by THIM CONSTRUCTION PVT. LTD. · Fort, PalgharAlso near Satpati, Bassein Road

Possession: SAI BABA RESIDENCY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000011750. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAI BABA RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI BABA RESIDENCY has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT99000010812)

    Reason the builder gave MahaRERA:
    “The application for occupancy certificate from Competent Authority(VVCMC) has been applied on 16/12/2020 but the issue of occupancy certificate is being delayed due to COVID Pandemic. once the occupancy certificate is granted we will intima…” Read the full reason“The application for occupancy certificate from Competent Authority(VVCMC) has been applied on 16/12/2020 but the issue of occupancy certificate is being delayed due to COVID Pandemic. once the occupancy certificate is granted we will intimate to MahaRera. Therefore, we request you to kindly grant extension of project till occupancy certificate is granted so that we could sell our Apartments.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000012119)

    Reason the builder gave MahaRERA: “Due to covid-19 pandemic the demand for the project has been slow down and as a result we are suffering from financial crisis so, we could not complete the project within time hence, we hereby request to grant further extension.”

Source: SAI BABA RESIDENCY’s extension records on MahaRERA (P99000011750), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI BABA RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000011750
Status
Completed
Builder
THIM CONSTRUCTION PVT. LTD.
Location
Fort, Palghar · 401202
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2025
Delay so far
54 months
Homes
114
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SAI BABA RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CORAL100%100%100%100%
EMERALD100%100%100%100%
GARNET100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI BABA RESIDENCY every month.

SAI BABA RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: CORAL (6 floors) · EMERALD (6 floors) · GARNET (6 floors)
  • Land: 3,390 sq m (about 0.8 acres) · sanctioned built-up 4,716 sq m · recreational space 508 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI BABA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI BABA RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI BABA RESIDENCY

What is the possession date of SAI BABA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI BABA RESIDENCY in Fort, Palghar is 31 December 2025 — 54 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI BABA RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI BABA RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2025, already 54 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI BABA RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "The application for occupancy certificate from Competent Authority(VVCMC) has been applied on 16/12/2020 but the issue of occupancy certificate is being delayed due to COVID Pandemic. once the occupancy certificate is granted we will intimate to MahaRera. Therefore, we request you to kindly grant extension of project till occupancy certificate is granted so that we could sell our Apartments."; to 31 December 2025, giving the reason "Due to covid-19 pandemic the demand for the project has been slow down and as a result we are suffering from financial crisis so, we could not complete the project within time hence, we hereby request to grant further extension.".

What is the RERA number of SAI BABA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI BABA RESIDENCY in Fort, Palghar is P99000011750.

Is SAI BABA RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY is registered as P99000011750 and its status is "Completed".

What is the construction status of SAI BABA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does SAI BABA RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAI BABA RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY is registered on MahaRERA as P99000011750, its MahaRERA status is "Completed", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI BABA RESIDENCY's possession date changes?

The latest dates are on SAI BABA RESIDENCY's MahaRERA page (P99000011750). GharKundli's Kundli Watch sends a free WhatsApp update on SAI BABA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI BABA RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY has 3 buildings filed: CORAL with 6 floors; EMERALD with 6 floors; GARNET with 6 floors.

How big is the land of SAI BABA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY stands on 3,390 sq m of land (about 0.8 acres), with 4,716 sq m of sanctioned built-up area and 508 sq m of recreational open space.

Where can I read reviews of SAI BABA RESIDENCY?

Google Maps has reviews of SAI BABA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI BABA RESIDENCY?

SAI BABA RESIDENCY by THIM CONSTRUCTION PVT. LTD. is in Fort, Palghar (pincode 401202), near Satpati, Bassein Road, Maharashtra, and is registered on MahaRERA as P99000011750, per GharKundli's check of MahaRERA records.

How many homes are in SAI BABA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY has 114 homes in 3 towers registered on MahaRERA.

When was SAI BABA RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BABA RESIDENCY was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI BABA RESIDENCY?

No court cases are listed for SAI BABA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI BABA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is THIM CONSTRUCTION PVT. LTD..