Skyi Wild Woods Phase I
by Enerrgia Skyi Ventures · Wanjalewadi, Pune
Possession date of Skyi Wild Woods Phase I: 30 November 2027, moved from 31 July 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100000763, and currently active. Its completion date has moved from July 2022 to November 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Skyi Wild Woods Phase I?
How the possession date of Skyi Wild Woods Phase I has moved
31 July 2022
Completion date given when the project was registered
31 July 2027
Extended at the builder's request (MahaRERA application EXT52100012346)
Reason the builder gave MahaRERA:
“The Project “Skyi Wild Woods Phase I” is located outside from the City of Pune in the Village Wanjalewadi, Taluka Haveli, Dist Pune. The Village Wanjalewadi falls under a substantial rainfall area. In the year 2019-2022, we have experienced…” Read the full reason
“The Project “Skyi Wild Woods Phase I” is located outside from the City of Pune in the Village Wanjalewadi, Taluka Haveli, Dist Pune. The Village Wanjalewadi falls under a substantial rainfall area. In the year 2019-2022, we have experienced unprecedented rainfall leading to severe flood situation, which derailed construction activities. We kindly request you to extend the project Completion date from 31/07/2022 to 31/07/2032. Having requested this, we are confident that the project would be completed on or before our new proposed completion date.”30 November 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Skyi Wild Woods Phase I’s extension records on MahaRERA (P52100000763), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Skyi Wild Woods Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100000763
- Status
- Registered and active
- Builder
- Enerrgia Skyi Ventures
- Location
- Wanjalewadi, Pune · 411023
- Project type
- Plotted
- Registered on
- 23 Jul 2017
- Completion date at registration
- July 2022
- Latest completion date
- November 2027
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Skyi Wild Woods Phase I: buildings, flats and land, as filed on MahaRERA
- Land: 2,04,807 sq m (about 50.6 acres) · sanctioned built-up 1,27,743 sq m
The builder’s record and reviews
Enerrgia Skyi Developers (a group of 8 linked companies) has 48 projects on MahaRERA since 2019, this one included. Of the 29 GharKundli has checked: 1 finished, all within the promised date; 22 still being built, 3 past the promised date (typically 3 months late); 6 lapsed. 19 complaints on MahaRERA across 9 projects.
Read Google reviews of Skyi Wild Woods Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Skyi Wild Woods Phase I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Skyi Wild Woods Phase I
What is the possession date of Skyi Wild Woods Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Skyi Wild Woods Phase I in Wanjalewadi, Pune is 30 November 2027 — 60 months later than 31 July 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Skyi Wild Woods Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Skyi Wild Woods Phase I's builder has filed on MahaRERA, the official one, is 30 November 2027, already 60 months later than the 31 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Skyi Wild Woods Phase I extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Wild Woods Phase I's builder applied to MahaRERA to extend the completion date once: to 31 July 2027, giving the reason "The Project “Skyi Wild Woods Phase I” is located outside from the City of Pune in the Village Wanjalewadi, Taluka Haveli, Dist Pune. The Village Wanjalewadi falls under a substantial rainfall area. In the year 2019-2022, we have experienced unprecedented rainfall leading to severe flood situation, which derailed construction activities. We kindly request you to extend the project Completion date from 31/07/2022 to 31/07/2032. Having requested this, we are confident that the project would be completed on or before our new proposed completion date.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Skyi Wild Woods Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Skyi Wild Woods Phase I in Wanjalewadi, Pune is P52100000763.
Is Skyi Wild Woods Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Wild Woods Phase I is registered as P52100000763 and its status is "Registered and active".
What is the construction status of Skyi Wild Woods Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Wild Woods Phase I's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Skyi Wild Woods Phase I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Skyi Wild Woods Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Wild Woods Phase I is registered on MahaRERA as P52100000763, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Skyi Wild Woods Phase I's possession date changes?
The latest dates are on Skyi Wild Woods Phase I's MahaRERA page (P52100000763). GharKundli's Kundli Watch sends a free WhatsApp update on Skyi Wild Woods Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Skyi Wild Woods Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Wild Woods Phase I stands on 2,04,807 sq m of land (about 50.6 acres), with 1,27,743 sq m of sanctioned built-up area.
What is the track record of Skyi Wild Woods Phase I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Enerrgia Skyi Developers (a group of 8 linked companies) has 48 projects on MahaRERA since 2019, this one included. Of the 29 GharKundli has checked: 1 finished, all within the promised date; 22 still being built, 3 past the promised date (typically 3 months late); 6 lapsed. 19 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Skyi Wild Woods Phase I?
Google Maps has reviews of Skyi Wild Woods Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Skyi Wild Woods Phase I?
Skyi Wild Woods Phase I by Enerrgia Skyi Ventures is in Wanjalewadi, Pune (pincode 411023), Maharashtra, and is registered on MahaRERA as P52100000763, per GharKundli's check of MahaRERA records.
When was Skyi Wild Woods Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Wild Woods Phase I was registered on MahaRERA on 23 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Skyi Wild Woods Phase I?
No court cases are listed for Skyi Wild Woods Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Skyi Wild Woods Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Enerrgia Skyi Ventures, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Skyi Wild Woods Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Haveli
- QUE 101 PHASE I
- MADHUGHAT
- CULLINAN
- SIDDHI AURUM
- ATS - THE CONDOMINIUMS
- DYNAMIC SOLITAIRE – PHASE II
- BALWANT EMPIRE
- SnehKunj
Other projects by Enerrgia Skyi Ventures
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.