Possession: MANAV MAITRY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000012261. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about MANAV MAITRY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MANAV MAITRY has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000013057)

    Reason the builder gave MahaRERA:
    “PROJECT MANAV MAITRY WAS FIRST REVISED VIDE REVISED DEVELOPMENT PERMISSION DATED 29-11-2021 IN WHICH ADDITIONAL BUA WAS SANCTIONED WAS 900.54 SQ.MTRS. & SAME PROJECT WAS AGAIN REVISED VIDE REVISED DEV. PERMISSION DATED 07-10-2022 & IN WHICH…” Read the full reason“PROJECT MANAV MAITRY WAS FIRST REVISED VIDE REVISED DEVELOPMENT PERMISSION DATED 29-11-2021 IN WHICH ADDITIONAL BUA WAS SANCTIONED WAS 900.54 SQ.MTRS. & SAME PROJECT WAS AGAIN REVISED VIDE REVISED DEV. PERMISSION DATED 07-10-2022 & IN WHICH TOTAL BUA OF THE PROPOSAL WAS SANCTIONED AS 2093 SQ.MTRS. WITH SAME PLOT AREA OF 1220 SQ.MTRS. PROMOTER HAS OBTAINED NOC FROM 25 FLAT/SHOP OWNERS OUT OF 42 UNITS SOLD WHICH COMES TO 59.52% & PROMOTER REQUEST FOR PROJECT EXTENSION UPTO 31-12-2025”

Source: MANAV MAITRY’s extension records on MahaRERA (P99000012261), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MANAV MAITRY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000012261
Status
Completed
Builder
MANAV REALTORS
Location
Gaothan Village, Palghar · 401303
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
December 2021
Latest completion date
December 2025
Delay so far
48 months
Homes
51
Sold or booked
87%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MANAV MAITRY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MANAV MAITRY A WING100%100%100%0%
MANAV MAITRY B WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANAV MAITRY every month.

MANAV MAITRY: buildings, flats and land, as filed on MahaRERA

  • Buildings: MANAV MAITRY A WING (6 floors) · MANAV MAITRY B WING (6 floors)
  • Land: 1,220 sq m (about 0.3 acres) · sanctioned built-up 1,210 sq m
  • Boundaries filed include: MUNICIPALITY ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MANAV MAITRY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MANAV MAITRY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MANAV MAITRY

What is the possession date of MANAV MAITRY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MANAV MAITRY in Gaothan Village, Palghar is 31 December 2025 — 48 months later than 30 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MANAV MAITRY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MANAV MAITRY's builder has filed on MahaRERA, the official one, is 31 December 2025, already 48 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MANAV MAITRY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "PROJECT MANAV MAITRY WAS FIRST REVISED VIDE REVISED DEVELOPMENT PERMISSION DATED 29-11-2021 IN WHICH ADDITIONAL BUA WAS SANCTIONED WAS 900.54 SQ.MTRS. & SAME PROJECT WAS AGAIN REVISED VIDE REVISED DEV. PERMISSION DATED 07-10-2022 & IN WHICH TOTAL BUA OF THE PROPOSAL WAS SANCTIONED AS 2093 SQ.MTRS. WITH SAME PLOT AREA OF 1220 SQ.MTRS. PROMOTER HAS OBTAINED NOC FROM 25 FLAT/SHOP OWNERS OUT OF 42 UNITS SOLD WHICH COMES TO 59.52% & PROMOTER REQUEST FOR PROJECT EXTENSION UPTO 31-12-2025".

What is the RERA number of MANAV MAITRY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MANAV MAITRY in Gaothan Village, Palghar is P99000012261.

Is MANAV MAITRY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY is registered as P99000012261 and its status is "Completed".

What is the construction status of MANAV MAITRY?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does MANAV MAITRY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MANAV MAITRY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY is registered on MahaRERA as P99000012261, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MANAV MAITRY's possession date changes?

The latest dates are on MANAV MAITRY's MahaRERA page (P99000012261). GharKundli's Kundli Watch sends a free WhatsApp update on MANAV MAITRY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MANAV MAITRY have?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY has 2 buildings filed: MANAV MAITRY A WING with 6 floors; MANAV MAITRY B WING with 6 floors.

How big is the land of MANAV MAITRY?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY stands on 1,220 sq m of land (about 0.3 acres), with 1,210 sq m of sanctioned built-up area.

Where can I read reviews of MANAV MAITRY?

Google Maps has reviews of MANAV MAITRY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MANAV MAITRY?

MANAV MAITRY by MANAV REALTORS is in Gaothan Village, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000012261, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNICIPALITY ROAD.

How many homes are in MANAV MAITRY?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY has 51 homes in 2 towers registered on MahaRERA, and 87% of them are sold or booked.

When was MANAV MAITRY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MANAV MAITRY was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MANAV MAITRY?

No court cases are listed for MANAV MAITRY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MANAV MAITRY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MANAV REALTORS.