KINI TOWER

by SHUBH SHWET DEVELOPERS · Virar East, PalgharAlso near Virar West

Possession date of KINI TOWER: 31 July 2026, moved from 30 August 2019 (79 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000010978. Status: Lapsed (registration period ended). Its completion date has moved from August 2019 to July 2026: 79 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about KINI TOWER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KINI TOWER has moved

  1. 30 August 2019

    Completion date given when the project was registered

  2. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT99000002401)

    Reason the builder gave MahaRERA: “WE HAVE GIVEN CONTRACT WITH MATERIAL TO THE CONTRACTOR BUT DUE TO FINANCIAL CRISES AND DISPUTE AMONG THE PARTNERS THEY COULD NOT COMPLETE THE CONTRACT..NOW WE APPOINT ANOTHER CONTRACTOR TO COMPLETE THE PROJECT.”
  3. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT99000011705)

    Reason the builder gave MahaRERA: “BUILDING IS 100 % COMPLETED AND READY TO FIT OUT BUT THIS BUILDING CONSTRUCTED ON HDIL LAYOUT AND THERE IS DELAY IN GETTING OF ENVIORNMENTAL CLERANCE BY HDIL.. THIS IS THE REASON WE WANT EXTENSION.”
  4. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: KINI TOWER’s extension records on MahaRERA (P99000010978), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KINI TOWER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000010978
Status
Lapsed (registration period ended)
Builder
SHUBH SHWET DEVELOPERS
Location
Virar East, Palghar · 401303
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
August 2019
Latest completion date
July 2026
Delay so far
79 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
69
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KINI TOWER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KINI TOWER100%63%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KINI TOWER every month.

KINI TOWER: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KINI TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KINI TOWER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KINI TOWER

What is the possession date of KINI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KINI TOWER in Virar East, Palghar is 31 July 2026 — 79 months later than 30 August 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for KINI TOWER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KINI TOWER's builder has filed on MahaRERA, the official one, is 31 July 2026, already 79 months later than the 30 August 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KINI TOWER extended?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2021, giving the reason "WE HAVE GIVEN CONTRACT WITH MATERIAL TO THE CONTRACTOR BUT DUE TO FINANCIAL CRISES AND DISPUTE AMONG THE PARTNERS THEY COULD NOT COMPLETE THE CONTRACT..NOW WE APPOINT ANOTHER CONTRACTOR TO COMPLETE THE PROJECT."; to 31 March 2026, giving the reason "BUILDING IS 100 % COMPLETED AND READY TO FIT OUT BUT THIS BUILDING CONSTRUCTED ON HDIL LAYOUT AND THERE IS DELAY IN GETTING OF ENVIORNMENTAL CLERANCE BY HDIL.. THIS IS THE REASON WE WANT EXTENSION.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of KINI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KINI TOWER in Virar East, Palghar is P99000010978.

Is KINI TOWER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER is registered as P99000010978 and its status is "Lapsed (registration period ended)".

What is the construction status of KINI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KINI TOWER is 63% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does KINI TOWER have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KINI TOWER safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER is registered on MahaRERA as P99000010978, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 79 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KINI TOWER's possession date changes?

The latest dates are on KINI TOWER's MahaRERA page (P99000010978). GharKundli's Kundli Watch sends a free WhatsApp update on KINI TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KINI TOWER have?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER has one building filed: KINI TOWER with 8 floors.

How big is the land of KINI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER stands on 4,088 sq m of land (about 1.0 acres), with 4,088 sq m of sanctioned built-up area.

Where can I read reviews of KINI TOWER?

Google Maps has reviews of KINI TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KINI TOWER?

KINI TOWER by SHUBH SHWET DEVELOPERS is in Virar East, Palghar (pincode 401303), near Virar West, Maharashtra, and is registered on MahaRERA as P99000010978, per GharKundli's check of MahaRERA records.

How many homes are in KINI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER has 69 homes in 1 tower registered on MahaRERA.

When was KINI TOWER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KINI TOWER was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KINI TOWER?

No court cases are listed for KINI TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KINI TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHUBH SHWET DEVELOPERS.

All projects with possession due in 2026 in Palghar →

Other projects in pincode 401303

All 210 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.