Skip to content
GharKundli

Paramount Heights

by M/s Zion Constructions · Vasai West, PalgharAlso near Chulne, Bassein Road

Possession: Paramount Heights is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000010275. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Paramount Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Paramount Heights has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT99000009644)

    Reason the builder gave MahaRERA:
    “To The respected MAHARERA Authority, Maharashtra State. Sir, We humbly submit as under: 1. The RERA Registration Certificate bearing registration Number P99000010275 dated 18 May 2020, commencing from 24 August 2017 in respect of our projec…” Read the full reason“To The respected MAHARERA Authority, Maharashtra State. Sir, We humbly submit as under: 1. The RERA Registration Certificate bearing registration Number P99000010275 dated 18 May 2020, commencing from 24 August 2017 in respect of our project- Paramount Heights is getting over/expired on 30 June 2021. 2. Owing to the delay caused by the competent authority in approving our revised development plan, the construction was stopped for some time. Thereafter, because of the Covid 19 Pandemic, during the Lockdown imposed by the Central Government we could carry on with the construction with only li…”
  3. 29 June 2023

    Extended at the builder's request (MahaRERA application EXT99000013444)

    Reason the builder gave MahaRERA:
    “To Tha MAHARERA Authority, Mumbai Maharashtra, Kindly allow our application for Second extension of our above project from 31st December, 2022 to 29th June, 2023. Although we tried completing our above project by the date of completion as w…” Read the full reason“To Tha MAHARERA Authority, Mumbai Maharashtra, Kindly allow our application for Second extension of our above project from 31st December, 2022 to 29th June, 2023. Although we tried completing our above project by the date of completion as was permitted by Maharera vide the extension application granted by Maharera vide its Certificate dated 09/09/2021, we have not yet received Occupation Certificate from the Municipal Corporation. Vide Application dated 30th November, 2022, on our behalf, Mr. Sanjay Narang has submitted application to VVCMC for grant of Occupation Certificate. Further, vide…”

Source: Paramount Heights’s extension records on MahaRERA (P99000010275), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Paramount Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000010275
Status
Completed
Builder
M/s Zion Constructions
Location
Vasai West, Palghar · 401202
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
June 2021
Latest completion date
June 2023
Delay so far
24 months
Homes
81
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of Paramount Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Bldg No 1100%100%80%60%
Bldg No 20%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Paramount Heights every month.

Paramount Heights: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Paramount Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Paramount Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Paramount Heights

What is the possession date of Paramount Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Paramount Heights in Vasai West, Palghar is 29 June 2023 — 24 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Paramount Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Paramount Heights's builder has filed on MahaRERA, the official one, is 29 June 2023, already 24 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Paramount Heights extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "To The respected MAHARERA Authority, Maharashtra State. Sir, We humbly submit as under: 1. The RERA Registration Certificate bearing registration Number P99000010275 dated 18 May 2020, commencing from 24 August 2017 in respect of our project- Paramount Heights is getting over/expired on 30 June 2021. 2. Owing to the delay caused by the competent authority in approving our revised development plan, the construction was stopped for some time. Thereafter, because of the Covid 19 Pandemic, during the Lockdown imposed by the Central Government we could carry on with the construction with only li…"; to 29 June 2023, giving the reason "To Tha MAHARERA Authority, Mumbai Maharashtra, Kindly allow our application for Second extension of our above project from 31st December, 2022 to 29th June, 2023. Although we tried completing our above project by the date of completion as was permitted by Maharera vide the extension application granted by Maharera vide its Certificate dated 09/09/2021, we have not yet received Occupation Certificate from the Municipal Corporation. Vide Application dated 30th November, 2022, on our behalf, Mr. Sanjay Narang has submitted application to VVCMC for grant of Occupation Certificate. Further, vide…".

What is the RERA number of Paramount Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Paramount Heights in Vasai West, Palghar is P99000010275.

Is Paramount Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights is registered as P99000010275 and its status is "Completed".

What is the construction status of Paramount Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Paramount Heights have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Paramount Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights is registered on MahaRERA as P99000010275, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Paramount Heights's possession date changes?

The latest dates are on Paramount Heights's MahaRERA page (P99000010275). GharKundli's Kundli Watch sends a free WhatsApp update on Paramount Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Paramount Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights has 2 buildings filed: Bldg No 1 with 21 floors; Bldg No 2 with 6 floors.

How big is the land of Paramount Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights stands on 2,510 sq m of land (about 0.6 acres), with 1,961 sq m of sanctioned built-up area and 251 sq m of recreational open space.

Where can I read reviews of Paramount Heights?

Google Maps has reviews of Paramount Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Paramount Heights?

Paramount Heights by M/s Zion Constructions is in Vasai West, Palghar (pincode 401202), near Chulne, Bassein Road, Maharashtra, and is registered on MahaRERA as P99000010275, per GharKundli's check of MahaRERA records.

How many homes are in Paramount Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights has 81 homes in 2 towers registered on MahaRERA.

When was Paramount Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Paramount Heights was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Paramount Heights?

No court cases are listed for Paramount Heights on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Paramount Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s Zion Constructions.

Other projects in pincode 401202

All 93 projects in Bassein Road (401202) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.