THE SCENIC RESIDENCY PHASE I
by Virendra Ramesh Mehta · Mor, Vasai, Palghar
Possession date of THE SCENIC RESIDENCY PHASE I: 30 June 2026, moved from 31 March 2020 (75 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000005001. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about THE SCENIC RESIDENCY PHASE I?
How the possession date of THE SCENIC RESIDENCY PHASE I has moved
31 March 2020
Completion date given when the project was registered
30 March 2021
Extended at the builder's request (MahaRERA application EXT99000005972)
Reason the builder gave MahaRERA:
“• The approvals for additional proposed FSI was not granted by Competent Authority in time and due to this delay we were unable to carry out the work any further. • The construction of structure is complete for the portion of project earlie…” Read the full reason
“• The approvals for additional proposed FSI was not granted by Competent Authority in time and due to this delay we were unable to carry out the work any further. • The construction of structure is complete for the portion of project earlier approved and registered with MahaRERA. • Brick work and plastering for the completed structure is in progress. • The construction of building could not be carried out completely due to sluggish sales in the project. • The construction work for the proposed building is in progress and we are arranging for funds from other sources. • The promoter humbly r…”30 March 2023
Extended at the builder's request (MahaRERA application EXT99000012051)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30-03-2023”
30 June 2026
Extended at the builder's request (MahaRERA application EXT99000025382)
Reason the builder gave MahaRERA: “extension is requested bcoz. we have applied for revised cc for additional FSi , and we need some more time to complete the project to the fullest.”
Source: THE SCENIC RESIDENCY PHASE I’s extension records on MahaRERA (P99000005001), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on THE SCENIC RESIDENCY PHASE I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000005001
- Status
- Lapsed (registration period ended)
- Builder
- Virendra Ramesh Mehta
- Location
- Mor, Vasai, Palghar · 401208
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- March 2020
- Latest completion date
- June 2026
- Delay so far
- 75 months
- Homes
- 40
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of THE SCENIC RESIDENCY PHASE I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 65% | 0% |
| B | 100% | 100% | 65% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A: covers up to ground + 4th upper floors
- B: covers up to ground + 4th upper floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE SCENIC RESIDENCY PHASE I every month.
THE SCENIC RESIDENCY PHASE I: buildings, flats and land, as filed on MahaRERA
- Buildings: A (3 floors, 20 units) · B (3 floors, 20 units)
- Land: 2,100 sq m (about 0.5 acres) · sanctioned built-up 1,060 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of THE SCENIC RESIDENCY PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE SCENIC RESIDENCY PHASE I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE SCENIC RESIDENCY PHASE I
What is the possession date of THE SCENIC RESIDENCY PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE SCENIC RESIDENCY PHASE I in Mor, Vasai, Palghar is 30 June 2026 — 75 months later than 31 March 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for THE SCENIC RESIDENCY PHASE I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE SCENIC RESIDENCY PHASE I's builder has filed on MahaRERA, the official one, is 30 June 2026, already 75 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of THE SCENIC RESIDENCY PHASE I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2021, giving the reason "• The approvals for additional proposed FSI was not granted by Competent Authority in time and due to this delay we were unable to carry out the work any further. • The construction of structure is complete for the portion of project earlier approved and registered with MahaRERA. • Brick work and plastering for the completed structure is in progress. • The construction of building could not be carried out completely due to sluggish sales in the project. • The construction work for the proposed building is in progress and we are arranging for funds from other sources. • The promoter humbly r…"; to 30 March 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30-03-2023"; to 30 June 2026, giving the reason "extension is requested bcoz. we have applied for revised cc for additional FSi , and we need some more time to complete the project to the fullest.".
What is the RERA number of THE SCENIC RESIDENCY PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE SCENIC RESIDENCY PHASE I in Mor, Vasai, Palghar is P99000005001.
Is THE SCENIC RESIDENCY PHASE I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I is registered as P99000005001 and its status is "Lapsed (registration period ended)".
What is the construction status of THE SCENIC RESIDENCY PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does THE SCENIC RESIDENCY PHASE I have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is THE SCENIC RESIDENCY PHASE I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I is registered on MahaRERA as P99000005001, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 75 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if THE SCENIC RESIDENCY PHASE I's possession date changes?
The latest dates are on THE SCENIC RESIDENCY PHASE I's MahaRERA page (P99000005001). GharKundli's Kundli Watch sends a free WhatsApp update on THE SCENIC RESIDENCY PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE SCENIC RESIDENCY PHASE I have?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I has 2 buildings filed: A with 3 floors and 20 units; B with 3 floors and 20 units.
How big is the land of THE SCENIC RESIDENCY PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I stands on 2,100 sq m of land (about 0.5 acres), with 1,060 sq m of sanctioned built-up area.
Where can I read reviews of THE SCENIC RESIDENCY PHASE I?
Google Maps has reviews of THE SCENIC RESIDENCY PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE SCENIC RESIDENCY PHASE I?
THE SCENIC RESIDENCY PHASE I by Virendra Ramesh Mehta is in Mor, Vasai, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000005001, per GharKundli's check of MahaRERA records.
How many homes are in THE SCENIC RESIDENCY PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I has 40 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was THE SCENIC RESIDENCY PHASE I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE SCENIC RESIDENCY PHASE I was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on THE SCENIC RESIDENCY PHASE I?
No court cases are listed for THE SCENIC RESIDENCY PHASE I on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of THE SCENIC RESIDENCY PHASE I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Virendra Ramesh Mehta.
Check it yourself on MahaRERA
- How to check the possession date of THE SCENIC RESIDENCY PHASE I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Palghar →
Other projects in Vasai
- VIMALNATH Building no-2
- STAR LEGACY
- COMFORT AARADHYA
- Acciano Bianca
- DHANANJAY ICON
- REALTECH VALENCIA
- GULMOHAR HERITAGE BUILDING NO 3 WING E PHASE I
- SHIVNERI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.