by RSN BALAJI REALTORS P LTD · Near Jain Mandir, MumbaiAlso near Santacruz East, Vakola, Andheri

Possession date of VAIBHAV HEIGHTS: 30 April 2027, moved from 31 December 2018 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002862, and currently active. Its completion date has moved from December 2018 to April 2027: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VAIBHAV HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VAIBHAV HEIGHTS has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800000915)

    Reason the builder gave MahaRERA:
    “Due to awaiting implementation of DCPR 2034 and road TDR policy in connection to DCPR 2034, no file was being processed by MCGM for concession and issue of further CC. Thus due to non issuance of permission by the authority the project was…” Read the full reason“Due to awaiting implementation of DCPR 2034 and road TDR policy in connection to DCPR 2034, no file was being processed by MCGM for concession and issue of further CC. Thus due to non issuance of permission by the authority the project was not completed on time. The said permission is now seeked into by applying for the same to MCGM after implementation of DCPR 2034. Thus we request for an extension till Dec 2019.”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800003750)

    Reason the builder gave MahaRERA:
    “1) Ours is an ongoing project on land bearing CTS No. 3929 to 3949 proposed for 14th floors. We have completed work up till 12th floor having achieved height of 42.83 AMSL. We are applying for part OC upto 12th Floor. 2) We received NOC fro…” Read the full reason“1) Ours is an ongoing project on land bearing CTS No. 3929 to 3949 proposed for 14th floors. We have completed work up till 12th floor having achieved height of 42.83 AMSL. We are applying for part OC upto 12th Floor. 2) We received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014 with sanctioned height of 50.50 AMSL valid for 5 years. 3) Thus we had applied to (AAI) for Revalidation of our NOC for further 3 years. To our surprise they have replied that “no construction work has commenced within the coordinates mentioned in the NO…”
  4. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51800006381)

    Reason the builder gave MahaRERA:
    “Due to Promoters RSN Balaji Realtors has received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014. This NOC is firstly issued for 5 (five) years, and then it can be further exten…” Read the full reason“Due to Promoters RSN Balaji Realtors has received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014. This NOC is firstly issued for 5 (five) years, and then it can be further extended for 3 (three) years. And the Promoter has applied to (AAI) for Revalidation of NOC for further 3 years. This is expected to get very soon. As per the new DCPR 2034, new widening of RL road from 12.20 mtrs. to 18.30 mtrs. on the existing C S M Road, and the same is under EP (excluded portion). Which is supposed to be sanctioned under s/c 30 .”
  5. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018202)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2024”
  6. 30 December 2026

    Extended at the builder's request (MahaRERA application EXT51800025455)

    Reason the builder gave MahaRERA:
    “The Project was Delay Due to awaiting implementation of DCPR 2034 and road policy in connection to DCPR 2034 and also because of getting Revalidations of NOC from civil aviation authority. The Plot was affected by road set back from both si…” Read the full reason“The Project was Delay Due to awaiting implementation of DCPR 2034 and road policy in connection to DCPR 2034 and also because of getting Revalidations of NOC from civil aviation authority. The Plot was affected by road set back from both side i.e back and front, therefore it took long to handover the road set back to both the DP department and RL department separately”
  7. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VAIBHAV HEIGHTS’s extension records on MahaRERA (P51800002862), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VAIBHAV HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002862
Status
Registered and active
Builder
RSN BALAJI REALTORS P LTD
Location
Near Jain Mandir, Mumbai · 400055
Project type
Residential / Group Housing
Registered on
4 Aug 2017
Completion date at registration
December 2018
Latest completion date
April 2027
Delay so far
96 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
48
Sold or booked
100%
Towers
2
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of VAIBHAV HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING CHOKSI APT REHAB100%100%100%95%
B WING VAIBHAV HEIGHTS100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • A WING CHOKSI APT REHAB: covers 14 th floor
  • B WING VAIBHAV HEIGHTS: covers 14 th floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VAIBHAV HEIGHTS every month.

VAIBHAV HEIGHTS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK662 – 77227
1 BHK49812
Multi Purpose Room181 – 3259
Shops235 – 2604
  • Buildings: A WING CHOKSI APT REHAB (15 floors, 9 units) · B WING VAIBHAV HEIGHTS (15 floors, 43 units)
  • Car parking: 47 covered
  • Land: 1,387 sq m (about 0.3 acres) · sanctioned built-up 3,589 sq m · recreational space 202 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VAIBHAV HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VAIBHAV HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VAIBHAV HEIGHTS

What is the possession date of VAIBHAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VAIBHAV HEIGHTS in Near Jain Mandir, Mumbai is 30 April 2027 — 96 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VAIBHAV HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VAIBHAV HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 96 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VAIBHAV HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS's builder applied to MahaRERA to extend the completion date 5 times: to 30 April 2020, giving the reason "Due to awaiting implementation of DCPR 2034 and road TDR policy in connection to DCPR 2034, no file was being processed by MCGM for concession and issue of further CC. Thus due to non issuance of permission by the authority the project was not completed on time. The said permission is now seeked into by applying for the same to MCGM after implementation of DCPR 2034. Thus we request for an extension till Dec 2019."; to 30 April 2020, giving the reason "1) Ours is an ongoing project on land bearing CTS No. 3929 to 3949 proposed for 14th floors. We have completed work up till 12th floor having achieved height of 42.83 AMSL. We are applying for part OC upto 12th Floor. 2) We received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014 with sanctioned height of 50.50 AMSL valid for 5 years. 3) Thus we had applied to (AAI) for Revalidation of our NOC for further 3 years. To our surprise they have replied that “no construction work has commenced within the coordinates mentioned in the NO…"; to 30 June 2023, giving the reason "Due to Promoters RSN Balaji Realtors has received NOC from Airport Authority of India (AAI), vide their letter no. BT-1/NOC/ CS/MUM/13/NOCAS/391 dated 9/5/2014. This NOC is firstly issued for 5 (five) years, and then it can be further extended for 3 (three) years. And the Promoter has applied to (AAI) for Revalidation of NOC for further 3 years. This is expected to get very soon. As per the new DCPR 2034, new widening of RL road from 12.20 mtrs. to 18.30 mtrs. on the existing C S M Road, and the same is under EP (excluded portion). Which is supposed to be sanctioned under s/c 30 ."; to 31 December 2024, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2024"; to 30 December 2026, giving the reason "The Project was Delay Due to awaiting implementation of DCPR 2034 and road policy in connection to DCPR 2034 and also because of getting Revalidations of NOC from civil aviation authority. The Plot was affected by road set back from both side i.e back and front, therefore it took long to handover the road set back to both the DP department and RL department separately". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VAIBHAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VAIBHAV HEIGHTS in Near Jain Mandir, Mumbai is P51800002862.

Is VAIBHAV HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS is registered as P51800002862 and its status is "Registered and active".

What is the construction status of VAIBHAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does VAIBHAV HEIGHTS have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is VAIBHAV HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS is registered on MahaRERA as P51800002862, its completion date has moved 96 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VAIBHAV HEIGHTS's possession date changes?

The latest dates are on VAIBHAV HEIGHTS's MahaRERA page (P51800002862). GharKundli's Kundli Watch sends a free WhatsApp update on VAIBHAV HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VAIBHAV HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS has 2 buildings filed: A WING CHOKSI APT REHAB with 15 floors and 9 units; B WING VAIBHAV HEIGHTS with 15 floors and 43 units.

What are the flat sizes (carpet area) in VAIBHAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for VAIBHAV HEIGHTS: 2 BHK: 662 to 772 sq ft carpet (27 homes); 1 BHK: 498 sq ft carpet (12 homes); Multi Purpose Room: 181 to 325 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does VAIBHAV HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 47 covered car parking spaces for VAIBHAV HEIGHTS.

How big is the land of VAIBHAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS stands on 1,387 sq m of land (about 0.3 acres), with 3,589 sq m of sanctioned built-up area and 202 sq m of recreational open space.

Where can I read reviews of VAIBHAV HEIGHTS?

Google Maps has reviews of VAIBHAV HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VAIBHAV HEIGHTS?

VAIBHAV HEIGHTS by RSN BALAJI REALTORS P LTD is in Near Jain Mandir, Mumbai (pincode 400055), near Santacruz East, Vakola, Andheri, Maharashtra, and is registered on MahaRERA as P51800002862, per GharKundli's check of MahaRERA records.

How many homes are in VAIBHAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS has 48 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.

When was VAIBHAV HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VAIBHAV HEIGHTS was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VAIBHAV HEIGHTS?

No court cases are listed for VAIBHAV HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VAIBHAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RSN BALAJI REALTORS P LTD.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Andheri

All 112 projects in Santacruz East (400055) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.