad Municipal Corporation (PCMC). The said revision required the promoter to re-align certain aspects of the construction schedule, a circumstance that could not have been foreseen at the time of the original project registration and the proposed date of completion. The promoter wishes to humbly submit that construction of the project is progressing steadily and in good…”

Source: GOLDEN PALMS’s extension records on MahaRERA (P52100050226), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GOLDEN PALMS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100050226
Status
Registered and active
Builder
PRAKASH NANDLAL LAKHWANI
Location
Lonavala, Pune · 410401
Project type
Others
Registered on
27 Mar 2023
Completion date at registration
December 2025
Latest completion date
March 2027
Delay so far
15 months
Homes
21
Sold or booked
29%
Towers
21
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GOLDEN PALMS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A1 - 1100%100%100%100%
BUILDING A1 - 2100%100%100%100%
BUILDING A1 - 3100%100%100%100%
BUILDING A1 - 4100%100%100%100%
BUILDING A1 - 5100%100%100%100%
BUILDING A1 - 6100%100%100%100%
BUILDING A1 - 7100%100%100%100%
BUILDING A1 - 8100%100%100%100%
BUILDING A1 - 9100%100%100%100%
BUILDING A1 - 10100%100%100%100%
BUILDING A1 - 11100%100%100%0%
BUILDING A1 - 12100%100%100%0%
BUILDING A1 - 13100%100%100%0%
BUILDING A1 - 14100%100%100%0%
BUILDING A1 - 15100%100%100%0%
BUILDING A1 - 16100%100%100%0%
BUILDING A2 - 1100%75%50%0%
BUILDING A2 - 2100%75%50%0%
BUILDING A2 - 3100%75%50%0%
BUILDING A2 - 4100%75%50%0%
BUILDING A2 - 5100%75%50%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A1 - 1: covers 2 floors
  • BUILDING A1 - 2: covers 2 floors
  • BUILDING A1 - 3: covers 2 floors
  • BUILDING A1 - 4: covers 2 floors
  • BUILDING A1 - 5: covers 2 floors
  • BUILDING A1 - 6: covers 2 floors
  • BUILDING A1 - 7: covers 2 floors
  • BUILDING A1 - 8: covers 2 floors
  • BUILDING A1 - 9: covers 2 floors
  • BUILDING A1 - 10: covers 2 floors
  • BUILDING A1 - 11: covers 2 floors
  • BUILDING A1 - 12: covers 2 floors
  • BUILDING A1 - 13: covers 2 floors
  • BUILDING A1 - 14: covers 2 floors
  • BUILDING A1 - 15: covers 2 floors
  • BUILDING A1 - 16: covers 2 floors
  • BUILDING A2 - 1: covers 2 floors
  • BUILDING A2 - 2: covers 2 floors
  • BUILDING A2 - 3: covers 2 floors
  • BUILDING A2 - 4: covers 2 floors
  • BUILDING A2 - 5: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOLDEN PALMS every month.

GOLDEN PALMS: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A1 - 1 (2 floors, 1 units) · BUILDING A1 - 2 (2 floors, 1 units) · BUILDING A1 - 3 (2 floors, 1 units) · BUILDING A1 - 4 (2 floors, 1 units) · BUILDING A1 - 5 (2 floors, 1 units) · BUILDING A1 - 6 (2 floors, 1 units) · BUILDING A1 - 7 (2 floors, 1 units) · BUILDING A1 - 8 (2 floors, 1 units) · and 13 more
  • Land: 10,600 sq m (about 2.6 acres) · sanctioned built-up 3,621 sq m · recreational space 2,550 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GOLDEN PALMS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GOLDEN PALMS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GOLDEN PALMS

What is the possession date of GOLDEN PALMS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GOLDEN PALMS in Lonavala, Pune is 31 March 2027 — 15 months later than 31 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for GOLDEN PALMS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GOLDEN PALMS's builder has filed on MahaRERA, the official one, is 31 March 2027, already 15 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GOLDEN PALMS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The promoter respectfully submits that the delay in completion of the project "Golden Palms" (MahaRERA Registration No. P52100050226) has arisen on account of the revision of the sanctioned building plan by the Pimpri Chinchwad Municipal Corporation (PCMC). The said revision required the promoter to re-align certain aspects of the construction schedule, a circumstance that could not have been foreseen at the time of the original project registration and the proposed date of completion. The promoter wishes to humbly submit that construction of the project is progressing steadily and in good…".

What is the RERA number of GOLDEN PALMS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GOLDEN PALMS in Lonavala, Pune is P52100050226.

Is GOLDEN PALMS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS is registered as P52100050226 and its status is "Registered and active".

What is the construction status of GOLDEN PALMS?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 75% to 100% across 21 towers. GharKundli's full report compares construction progress with the deadline.

Does GOLDEN PALMS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GOLDEN PALMS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS is registered on MahaRERA as P52100050226, its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GOLDEN PALMS's possession date changes?

The latest dates are on GOLDEN PALMS's MahaRERA page (P52100050226). GharKundli's Kundli Watch sends a free WhatsApp update on GOLDEN PALMS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GOLDEN PALMS have?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS has 21 buildings filed: BUILDING A1 - 1 with 2 floors and 1 units; BUILDING A1 - 2 with 2 floors and 1 units; BUILDING A1 - 3 with 2 floors and 1 units; BUILDING A1 - 4 with 2 floors and 1 units; BUILDING A1 - 5 with 2 floors and 1 units; BUILDING A1 - 6 with 2 floors and 1 units; and 15 more.

How big is the land of GOLDEN PALMS?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS stands on 10,600 sq m of land (about 2.6 acres), with 3,621 sq m of sanctioned built-up area and 2,550 sq m of recreational open space.

Where can I read reviews of GOLDEN PALMS?

Google Maps has reviews of GOLDEN PALMS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GOLDEN PALMS?

GOLDEN PALMS by PRAKASH NANDLAL LAKHWANI is in Lonavala, Pune (pincode 410401), Maharashtra, and is registered on MahaRERA as P52100050226, per GharKundli's check of MahaRERA records.

How many homes are in GOLDEN PALMS?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS has 21 homes in 21 towers registered on MahaRERA, and 29% of them are sold or booked.

When was GOLDEN PALMS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN PALMS was registered on MahaRERA on 27 March 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on GOLDEN PALMS?

No court cases are listed for GOLDEN PALMS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GOLDEN PALMS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRAKASH NANDLAL LAKHWANI.

All projects with possession due in 2027 in Pune →

Other projects in pincode 410401

All 50 projects in Lonavala (410401) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.