by RAFIK AKBAR MULLA · Tingre Nagar, Pune

Possession: SHREE DREAMS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100001844. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SHREE DREAMS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE DREAMS has moved

  1. 25 February 2020

    Completion date given when the project was registered

  2. 24 February 2021

    Extended at the builder's request (MahaRERA application EXT52100005848)

    Reason the builder gave MahaRERA:
    “Due to recession in current market bookings of the flats was not completed and the stage wise amount receivable from flat holders are not received during regular stages due to their personal problems. Hence the project loan has been availed…” Read the full reason“Due to recession in current market bookings of the flats was not completed and the stage wise amount receivable from flat holders are not received during regular stages due to their personal problems. Hence the project loan has been availed from Bank . Due to such various reasons project has been delayed.”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52100011474)

    Reason the builder gave MahaRERA:
    “Due to Covid 19 construction activities were held up and manpower were not available for construction work . Also for occupancy certificate application was made on 24/8/2021 with PMRDA Authority but still occupancy certificate was not recei…” Read the full reason“Due to Covid 19 construction activities were held up and manpower were not available for construction work . Also for occupancy certificate application was made on 24/8/2021 with PMRDA Authority but still occupancy certificate was not received due to some technical issues with PMRDA Authority and Revenue Authorities. Acknowledgment of application dated 24/8/21 attached herewith . Now completition certificate for B wing attached .”
  4. 31 August 2023

    Extended at the builder's request (MahaRERA application EXT52100013589)

    Reason the builder gave MahaRERA:
    “Dear Sir, We received OC of Wing B on 11-03-2022, however, due to documentation and paperwork mentioned below, we were unable to complete Wing A of the project Shree Dreams well before 31-12-2022. The reasons are mentioned as below: 1. I su…” Read the full reason“Dear Sir, We received OC of Wing B on 11-03-2022, however, due to documentation and paperwork mentioned below, we were unable to complete Wing A of the project Shree Dreams well before 31-12-2022. The reasons are mentioned as below: 1. I submitted an application for 'Taba Yadi' in PMRDA on 06-10-2022, but the further operational process at PMRDA took time which ultimately resulted in lowering down the construction of Wing A of the project. 2. I received documents from the Tahsildar office, Shirur, Pune on 10-02-2022. This created delay in submitting the documents to the Talathi office for N…”
  5. 30 April 2024

    Extended at the builder's request (MahaRERA application EXT52100017709)

    Reason the builder gave MahaRERA:
    “Respected Sir, I/ We the promoter RAFIK AKBAR MULLA for Chandan Constructions does hereby apply for the project extension for the following reasons- 1. We received the occupancy certificate of Wing ‘B’ on 11-03-2022. We are hereby requestin…” Read the full reason“Respected Sir, I/ We the promoter RAFIK AKBAR MULLA for Chandan Constructions does hereby apply for the project extension for the following reasons- 1. We received the occupancy certificate of Wing ‘B’ on 11-03-2022. We are hereby requesting a further extension to complete and hand over wing 'A’ of the project. 2. We obtained documents from Tahsildar office Shirur Pune on 10-02-2022. This created a delay in submitting the documents to the Talathi office for NA purposes. This submission took place on 10-02-2022. The further process tnok time. This is one of the reasons resulting in a delay i…”

Source: SHREE DREAMS’s extension records on MahaRERA (P52100001844), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE DREAMS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100001844
Status
Completed
Builder
RAFIK AKBAR MULLA
Location
Tingre Nagar, Pune · 412208
Project type
Residential / Group Housing
Registered on
29 Jul 2017
Completion date at registration
February 2020
Latest completion date
April 2024
Delay so far
50 months
Homes
80
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHREE DREAMS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE DREAMS BLDG A100%100%100%100%
SHREE DREAMS BLDG B100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE DREAMS every month.

SHREE DREAMS: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREE DREAMS BLDG A (7 floors) · SHREE DREAMS BLDG B (7 floors)
  • Land: 3,100 sq m (about 0.8 acres) · sanctioned built-up 2,713 sq m · recreational space 3,100 sq m
  • Boundaries filed include: Talegaon Dhamdhere-Sanawawadi Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREE DREAMS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE DREAMS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE DREAMS

What is the possession date of SHREE DREAMS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREE DREAMS in Tingre Nagar, Pune is 30 April 2024 — 50 months later than 25 February 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHREE DREAMS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE DREAMS's builder has filed on MahaRERA, the official one, is 30 April 2024, already 50 months later than the 25 February 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE DREAMS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS's builder applied to MahaRERA to extend the completion date 4 times: to 24 February 2021, giving the reason "Due to recession in current market bookings of the flats was not completed and the stage wise amount receivable from flat holders are not received during regular stages due to their personal problems. Hence the project loan has been availed from Bank . Due to such various reasons project has been delayed."; to 31 December 2022, giving the reason "Due to Covid 19 construction activities were held up and manpower were not available for construction work . Also for occupancy certificate application was made on 24/8/2021 with PMRDA Authority but still occupancy certificate was not received due to some technical issues with PMRDA Authority and Revenue Authorities. Acknowledgment of application dated 24/8/21 attached herewith . Now completition certificate for B wing attached ."; to 31 August 2023, giving the reason "Dear Sir, We received OC of Wing B on 11-03-2022, however, due to documentation and paperwork mentioned below, we were unable to complete Wing A of the project Shree Dreams well before 31-12-2022. The reasons are mentioned as below: 1. I submitted an application for 'Taba Yadi' in PMRDA on 06-10-2022, but the further operational process at PMRDA took time which ultimately resulted in lowering down the construction of Wing A of the project. 2. I received documents from the Tahsildar office, Shirur, Pune on 10-02-2022. This created delay in submitting the documents to the Talathi office for N…"; to 30 April 2024, giving the reason "Respected Sir, I/ We the promoter RAFIK AKBAR MULLA for Chandan Constructions does hereby apply for the project extension for the following reasons- 1. We received the occupancy certificate of Wing ‘B’ on 11-03-2022. We are hereby requesting a further extension to complete and hand over wing 'A’ of the project. 2. We obtained documents from Tahsildar office Shirur Pune on 10-02-2022. This created a delay in submitting the documents to the Talathi office for NA purposes. This submission took place on 10-02-2022. The further process tnok time. This is one of the reasons resulting in a delay i…".

What is the RERA number of SHREE DREAMS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREE DREAMS in Tingre Nagar, Pune is P52100001844.

Is SHREE DREAMS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS is registered as P52100001844 and its status is "Completed".

What is the construction status of SHREE DREAMS?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does SHREE DREAMS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHREE DREAMS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS is registered on MahaRERA as P52100001844, its MahaRERA status is "Completed", its completion date has moved 50 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE DREAMS's possession date changes?

The latest dates are on SHREE DREAMS's MahaRERA page (P52100001844). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE DREAMS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE DREAMS have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS has 2 buildings filed: SHREE DREAMS BLDG A with 7 floors; SHREE DREAMS BLDG B with 7 floors.

How big is the land of SHREE DREAMS?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS stands on 3,100 sq m of land (about 0.8 acres), with 2,713 sq m of sanctioned built-up area and 3,100 sq m of recreational open space.

Where can I read reviews of SHREE DREAMS?

Google Maps has reviews of SHREE DREAMS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE DREAMS?

SHREE DREAMS by RAFIK AKBAR MULLA is in Tingre Nagar, Pune (pincode 412208), Maharashtra, and is registered on MahaRERA as P52100001844, per GharKundli's check of MahaRERA records. Its boundaries filed there include Talegaon Dhamdhere-Sanawawadi Road.

How many homes are in SHREE DREAMS?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS has 80 homes in 2 towers registered on MahaRERA.

When was SHREE DREAMS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHREE DREAMS was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE DREAMS?

No court cases are listed for SHREE DREAMS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHREE DREAMS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAFIK AKBAR MULLA.