Possession date of Hayaat Palace: 31 August 2023, moved from 30 September 2020 (35 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000008597. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (August 2023) has passed.
What do you want to know about Hayaat Palace?
How the possession date of Hayaat Palace has moved
30 September 2020
Completion date given when the project was registered
30 September 2021
Extended at the builder's request (MahaRERA application EXT99000006308)
Reason the builder gave MahaRERA: “The project work is more than 85% complete, but due to COVID 19 pandemic, there is financial and labour crunch, due to which the project is getting delayed. We would like to apply for extension so that we can complete the work on time.”
31 August 2023
Extended at the builder's request (MahaRERA application EXT99000011887)
Reason the builder gave MahaRERA: “the project is more than 95% complete but receipt of Occupancy Certificate (OC) is pending. We assure you that we will receive the OC very soon and will upload the same along with Form 4.”
Source: Hayaat Palace’s extension records on MahaRERA (P99000008597), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hayaat Palace
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000008597
- Status
- Lapsed (registration period ended)
- Builder
- Sky Developers
- Location
- Vasai East, Palghar · 401208
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- September 2020
- Latest completion date
- August 2023
- Delay so far
- 35 months
- Homes
- 107
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
Construction progress of Hayaat Palace, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Wing | 100% | 100% | 10% | 100% |
| B Wing | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hayaat Palace every month.
Hayaat Palace: buildings, flats and land, as filed on MahaRERA
- Buildings: A Wing (16 floors) · B Wing (16 floors)
- Land: 6,826 sq m (about 1.7 acres) · sanctioned built-up 3,927 sq m · recreational space 727 sq m
- Boundaries filed include: Recreation Garden
The builder’s record and reviews
Sky Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Hayaat Palace →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hayaat Palace: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Hayaat Palace
What is the possession date of Hayaat Palace?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Hayaat Palace in Vasai East, Palghar is 31 August 2023 — 35 months later than 30 September 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Hayaat Palace?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hayaat Palace's builder has filed on MahaRERA, the official one, is 31 August 2023, already 35 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hayaat Palace extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2021, giving the reason "The project work is more than 85% complete, but due to COVID 19 pandemic, there is financial and labour crunch, due to which the project is getting delayed. We would like to apply for extension so that we can complete the work on time."; to 31 August 2023, giving the reason "the project is more than 95% complete but receipt of Occupancy Certificate (OC) is pending. We assure you that we will receive the OC very soon and will upload the same along with Form 4.".
What is the RERA number of Hayaat Palace?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Hayaat Palace in Vasai East, Palghar is P99000008597.
Is Hayaat Palace registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace is registered as P99000008597 and its status is "Lapsed (registration period ended)".
What is the construction status of Hayaat Palace?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Hayaat Palace have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Hayaat Palace safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace is registered on MahaRERA as P99000008597, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 35 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Hayaat Palace's possession date changes?
The latest dates are on Hayaat Palace's MahaRERA page (P99000008597). GharKundli's Kundli Watch sends a free WhatsApp update on Hayaat Palace every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hayaat Palace have?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace has 2 buildings filed: A Wing with 16 floors; B Wing with 16 floors.
How big is the land of Hayaat Palace?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace stands on 6,826 sq m of land (about 1.7 acres), with 3,927 sq m of sanctioned built-up area and 727 sq m of recreational open space.
What is the track record of Hayaat Palace's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sky Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Hayaat Palace?
Google Maps has reviews of Hayaat Palace written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Hayaat Palace?
Hayaat Palace by Sky Developers is in Vasai East, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000008597, per GharKundli's check of MahaRERA records. Its boundaries filed there include Recreation Garden.
How many homes are in Hayaat Palace?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace has 107 homes in 2 towers registered on MahaRERA.
When was Hayaat Palace registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Hayaat Palace was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Hayaat Palace?
No court cases are listed for Hayaat Palace on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Hayaat Palace?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sky Developers, which has 9 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Hayaat Palace
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401208
- Imperial Splendora F wing
- SERENO
- Agarwal Sky Heights
- Sunteck OneWorld -Tower 1
- Akhand Phase 3
- ARVIAN GENESIS
- ANANTA ONE
- Suraksha Smart City - Phase II
Other projects by Sky Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.