MARUTI PRAKKRUTI
by BHAVANA VINOD PATEL · Ambadi Road, PalgharAlso near Vasai West, Diwanman, Chulne
Possession date of MARUTI PRAKKRUTI: 30 March 2023, moved from 15 March 2019 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000006293. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (March 2023) has passed.
What do you want to know about MARUTI PRAKKRUTI?
How the possession date of MARUTI PRAKKRUTI has moved
15 March 2019
Completion date given when the project was registered
30 September 2021
Extended at the builder's request (MahaRERA application EXT99000003828)
Reason the builder gave MahaRERA: “Due to unsold bungalows followed by shortage of funds, our working capital has affected largely and as a result, it is not possible to complete the said project within the aforesaid date.”
30 March 2023
Extended at the builder's request (MahaRERA application EXT99000012010)
Reason the builder gave MahaRERA:
“As said project was proposed to be completed by 30th of March 2022. However, due to unsold bungalows followed by shortage of funds, our working capital has affected largely and as a result, it is not possible to complete the said project wi…” Read the full reason
“As said project was proposed to be completed by 30th of March 2022. However, due to unsold bungalows followed by shortage of funds, our working capital has affected largely and as a result, it is not possible to complete the said project within the aforesaid date. Hence we wish to seek an extension of 1 year for completion of project i.e. 30th March 2023,in compliance to the provisions of the Act i.e. section 6 of The Real Estate (Regulation And Development) Act, 2016.”
Source: MARUTI PRAKKRUTI’s extension records on MahaRERA (P99000006293), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MARUTI PRAKKRUTI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000006293
- Status
- Lapsed (registration period ended)
- Builder
- BHAVANA VINOD PATEL
- Location
- Ambadi Road, Palghar · 401202
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- March 2023
- Delay so far
- 48 months
- Homes
- 30
- Sold or booked
- 29%
- Towers
- 32
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MARUTI PRAKKRUTI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| UNIT - 1 | 100% | 100% | 70% | 0% |
| UNIT 2 | 100% | 100% | 70% | 0% |
| UNIT 3 | 0% | 0% | 0% | 0% |
| UNIT 4 | 0% | 0% | 0% | 0% |
| UNIT 5 | 0% | 0% | 0% | 0% |
| UNIT 6 | 0% | 0% | 0% | 0% |
| UNIT 7 | 0% | 0% | 0% | 0% |
| UNIT 8 | 0% | 0% | 0% | 0% |
| UNIT 9 | 0% | 0% | 0% | 0% |
| UNIT 10 | 0% | 0% | 0% | 0% |
| UNIT 11 | 40% | 0% | 0% | 0% |
| UNIT 12 | 40% | 0% | 0% | 0% |
| UNIT 13 | 40% | 0% | 0% | 0% |
| UNIT 14 | 40% | 0% | 0% | 0% |
| UNIT 15 | 40% | 0% | 0% | 0% |
| UNIT 16 | 40% | 0% | 0% | 0% |
| UNIT 17 | 40% | 0% | 0% | 0% |
| UNIT 18 | 40% | 0% | 0% | 0% |
| UNIT 19 | 40% | 0% | 0% | 0% |
| UNIT 20 | 40% | 0% | 0% | 0% |
| UNIT 21 | 40% | 0% | 0% | 0% |
| UNIT 22 | 40% | 0% | 0% | 0% |
| UNIT 23 | 40% | 0% | 0% | 0% |
| UNIT 24 | 40% | 0% | 0% | 0% |
| UNIT 25 | 75% | 0% | 0% | 0% |
| UNIT 26 | 75% | 0% | 0% | 0% |
| UNIT 27 | 75% | 0% | 0% | 0% |
| UNIT 28 | 75% | 0% | 0% | 0% |
| UNIT 29 | 75% | 0% | 0% | 0% |
| UNIT 30 | 75% | 0% | 0% | 0% |
Showing 30 of 32 towers.
Commencement certificate (CC), as filed on MahaRERA
- UNIT - 1: covers 3 floors
- UNIT 2: covers 3 floors
- UNIT 3: covers 3 floors
- UNIT 4: covers 3 floors
- UNIT 5: covers 3 floors
- UNIT 6: covers 3 floors
- UNIT 7: covers 3 floors
- UNIT 8: covers 3 floors
- UNIT 9: covers 3 floors
- UNIT 10: covers 3 floors
- UNIT 11: covers 3 floors
- UNIT 12: covers 3 floors
- UNIT 13: covers 3 floors
- UNIT 14: covers 3 floors
- UNIT 15: covers 3 floors
- UNIT 16: covers 3 floors
- UNIT 17: covers 3 floors
- UNIT 18: covers 3 floors
- UNIT 19: covers 3 floors
- UNIT 20: covers 3 floors
- UNIT 21: covers 3 floors
- UNIT 22: covers 3 floors
- UNIT 23: covers 3 floors
- UNIT 24: covers 3 floors
- UNIT 25: covers 3 floors
- UNIT 26: covers 3 floors
- UNIT 27: covers 3 floors
- UNIT 28: covers 3 floors
- UNIT 29: covers 3 floors
- UNIT 30: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARUTI PRAKKRUTI every month.
MARUTI PRAKKRUTI: buildings, flats and land, as filed on MahaRERA
- Buildings: UNIT - 1 (3 floors, 1 units) · UNIT 2 (3 floors, 1 units) · UNIT 3 (3 floors, 1 units) · UNIT 4 (3 floors, 1 units) · UNIT 5 (3 floors, 1 units) · UNIT 6 (3 floors, 1 units) · UNIT 7 (3 floors, 1 units) · UNIT 8 (3 floors, 1 units) · and 22 more
- Land: 8,800 sq m (about 2.2 acres) · sanctioned built-up 2,231 sq m · recreational space 1,320 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MARUTI PRAKKRUTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MARUTI PRAKKRUTI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MARUTI PRAKKRUTI
What is the possession date of MARUTI PRAKKRUTI?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MARUTI PRAKKRUTI in Ambadi Road, Palghar is 30 March 2023 — 48 months later than 15 March 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MARUTI PRAKKRUTI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MARUTI PRAKKRUTI's builder has filed on MahaRERA, the official one, is 30 March 2023, already 48 months later than the 15 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MARUTI PRAKKRUTI extended?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2021, giving the reason "Due to unsold bungalows followed by shortage of funds, our working capital has affected largely and as a result, it is not possible to complete the said project within the aforesaid date."; to 30 March 2023, giving the reason "As said project was proposed to be completed by 30th of March 2022. However, due to unsold bungalows followed by shortage of funds, our working capital has affected largely and as a result, it is not possible to complete the said project within the aforesaid date. Hence we wish to seek an extension of 1 year for completion of project i.e. 30th March 2023,in compliance to the provisions of the Act i.e. section 6 of The Real Estate (Regulation And Development) Act, 2016.".
What is the RERA number of MARUTI PRAKKRUTI?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MARUTI PRAKKRUTI in Ambadi Road, Palghar is P99000006293.
Is MARUTI PRAKKRUTI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI is registered as P99000006293 and its status is "Lapsed (registration period ended)".
What is the construction status of MARUTI PRAKKRUTI?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.
Does MARUTI PRAKKRUTI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MARUTI PRAKKRUTI safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI is registered on MahaRERA as P99000006293, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MARUTI PRAKKRUTI's possession date changes?
The latest dates are on MARUTI PRAKKRUTI's MahaRERA page (P99000006293). GharKundli's Kundli Watch sends a free WhatsApp update on MARUTI PRAKKRUTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MARUTI PRAKKRUTI have?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI has 30 buildings filed: UNIT - 1 with 3 floors and 1 units; UNIT 2 with 3 floors and 1 units; UNIT 3 with 3 floors and 1 units; UNIT 4 with 3 floors and 1 units; UNIT 5 with 3 floors and 1 units; UNIT 6 with 3 floors and 1 units; and 24 more.
How big is the land of MARUTI PRAKKRUTI?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI stands on 8,800 sq m of land (about 2.2 acres), with 2,231 sq m of sanctioned built-up area and 1,320 sq m of recreational open space.
Where can I read reviews of MARUTI PRAKKRUTI?
Google Maps has reviews of MARUTI PRAKKRUTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MARUTI PRAKKRUTI?
MARUTI PRAKKRUTI by BHAVANA VINOD PATEL is in Ambadi Road, Palghar (pincode 401202), near Vasai West, Diwanman, Chulne, Maharashtra, and is registered on MahaRERA as P99000006293, per GharKundli's check of MahaRERA records.
How many homes are in MARUTI PRAKKRUTI?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI has 30 homes in 32 towers registered on MahaRERA, and 29% of them are sold or booked.
When was MARUTI PRAKKRUTI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MARUTI PRAKKRUTI was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MARUTI PRAKKRUTI?
No court cases are listed for MARUTI PRAKKRUTI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of MARUTI PRAKKRUTI?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BHAVANA VINOD PATEL.
Check it yourself on MahaRERA
- How to check the possession date of MARUTI PRAKKRUTI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Vasai
- VIMALNATH Building no-2
- STAR LEGACY
- REALTECH VALENCIA
- DHANANJAY ICON
- COMFORT AARADHYA
- GULMOHAR HERITAGE BUILDING NO 3 WING E PHASE I
- Acciano Bianca
- SHIVNERI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.