Mahavir Kanti Regency

by MAHAVIR PROPERTIES · Vasai Road West, Palghar 401202Also near Diwanman, Vasai West, NavgharRegistered on MahaRERA as “KANTI REGENCY”

What’s in the report? →

Possession: Mahavir Kanti Regency (MahaRERA P99000010163) is marked completed on MahaRERA. It has 93 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000010163. Status: Completed.

Source: MahaRERA website — records for P99000010163, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Mahavir Kanti Regency?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mahavir Kanti Regency has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT99000005143)

    Reason the builder gave MahaRERA: “Building Completed 100% in all respects . Fire & Tree NOC obtained from the Competent Authority. Occupancy Certificate not received from Competent Authority.”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: Mahavir Kanti Regency’s extension records on MahaRERA (P99000010163), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mahavir Kanti Regency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000010163
Status
Completed
Builder
MAHAVIR PROPERTIES
Location
Vasai Road West, Palghar · 401202
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
93
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Mahavir Kanti Regency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING - B100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahavir Kanti Regency every 1–2 months.

Mahavir Kanti Regency: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Mahavir Homes (a group of 6 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 11 months); 4 still being built, 4 past the promised date (typically 42 months late). No complaints on MahaRERA.

Read Google reviews of Mahavir Kanti Regency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mahavir Kanti Regency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mahavir Kanti Regency

What is the possession date of Mahavir Kanti Regency?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mahavir Kanti Regency in Vasai Road West, Palghar is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Mahavir Kanti Regency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahavir Kanti Regency's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mahavir Kanti Regency extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "Building Completed 100% in all respects . Fire & Tree NOC obtained from the Competent Authority. Occupancy Certificate not received from Competent Authority.".

What is the RERA number of Mahavir Kanti Regency?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mahavir Kanti Regency in Vasai Road West, Palghar is P99000010163.

Is Mahavir Kanti Regency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency is registered as P99000010163 and its status is "Completed".

What is the current construction status of Mahavir Kanti Regency? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency's status on MahaRERA is "Completed". As filed by the builder, slab work on WING - B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Mahavir Kanti Regency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Mahavir Kanti Regency safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency is registered on MahaRERA as P99000010163, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mahavir Kanti Regency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Mahavir Kanti Regency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Mahavir Kanti Regency: gharkundli.com/tools/property-cost-calculator

Has Mahavir Kanti Regency received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Mahavir Kanti Regency completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency is marked completed on MahaRERA, and the completion date filed there is 30 December 2021. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Mahavir Kanti Regency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Mahavir Kanti Regency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mahavir Kanti Regency's possession date changes?

The latest dates are on Mahavir Kanti Regency's MahaRERA page (P99000010163). GharKundli's Kundli Watch sends a free WhatsApp update on Mahavir Kanti Regency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mahavir Kanti Regency have?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency has one building filed: WING - B with 17 floors.

How big is the land of Mahavir Kanti Regency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency stands on 1,063 sq m of land (about 0.3 acres), with 4,901 sq m of sanctioned built-up area.

What is the track record of Mahavir Kanti Regency's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Homes (a group of 6 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 11 months); 4 still being built, 4 past the promised date (typically 42 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Mahavir Kanti Regency?

Google Maps has reviews of Mahavir Kanti Regency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mahavir Kanti Regency?

Mahavir Kanti Regency by MAHAVIR PROPERTIES is in Vasai Road West, Palghar, pincode 401202 (near Diwanman, Vasai West, Navghar), Maharashtra, and is registered on MahaRERA as P99000010163, per GharKundli's check of MahaRERA records. Its land is filed as S. NO. 70,90,91,96,98,106,108,110,111,112,113. GharKundli lists all 165 MahaRERA projects in Bassein Road (401202).

How many flats are in Mahavir Kanti Regency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency has 93 homes in 1 tower registered on MahaRERA.

When was Mahavir Kanti Regency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahavir Kanti Regency was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Does Mahavir Kanti Regency have any legal issues or court cases?

No court cases are listed for Mahavir Kanti Regency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Mahavir Kanti Regency?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHAVIR PROPERTIES, which has 1 other project registered on MahaRERA.

Other projects in Bassein Road (401202)

All 165 projects in Bassein Road (401202) →

Other projects by MAHAVIR PROPERTIES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.