Ecstasy Sylvanscape
by ECSTASY COMMUNITIES PVT LTD · Mulshi, Pune 412108Registered on MahaRERA as “SYLVANSCAPE”
What’s in the report? →Possession date of Ecstasy Sylvanscape (MahaRERA P52100054087): 30 September 2027, moved from 31 December 2025 (17 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100054087, and currently active. Its completion date has moved from December 2025 to September 2027: 17 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100054087, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Ecstasy Sylvanscape?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ecstasy Sylvanscape has moved
31 December 2025
Completion date given when the project was registered
31 May 2027
Extended at the builder's request (MahaRERA application EA27032620399)
Reason the builder gave MahaRERA: “Due to heavy rains, availability of skilled labourers, & consistent Dewatering Project Work Scheduled has been shuffled and Re-scheduling of Work Taska has made non anticipated delay in work activities”
30 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ecstasy Sylvanscape’s extension records on MahaRERA (P52100054087), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ecstasy Sylvanscape
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100054087
- Status
- Registered and active
- Builder
- ECSTASY COMMUNITIES PVT LTD
- Location
- Mulshi, Pune · 412108
- Project type
- Plotted
- Registered on
- 27 Dec 2023
- Completion date at registration
- December 2025
- Latest completion date
- September 2027
- Delay so far
- 17 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Ecstasy Sylvanscape: buildings, flats and land, as filed on MahaRERA
- Land: 3,181 sq m (about 0.8 acres) · recreational space 318 sq m
- Land, as filed: GAT NO 426 , GAT NO 427
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Ecstasy Sylvanscape →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ecstasy Sylvanscape: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ecstasy Sylvanscape
What is the possession date of Ecstasy Sylvanscape?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ecstasy Sylvanscape in Mulshi, Pune is 30 September 2027 — 17 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 17 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Ecstasy Sylvanscape?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ecstasy Sylvanscape's builder has filed on MahaRERA, the official one, is 30 September 2027, already 17 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ecstasy Sylvanscape extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ecstasy Sylvanscape's builder applied to MahaRERA to extend the completion date once: to 31 May 2027, giving the reason "Due to heavy rains, availability of skilled labourers, & consistent Dewatering Project Work Scheduled has been shuffled and Re-scheduling of Work Taska has made non anticipated delay in work activities". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Ecstasy Sylvanscape?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ecstasy Sylvanscape in Mulshi, Pune is P52100054087.
Is Ecstasy Sylvanscape registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ecstasy Sylvanscape is registered as P52100054087 and its status is "Registered and active".
What is the current construction status of Ecstasy Sylvanscape? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ecstasy Sylvanscape's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Ecstasy Sylvanscape have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ecstasy Sylvanscape safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ecstasy Sylvanscape is registered on MahaRERA as P52100054087, its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ecstasy Sylvanscape?
Ecstasy Sylvanscape is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ecstasy Sylvanscape?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Ecstasy Sylvanscape: gharkundli.com/tools/property-cost-calculator
Has Ecstasy Sylvanscape received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ecstasy Sylvanscape is still under construction, with 30 September 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Ecstasy Sylvanscape uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ecstasy Sylvanscape was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ecstasy Sylvanscape's possession date changes?
The latest dates are on Ecstasy Sylvanscape's MahaRERA page (P52100054087). GharKundli's Kundli Watch sends a free WhatsApp update on Ecstasy Sylvanscape every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Ecstasy Sylvanscape?
According to GharKundli's check of MahaRERA records (updated October 2026), Ecstasy Sylvanscape stands on 3,181 sq m of land (about 0.8 acres) and 318 sq m of recreational open space.
What are the reviews of Ecstasy Sylvanscape?
Google Maps has reviews of Ecstasy Sylvanscape written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ecstasy Sylvanscape?
Ecstasy Sylvanscape by ECSTASY COMMUNITIES PVT LTD is in Mulshi, Pune, pincode 412108, Maharashtra, and is registered on MahaRERA as P52100054087, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO 426 , GAT NO 427. GharKundli lists all 73 MahaRERA projects in Paud (412108).
When was Ecstasy Sylvanscape registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ecstasy Sylvanscape was registered on MahaRERA on 27 December 2023. GharKundli did not find a title report on the land on file there.
Does Ecstasy Sylvanscape have any legal issues or court cases?
No court cases are listed for Ecstasy Sylvanscape on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ecstasy Sylvanscape?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ECSTASY COMMUNITIES PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of Ecstasy Sylvanscape
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Paud (412108)
- Iris View
- Aarambh
- LIFE REPUBLIC SECTOR R31/31st AVENUE – ECHOES/PHASE – 1
- Casa Feliz
- Nandanvan
- Shivram Heights
- Sai Planet
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.